National Civil Service League v. United States

643 F.2d 768, 28 Cont. Cas. Fed. 81,100, 226 Ct. Cl. 478, 1981 U.S. Ct. Cl. LEXIS 98
CourtUnited States Court of Claims
DecidedFebruary 25, 1981
DocketNo. 330-79C
StatusPublished
Cited by4 cases

This text of 643 F.2d 768 (National Civil Service League v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Civil Service League v. United States, 643 F.2d 768, 28 Cont. Cas. Fed. 81,100, 226 Ct. Cl. 478, 1981 U.S. Ct. Cl. LEXIS 98 (cc 1981).

Opinion

SKELTON, Senior Judge,

delivered the opinion of the court:

This is an appeal by the National Civil Service League (Appellant) for a review under the standards of the Wunderlich Act (41 U.S.C. §§321-322) of a decision of the Department of Housing and Urban Development Board of Contract Appeals (HUDBCA or the Board) which affirmed a denial by a contracting officer of Appellant’s claim for a cost overrun reimbursement it incurred as a contractor in the performance of contract No. H-1092 between it and the Department of Housing and Urban Development (HUD).

The basic facts giving rise to this case are set forth in the opinion of the Board in HUDBCA No. 76-23, September 19, 1978, which we repeat, as follows:

STATEMENT OF FACTS

Appellant is a non-profit corporation, seeking to improve federal, state, and local civil service policies. On June 27, Í969, Appellant contracted with the Department of Housing and Urban Development (hereinafter HUD or the Government) to provide technical assistance and reports in connection with the Model Cities Program. The contract was awarded on a cost-no-fee basis, and contained the standard cost reimbursement clauses including the Allowable Cost, Fixed Fee and Payment, and Limitation of Cost articles prescribed by the Federal Procurement Regulations. Provisional overhead rates were established during negotiations with actual rates to be adjusted after each fiscal year.

Performance of the original agreement was to be complete within thirteen months of the effective date of the contract, and total allowable direct and indirect costs were estimated not to exceed $200,000. On July 27,1970, certain additional tasks were added and the total estimated cost was adjusted to $220,000 (Modification No. 1). Until that [480]*480date, Appellant was being paid from HUD funds allocated to the Model Cities Program. In June, 1970, HÜD entered into, a transfer of funds agreement with the Department of Labor. After execution of this agreeihent, the contract between HUD and the Appellant was modified five more times. These amendments ultimately extended the period for contract performance to June 30, 1974, and substantially increased the total estimated contract amount to $1,583,351, including a fixed fee of $59,300. Funding of these amendments was derived from the transfer of monies pursuant to the agreement with the Department of Labor.

Amendment No. 5 to the contract executed on June 27, 1973, inserted the following language:

"Whereas, it is the intent of the parties to amend this contract to provide a ceiling amount and any costs exceeding the ceiling amount are to be borne by the Contractor solely . . .
3. Article III, Extimated Cost, Fixed Fee and Payment, is amended by . . . adding ¿ new Paragraph A and amending B as follows:
A. Notwithstanding any rights the Contractor may have under any portion or portions of this contract, the Contractor agrees to complete all work required by this contract and that he shall [be] reimbursed for allowable costs up to a ceiling amount which is the total amount contained in Block 21 of the face page. Iri the event that actual allowable costs are below the ceiling amount the Contractor shall be reimbursed for such actual allowable costs.”

The estimated total cost of the contract was increased by that amendment to $1,495,351. The testimony indicated that the ceiling was imposed because Appellant was experiencing steadily increasing overhead rates, several overruns had already occurred, and HUD wanted to avoid any obligation over and above the funds transferred from the Department of Labor. Because of delays caused by some of the local offices in the Model Cities Program, Appellant was unable to complete its contractual obligations within the prescribed ceiling. Consequently, an additional amendment was requested for an increase of $88,000 in the ceiling price, and Appellant indicated at that time that the additional [481]*481funding would be "the final amount necessary to complete the previously referenced contract tasks.” The request was granted, and on May 7, 1974, Modification No. 6 to the contract was executed. The amendment increased the ceiling price to $1,583,351, and restated without change the language forbidding reimbursement of costs incurred in excess of that amount.

Performance of the contract was completed on June 30, 1974, and the work product was described as "excellent” by the Government Technical Representative. Appellant’s final payment voucher, which was submitted on June 30, 1975, indicated that total expenditures including the fixed fee were $1,583,970.27, which exceeded the contractually set ceiling by $619.27. The voucher was based on a 55.7% overhead rate' for fiscal years 1973 and 1974, the provisional rate established by Modification Np. 5. ,

A post-contract audit was conducted by the Government in November, 1975. The Government auditor found that $6,790.98 of the claimed direct costs were questionable, and that actual expenditures on overhead exceeded the provisional amount by $32,439.18. The auditor concluded that the actjial overhead rates for fiscal years 1973 and 1974 were 60.9% find 81.6%, respectively. The auditor testified that Appellant’s accounting system was adequate to record and support costs allocable to the contract on a historical basis, and that it should have become aware that the provisional overhead rate was too low after three months of consecutive overruns. Consequently, Appellant should have discovered t|ie 1973 overrun when the final figures were posted shortly after the close of the fiscal year in January, 1974. The actual 1974 overhead rate did not fcegin exceeding the provisional rate, however, until June of 1974 with a steady increase in the actual rate throughout the remainder of the year. Therefore, Appellant did not have actual knowledge of the 1974 overrun until several months after it completed performance of the contract on June 30, 1974.

The Board also described the contentions of the parties in the following language.

[482]*482 POSITION OF THE PARTIES

The Government contends that reimbursement for any additional costs is barred by the ceiling provision in Article III of the contract. Even if the ceiling amount is not controlling, the Government argues that Appellant failed to give timely notice of an impending overrun within the meaning of the Limitation of Cost Clause and therefore is barred from recovery.

Appellant raises a number of arguments to avoid a strict application of the ceiling. It contends that:

1) The Government waived the ceiling limitation by its "acquiescence or inducement to NCSL to continue work.”
2) The Government was obligated to fund the overrun, since it was proximately caused by the "administrative actions and inactions of the Contracting Officer and his representatives.”
3) The ceiling language should be rescinded because it was the product of a mutual mistake, i.e., reliance on the provisional overhead rate.

Even if the ceiling limitation is upheld, Appellant contends that the Limitation of Cost clause authorizes payment of the overrun.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

APTIM Federal Services, LLC
Armed Services Board of Contract Appeals, 2020
Round Place, Inc. v. United States
39 Cont. Cas. Fed. 76,699 (Federal Claims, 1994)
Maitland Bros. v. United States
36 Cont. Cas. Fed. 75,835 (Court of Claims, 1990)
C & L Construction Co. v. United States
32 Cont. Cas. Fed. 73,102 (Court of Claims, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
643 F.2d 768, 28 Cont. Cas. Fed. 81,100, 226 Ct. Cl. 478, 1981 U.S. Ct. Cl. LEXIS 98, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-civil-service-league-v-united-states-cc-1981.