General Electric Company, a Corporation v. The United States

440 F.2d 420, 194 Ct. Cl. 678, 1971 U.S. Ct. Cl. LEXIS 120
CourtUnited States Court of Claims
DecidedApril 16, 1971
Docket503-69
StatusPublished
Cited by11 cases

This text of 440 F.2d 420 (General Electric Company, a Corporation v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Electric Company, a Corporation v. The United States, 440 F.2d 420, 194 Ct. Cl. 678, 1971 U.S. Ct. Cl. LEXIS 120 (cc 1971).

Opinion

*421 COLLINS, Judge.

This case arose from a cost overrun under a contract between plaintiff and defendant’s Department of the Army. The relevant facts were stipulated in proceedings before the Armed Services Board of Contract Appeals.

Plaintiff, General Electric, and defendant entered into the contract involved in this ease on September 19, 1963. The contract, which involved research and development work relative to a chemieal/biological warning system, was negotiated and was of the cost-plus-incentive-fee variety. All work under the contract was required to be completed by May 31, 1964. The final report was received by the Government project manager, in time, on June 8, 1964.

At the outset, the amount of the contract, including target fee, was $800,000. The contract was amended, however, at a later time to increase the total amount, including target fee, to $835,800. The incentive formula provided for a 15-cent increase in the target fee for every dollar by which allowable costs fell short of the target cost and for a 15-cent reduction in the target fee for every dollar by which allowable costs exceeded the target cost.

The contract provided that allowable costs would include, among other things:

2. Indirect Costs: Allowances for indirect costs, including independent research and development, not otherwise reimbursable as a direct charge hereunder, at such provisional billing rates as may be acceptable to the Contracting Officer. It is understood and agreed that such rates shall be provisional rates for billing purposes only and shall be subject to negotiations and revision to the final negotiated indirect cost rates, based upon Government audit of the Contractor’s books and records on a fiscal year basis ending 31 December of each year, and in accordance with the terms of the General Provision of this contract, entitled “Negotiated Overhead Rates.”

Also included in the contract was the standard Negotiated Overhead Rates clause which provided that allowable indirect costs under the contract would be arrived at by the use of negotiated overhead rates, and furthermore:

(d) The results of each negotiation shall be set forth in a modification to this contract, which shall specify (i) the agreed final rates, (ii) the bases to which the rates apply, and (iii) the periods for which the rates apply.
(e) Pending establishment of final overhead rates for any period, the Contractor shall be reimbursed either at negotiated provisional rates as provided in the Schedule or at billing rates acceptable to the Contracting Officer, subject to appropriate adjustment when the final rates for that period are established. To prevent substantial over or under payment, the provisional or billing rates may, at the request of either party, be revised by mutual agreement, either retroactively or prospectively. Any such revision of negotiated provisional rates provided in the Schedule shall be set forth in a modification to this contract.

Pursuant to ASPR § 3.706, 1 the military departments maintained at the time *422 of this contract an inter-service committee, commonly referred to as the TriServices Committee, which negotiated final overhead rates with contractors having cost-reimbursement type contracts with more than one military department. The ASPR section provided that, after a determination of final overhead rates by the Tri-Services Committee, “[e]ach Military Department shall thereupon amend or supplement the affected contracts in accordance with the rates and other data set forth in the negotiation report or summary.” 2

For the calendar year 1963 the provisional billing rates applicable to the contract were as follows:

Engineering, Drafting & Labor__________133.0%
Independent Research & Development______ 1.8%
General & Administrative ______________ 11.7%

Final overhead rates for 1963 were negotiated in 1965 and were incorporated into the contract by the contracting officer on May 2, 1966. The final rates were as follows:

Engineering, Drafting & Labor__________139.7%
Independent Research & Development______ 1.8%
General & Administrative ______________ 12.4%

For the calendar year 1964 the provisional rates were:

Engineering ________________________155.0 %
Independent Research & Development______ 1.8%
General & Administrative ______________ 14.6%

The final rates for 1964 were negotiated in 1965 and 1966 and were as follows:

Engineering, Drafting & Laboratory Rates __ 169.80%
Material Rates_____________________ 11.58%
General & Administrative _____________ 14.85%
Transfer Expense ___________________ 1.70%
CIRP ____________________________ 2.05%

Unlike the final rates for 1963, however, the final rates for 1964 were never incorporated into the contract.

Plaintiff’s request of the contracting officer on December 16, 1966, for additional funds owing to the difference between the provisional and final overhead rates for 1963 and 1964 was denied. The contracting officer’s decision was based on plaintiff’s failure to give notice to the Government of the possibility of a cost overrun in accordance with the contract’s Limitation of Cost clause (hereinafter LOCC):

LIMITATION OF COST (FEB. 1959) (ASPR 7-402.2)
(a) It is estimated that the total cost to the Government, exclusive of any fixed fee, for the performance of this contract will not exceed the estimated cost set forth in the Schedule, and the Contractor agrees to use his best efforts to perform the work specified in the Schedule, and all obligations under this contract within such estimated cost. If at any time the Contractor has reason to believe that the costs which he expects to incur in the performance of this contract in the next succeeding sixty (60) days, when added to all costs previously incurred, will exceed seventy-five percent (75%) of the estimated cost then set forth in the Schedule, or if at any time, the Contractor has reason to believe that the total cost to the Government, exclusive of any fixed fee, for the performance of this contract will be substantially greater or less than the then estimated cost thereof, the Contractor shall notify the Contracting Officer in writing to that effect, giving the revised estimate of such total cost for the performance of this contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

APTIM Federal Services, LLC
Armed Services Board of Contract Appeals, 2020
Johnson Controls World Services, Inc. v. United States
48 Fed. Cl. 479 (Federal Claims, 2001)
Rmi, Inc. v. The United States
800 F.2d 246 (Federal Circuit, 1986)
National Civil Service League v. United States
643 F.2d 768 (Court of Claims, 1981)
Meva Corp. v. United States
511 F.2d 548 (Court of Claims, 1975)
Talisman Associates, Ltd.
202 Ct. Cl. 1119 (Court of Claims, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
440 F.2d 420, 194 Ct. Cl. 678, 1971 U.S. Ct. Cl. LEXIS 120, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-electric-company-a-corporation-v-the-united-states-cc-1971.