Rmi, Inc. v. The United States

800 F.2d 246, 33 Cont. Cas. Fed. 74,556, 1986 U.S. App. LEXIS 20354
CourtCourt of Appeals for the Federal Circuit
DecidedAugust 29, 1986
DocketAppeal 86-659
StatusPublished
Cited by6 cases

This text of 800 F.2d 246 (Rmi, Inc. v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rmi, Inc. v. The United States, 800 F.2d 246, 33 Cont. Cas. Fed. 74,556, 1986 U.S. App. LEXIS 20354 (Fed. Cir. 1986).

Opinion

BISSELL, Circuit Judge.

RMI, Inc. appeals from the decision of the Armed Services Board of Contract Appeals (ASBCA or Board) sustaining a contracting officer’s final decision denying RMI’s request for reimbursement of its cost overrun. 85-3 BCA 1118,231 (ASBCA 1985). We vacate the Board’s decision and remand the case for proceedings consistent with this opinion.

BACKGROUND

RMI appeals the decision of the Board denying RMI’s recovery of a cost overrun in the performance of Contract No. N00024-80-C-2204 (contract) with the United States Defense Contract Administration Services Region, Los Angeles, of the Defense Logistics Agency (agency). The contract was one of two in a Department of the Navy (Navy) procurement process by which two contractors developed competing system designs for an advanced marine vehicle. Upon completion of these *247 development contracts, the Navy was to select a contractor for actual production of the vehicle. RMI was awarded the contract on June 5, 1980. The term of the contract was for a period of 17 months, extending from June 1980 to November 1981. On June 1,1981, the Navy terminated for convenience RMI’s contract and awarded the follow-on production contract to the other contractor.

In January 1982, RMI submitted to the Termination Contracting Officer (TCO) its Termination Settlement Proposal (proposal) in which it claimed certain contract costs, termination expenses and contract fees, including the cost overrun. RMI stated that the overrun was attributable to unexpected and unforeseeable increases in engineering and business overhead rates which were not discovered until after termination of the contract. The proposal and its underlying documentation was audited by the Defense Contract Audit Agency. The audit, Audit Report No. 4151-3B171001, indicated that (i) RMI had completed all tasks as required by the contract and as directed by the Navy; (ii) its job cost accounting system was acceptable for recording actual performance costs under cost-type contracts; and (iii) RMI had actually incurred the amounts representing the cost overrun but questioned payment of these amounts because they were overruns. In order to examine RMI’s claim that it had no reason to believe prior to the termination of the contract that the overhead expenses would exceed the estimated overhead expenses, RMI and the TCO agreed to a supplemental audit to examine the overhead rates. Prior to completion of the supplemental audit, the TCO by letters dated April 12, 1983, and June 28, 1983, first informed RMI that he had neither the funding nor the authority to recognize and negotiate the cost overrun and then made a unilateral determination that RMI’s request for payment of the cost overrun was without merit because of RMI’s failure to notify the agency that an overrun would occur under the Limitation of Cost Clause (LOCC) in the contract.

RMI appealed the TCO’s decision to the Board and submitted its case on affidavits and briefs as permitted by Rule 11 of the Board’s Rules of Procedure. Before the Board, RMI argued that the TCO’s decision was improper as it was based solely on RMI’s failure to give notice of the overrun and that the TCO did not consider, as required by the LOCC, whether RMI knew or should have known that a cost overrun would occur at year-end. The agency produced no evidence. Instead, the agency stated, in response to RMI’s interrogatories, that it had no specific information concerning whether RMI knew or should have known of a cost overrun.

In its decision on RMI’s appeal, the Board denied RMI’s claim for costs incurred in excess of the maximum contract target amount. The Board determined that RMI “failed to prove the overrun in question was not reasonably foreseeable and the TCO did not abuse his discretion in refusing to provide the requested funding.” 85-3 BCA 1118,231 at 91,547. RMI appeals to this court pursuant to the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-613.

ISSUE

Whether the Board correctly found that RMI failed to meet its burden of establishing that it reasonably could not have foreseen the cost overrun.

OPINION

Under our scope of review, the Board’s conclusions of law are not final and are thus freely reviewable, while the Board’s findings of fact are final and our review is limited to a determination whether those findings are arbitrary, capricious, based on less than substantial evidence, or rendered in bad faith. 41 U.S.C. § 609(b) (1982).

The LOCC at issue in this appeal, DAR § 7-402.2(a) (1966 OCT), provides in pertinent part:

(a) It is estimated that the total cost to the Government for the performance of this contract, exclusive of any fee, will not exceed the estimated cost set forth in the Schedule, and the Contractor agrees to use his best efforts to perform the work specified in the Schedule and all obligations under this contract within such estimated cost. If, at any time, the *248 Contractor has reason to believe that the cost which he expects to incur in the performance of this contract in the next succeeding sixty (60) days, when added to all costs previously incurred, will exceed seventy-five percent (75%) of the estimated cost set forth in the Schedule, or if, at any time, the Contractor has reason to believe that the total cost to the Government for the performance of this contract, exclusive of any fee, will be greater or substantially less than the then estimated cost hereof, the Contractor will notify the Contracting Officer in writing to that effect, giving the revised estimate of such total cost for the performance of this contract.

85-3 BCA ¶ 18,231 at 91,541 (emphasis in original).

One of our predecessor courts has held that by its own terms the above-cited portion of the LOCC can relieve a contractor of the notice requirement. General Electric Company v. United States, 194 Ct.Cl. 678, 440 F.2d 420, 423 (1971). The LOCC “provides that ‘[i]f at any time the Contractor has reason to believe’ that a cost overrun is imminent the contractor is required to so notify the contracting officer.” Id. Conversely, “[i]f the contractor has no reason to believe that an overrun is imminent, he is not required to give notice.” Id. Therefore if a “contractor, through no fault or inadequacy on its part, has no reason to believe, during performance, that a cost overrun will occur and the sole ground for the contracting officer’s refusal [to fund a cost overrun] is the contractor’s failure to give proper notice of the overrun” the contractor is entitled to have the overrun funded. Id. at 425.

Here, the Board placed the burden of proving on RMI that the cost overrun was not reasonably foreseeable. See General Time Corporation, 75-2 BCA ¶ 11,462. We agree that this is a proper allocation of the burden of proof. However, in carrying its burden of proof, the contractor must only prove that it could not have reasonably foreseen the cost overrun during the time of performance of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
800 F.2d 246, 33 Cont. Cas. Fed. 74,556, 1986 U.S. App. LEXIS 20354, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rmi-inc-v-the-united-states-cafc-1986.