Advanced Materials, Inc. v. William J. Perry, Secretary of Defense

108 F.3d 307, 41 Cont. Cas. Fed. 77,060, 1997 U.S. App. LEXIS 3302, 1997 WL 74531
CourtCourt of Appeals for the Federal Circuit
DecidedFebruary 24, 1997
Docket96-1028
StatusPublished
Cited by17 cases

This text of 108 F.3d 307 (Advanced Materials, Inc. v. William J. Perry, Secretary of Defense) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Advanced Materials, Inc. v. William J. Perry, Secretary of Defense, 108 F.3d 307, 41 Cont. Cas. Fed. 77,060, 1997 U.S. App. LEXIS 3302, 1997 WL 74531 (Fed. Cir. 1997).

Opinion

FRIEDMAN, Senior Circuit Judge.

A cost plus fixed fee government procurement contract specified the maximum amount the government would pay and provided a procedure whereby a contractor could exceed the cost limitation. The Armed Services Board of Contract Appeals held that the appellant’s failure to comply with that procedure barred it from obtaining amounts in excess of the specified maximum that it incurred in performing the contract. We affirm.

I.

In April 1991, the appellant Advanced Materials, Inc. (“Advanced Materials” or “the company”) entered into a contract to design and develop decontamination kits for the Army. The contract price was cost plus a fixed fee, and the contract contained a schedule showing the estimated total cost of performance. As modified, the contract was “fully fund[ed]” at $825,262.00. The total funding subsequently was increased to $1,085,712.

The contract incorporated by reference the “Limitation of Cost” provision (cost limitation provision) in Federal Acquisition Regulation, 48 C.F.R. § 52.232-20. That provision stated that “[t]he Government is not obligated to reimburse the contractor for costs incurred in excess of (i) the estimated cost specified in the Schedule.” The provision required the contractor to

notify the Contracting Officer in writing whenever it has reason to believe that — (1) [t]he costs the Contractor expects to incur under this contract in the next 60 days, when added to all costs previously incurred, will exceed 75 percent of the estimated cost specified in the Schedule; or (2) [t]he total cost for the performance of this contract ... will be either greater or substantially less than had been previously estimated.

The provision further stated:

*309 As part of the notification, the Contractor shall provide the Contracting Officer a revised estimate of the total cost of performing th[e] contract.... The Contractor is not obligated to continue performance under th[e] contract ... or otherwise incur costs in excess of the estimated cost specified in the Schedule, until the Contracting Officer (i) notifies the Contractor in writing that the estimated cost has been increased and (ii) provides a revised estimated total cost of performing th[e] contract.

The provision also provided:

In the absence of the specified notice, the Government is not obligated to reimburse the Contractor for any costs in excess of the estimated cost....

The contract was funded incrementally, i.e., for stated consecutive periods. The contract was awarded on April 4,1991 and had a completion date of November 24, 1992. On December 19, 1991, March 13, 1992 and August 14, 1992, Advanced Materials gave the Army written notification that it had reached seventy-five percent of the contract’s estimated cost. It did not give any revised estimate or indicate that the cost would exceed that percentage. Instead, Advanced Material^’ final contract status reports advised the Army that expenditures were within the contract’s estimated costs. Sometime after August 22, 1992, Advanced Materials delivered the kits and the Army paid the balance of the contract price.

In mid-November, after the kits were delivered but before Advanced Materials had completed performance of the contract, a company Vice-President (Hoefer) verbally told the contracting officer that Advanced Materials had a cost overrun on the contract. The contracting officer replied that the contract required written notification. Almost a month later, after the November 24, 1992 contract completion date had passed, the company wrote two letters stating that there had been cost overruns and that it anticipated an additional overrun to complete final reports under the contract.

On December 21, 1992, the contracting officer gave Advanced Materials written directions to stop work and to incur no additional costs. He stated that the government was not obligated to pay costs in excess of the amount specified in the contract until he had notified the company that the estimated costs had been increased and provided a revised total estimated cost of performance. The contracting officer also stated that “the Government is considering the allocation of additional funds to this contract.”

Four months later the contracting officer informed the company that he would not authorize additional funds without assurance from the Defense Contract Audit Agency (audit agency) that the additional costs were “properly allocable and allowable.” The audit agency concluded that the additional costs were unreasonable. After reviewing the report and the company’s objections thereto, the contracting officer notified the company that he agreed -with the conclusion that the company unreasonably had exceeded the contract’s estimated cost and he therefore disallowed the excess costs requested.

The company then submitted to the contracting officer a claim for $191,013. The contracting officer stated that he could not resolve certain issues relating to direct and indirect costs, and referred those matters to an administrative contracting officer. The latter wrote the company that the government owed it no additional money under the contract, but that “the Army is agreeable to increase funding if appropriate to cover allowable, allocable and reasonable costs incurred prior to 21 Dec[ember] 1992.” She requested the company to submit its final voucher and closing statement so that she could make a final determination of such costs.

Advanced Materials deemed the contracting officer’s failure to rule on its claim a denial thereof, and filed a complaint with the Board. It contended that the cost limitation provision was unenforceable because it had no reason to foresee the overrun. Furthermore, it asserted that the government was estopped from relying on the provision because the contracting officer and the administrative contracting officer induced the company to continue performing the contract by representing to it that the government would consider allocating additional funds. It also *310 alleged that the government had waived the provision by indicating that it would fund the overrun.

After an evidentiary hearing, the Board denied the claim, ruling that the cost limitation provision barred recovery of costs exceeding the amount stipulated in the contract. The Board found that the company “knew or had reason to know its year-to-date direct and G & A [general and administrative] costs as it was performing contract 80 and that no unforeseen event prevented AMI from seeking additional funds or stopping work before exceeding the funding limit.” The Board held that the company had not proved its claim that the government was estopped from relying on the cost limitation provision.

II.

A. Under the unambiguous language of the cost limitation provision, the estimated cost shown in the contract constitutes a ceiling on the government’s contractual liability.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

D-STAR Engineering Corp.
Armed Services Board of Contract Appeals, 2025
Interimage, Inc. v. United States
133 Fed. Cl. 355 (Federal Claims, 2017)
Mabus v. General Dynamics C4 Systems, Inc.
633 F.3d 1356 (Federal Circuit, 2011)
International Technology Corp. v. Winter
523 F.3d 1341 (Federal Circuit, 2008)
Kaeper Machine, Inc. v. United States
74 Fed. Cl. 1 (Federal Claims, 2006)
General Motors Corp. v. United States
66 Fed. Cl. 153 (Federal Claims, 2005)
Fluor Enterprises, Inc. v. United States
64 Fed. Cl. 461 (Federal Claims, 2005)
Johnson Controls World Services, Inc. v. United States
48 Fed. Cl. 479 (Federal Claims, 2001)
Scan-Tech Security, L.P. v. United States
46 Fed. Cl. 326 (Federal Claims, 2000)
CJP Contractors, Inc. v. United States
45 Fed. Cl. 343 (Federal Claims, 1999)
Northrop Grumman Corp. v. United States
42 Cont. Cas. Fed. 77,381 (Federal Claims, 1998)
Westinghouse Electric Corp. v. United States
42 Cont. Cas. Fed. 77,332 (Federal Claims, 1998)
KMS Fusion, Inc. v. United States
42 Cont. Cas. Fed. 77,211 (Federal Claims, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
108 F.3d 307, 41 Cont. Cas. Fed. 77,060, 1997 U.S. App. LEXIS 3302, 1997 WL 74531, Counsel Stack Legal Research, https://law.counselstack.com/opinion/advanced-materials-inc-v-william-j-perry-secretary-of-defense-cafc-1997.