International Technology Corp. v. Winter

523 F.3d 1341, 38 Envtl. L. Rep. (Envtl. Law Inst.) 20094, 2008 U.S. App. LEXIS 8406, 2008 WL 1757679
CourtCourt of Appeals for the Federal Circuit
DecidedApril 18, 2008
Docket2007-1276
StatusPublished
Cited by1 cases

This text of 523 F.3d 1341 (International Technology Corp. v. Winter) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
International Technology Corp. v. Winter, 523 F.3d 1341, 38 Envtl. L. Rep. (Envtl. Law Inst.) 20094, 2008 U.S. App. LEXIS 8406, 2008 WL 1757679 (Fed. Cir. 2008).

Opinion

Opinion for the court filed by Circuit Judge DYK. Circuit Judge MOORE concurs in the result.

DYK, Circuit Judge.

This case involves a claim for breach of a cost-plus-fixed-fee contract for treatment of contaminated soil at a Navy facility in Stockton, California. The contractor, International Technology Corporation (“ITC”), 1 seeks to recover additional soil treatment expenses incurred by a subcontractor, Terra Kleen Response Group, Inc. (“TK”), because of unexpectedly high concentrations of clay in the treated soil. The Armed Services Board of Contract Appeals (“Board”) held that ITC was not entitled to an award of costs and also determined that ITC was not entitled to damages for breach of the contract. We affirm.

BACKGROUND

I

ITC was awarded a cost-plus-fixed-fee contract on February 23, 1994, by the Department of the Navy. The contract was for environmental remediation services designed to remove pesticides and related chemicals at a variety of contaminated sites. The contract did not describe the services to be performed, but instead provided that services would be specified in a series of subsequent delivery orders. Because the contract was awarded on a cost-plus-fixed-fee basis, the contract contained the “Limitation of Cost” provision of Federal Acquisition Regulation (“FAR”) 52.232-20, 48 C.F.R. § 52.232-20. Pursuant to this clause, “the estimated cost shown in the contract constitutes a ceiling on the government’s contractual liability,” which can only be increased if the government modifies the cost ceiling. Advanced Materials, Inc. v. Perry, 108 F.3d 307, 310 (Fed.Cir.1997). In the absence of such a modification, “the contractor is not required to continue performance or incur costs that exceed those estimated in the contract.” Id. The Limitation of Cost clause also contains a notice provision, requiring “that the contractor notify the government in writing when it anticipates that within the next sixty days it will exceed seventy-five percent of the estimated cost and provide a revised estimate.” Id.

The delivery order relevant to this case, Delivery Order number 102 (“the DO”), was issued by the government on August 29, 1997. It called for treatment of pesticide-contaminated soil at the Naval Communication Station in Stockton, California. The DO also provided that the period of performance was September 1, 1997, through September 30, 1998, and stated an estimated cost, for purposes of the Limitation of Cost clause, in the amount of $1,228,409. 2 On approximately April 17, 1998, ITC awarded a fixed-price subcontract to TK to perform the soil treatment at the Stockton worksite.

TK had developed a solvent extraction technology for the removal of certain contaminants, including the pesticide DDT, from contaminated soil, and had earlier demonstrated its technology in a small-scale pilot soil treatment program at the Stockton worksite itself. The solvent extraction technology works by dissolving certain contaminants from the soil into a *1345 solvent in sealed treatment bins. The solvent is then drained and filtered to remove the contaminants, so that the solvent can be reused. Two reports, entitled Terra Kleen Solvent Extraction Technology Evaluation Report (“Solvent Technology Report”) and Focused Feasibility Study for DDT-Contaminated Soil (“Feasibility Study”), prepared by a third-party contractor, discussed and evaluated the results of TK’s pilot treatment program. TK provided technical input used in the preparation of both reports.

The Solvent Technology Report and the Feasibility Study were not prepared pursuant to the government contract involved here. However, the DO briefly referenced these reports. One section of the DO presented a series of “specific tasks” the contractor should perform, each followed by descriptive paragraphs. The first of these tasks was entitled “Examine Existing Documents.” It directed the contractor to “[ejxamine the following documents:” and then listed the Feasibility Study and the Solvent Technology Report. Appellant’s Supplemental App., tab 2, at 5. This provision also contained the following note: “The contractor is not required to provide written responses to these documents. Examining these items will assist the contractor in preparing the plans described in task 2 of this delivery order.” Id. 3

A key focus in this case has been the content of the two reports, and in particular what they represented about the clay content of the soil at the site. The Solvent Technology Report described the Stockton site, TK’s solvent extraction technology, the procedures used, and the results of the pilot study. A single, one-page figure in this report, Table 2-15, entitled “Soil Characteristics,” presented characteristics for nine soil samples taken from the site during the pilot treatment program, including the classification of the soil type for each and the percent of sand, silt, clay, and gravel in each. For the nine samples, the clay content figures reported in Table 2-15 were: 6%, 7%, 9%, 9%, 9%, 9%, 11 %, 10%, and 8%. TK’s President and CEO, Alan Cash, was present and observed the manner in which at least six of these soil samples were collected. The Solvent Technology Report also indicated:

Solvent extraction cycles took much longer than expected due to the reduced [soil] permeability, thereby increasing treatment time and cost.... The soil also tended to form clay lumps when compacted. This resulted in the formation of soil aggregates which were difficult to saturate with solvent, resulting in less particle contact and lower DDT removal efficiencies.

Appellant’s Supplemental App., tab 1, at 3-4.

The Feasibility Study compared the relative merits of several alternative methods for treatment or disposal of the contaminated soil at the Stockton site, including use of TK’s solvent extraction technology. The appendix of the Feasibility Study included a number of tables reporting analy-ses of samples of the contaminated Stockton soil before and after TK treated the soil in the pilot program. These tables referenced the soil composition, and indicated that some samples had a majority of clay, that is, substantially higher clay content than the figures in the Solvent Technology Report. It is unclear whether the samples reported in the Feasibility Study *1346 were the same as the samples reported in the Solvent Technology Report.

Pursuant to its subcontract with ITC, TK used its solvent extraction technology to treat the soil at the Stockton worksite. However, TK experienced problems in treating the contaminated soil. In a progress report to the government dated February 2, 1999, ITC noted that processing of the first increment of soil had been delayed, and attributed the delay in part to higher than expected levels of clay in the soil.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Amatea/Grimberg JV
Armed Services Board of Contract Appeals, 2023

Cite This Page — Counsel Stack

Bluebook (online)
523 F.3d 1341, 38 Envtl. L. Rep. (Envtl. Law Inst.) 20094, 2008 U.S. App. LEXIS 8406, 2008 WL 1757679, Counsel Stack Legal Research, https://law.counselstack.com/opinion/international-technology-corp-v-winter-cafc-2008.