CCI, Inc.

CourtArmed Services Board of Contract Appeals
DecidedMarch 14, 2014
DocketASBCA No. 57316
StatusPublished

This text of CCI, Inc. (CCI, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CCI, Inc., (asbca 2014).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of-- ) ) CCI, Inc. ) ASBCA No. 57316 ) Under Contract No. W917BK-08-C-0059 )

APPEARANCES FOR THE APPELLANT: Traeger Machetanz, Esq. Lisa M. Marchese, Esq. Dorsey & Whitney, LLP Seattle, WA

APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq. Engineer Chief Trial Attorney James D. Stephens, Esq. Jeremy Becker-Welts, Esq. Tania Wang, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Middle East Winchester, VA

OPINION BY ADMINISTRATIVE JUDGE SCOTT

CCI, Inc. appealed under the Contract Disputes Act (CDA), 41 U.S.C. §§ 7101-7109, from the contracting officer's (CO's) denial of its differing site conditions claim, then in the amount of$35,125,036, under its contract with the U.S. Army Corps of Engineers (Corps), Gulf Region South District (GRS), for a pier and seawall project in Iraq. The Board held a 15-day hearing, in Anchorage, Alaska, and Falls Church, Virginia. We heard entitlement and quantum but because we deny the appeal we do not decide quantum and therefore do not make quantum findings.

FINDINGS OF FACT

1. On 25 April 2008 GRS issued a request for proposals (RFP) for a negotiated design/build contract under the Foreign Military Sales (FMS) program. The Iraqi Navy was the FMS customer. The RFP sought seawall design and construction; a design to minimize dredging; and construction of an "L-shaped" pier ("Pier 1"), with an option for a "T-shaped" pier ("Pier 2") (north of an existing Pier 3) at Umm Qasr, Iraq. The contractor was responsible for project design and was to submit required design documentation at 35%, 99%, and 100% phases. (R4, tab 103 at 1 of87, at Scope of Work (SOW) at 96-97, 101-03 of 113, tab 103 at 5 of 89; tr. 8/80) 2. The RFP contained the FAR 52.236-27, SITE VISIT (CONSTRUCTION) (FEB 1995) clause under which offerors are urged and expected to inspect the work site (R4, tab 103 at 71 of 89).

3. The RFP included the FAR 52.236-2, DIFFERING SITE CONDITIONS (APR 1984) clause, which states, concerning a "Type I" differing site condition, at issue:

(a) The Contractor shall promptly, and before the conditions are disturbed, give a written notice to the [CO] of ( 1) subsurface or latent physical conditions at the site which differ materially from those indicated in this contract.. ..

(b) The [CO] shall investigate the site conditions promptly after receiving the notice. If [they] do materially so differ and cause an increase .. .in the Contractor's cost of, or the time required for, performing any part of the work under this contract, whether or not changed as a result of the conditions, an equitable adjustment shall be made ....

(R4, tab 103 at 84 of 89)

4. The RFP also contained the FAR 52.236-3, SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (APR 1984) clause which provides that the contractor acknowledges that it has satisfied itself as to the conditions that can affect the work, including tide uncertainties; ground conditions; and surface and subsurface conditions reasonably ascertainable from a site inspection, the government's exploratory work, and the contract. The clause disclaims government responsibility for the contractor's failure to do so or for its conclusions. (R4, tab 103 at 84-85 of 89)

5. The RFP stated that the "Contractor/Designer shall research all existing conditions" at the naval base and waterway (R4, tab 103, SOW at 96 of 113).

6. RFP § 4.1, "GEOTECHNICAL," provided:

4.1.1 Site Specific Information Site specific geotechnical information necessary to design and construct the pile foundations, sea wall and other geotechnical related items contained in this project shall be the Contractor's responsibility. The Contractor shall determine all necessary geotechnical conditions by appropriate field and laboratory investigations and supporting calculations ....

2 Additional explorations may be required to adequately determine the subsurface conditions if the soil is highly variable; unusual conditions are expected and/or to determine ... other geotechnical related requirements ....

4.1.2 Existing Geotechnical Information A geotechnical study of the project site containing 3 borings has been provided in Appendix C. This exploration's logs and geotechnical report by others are ''for information only".

4.1.3 Geotechnical Report The Contractor shall produce a detailed geotechnical report.... Information in the report shall include, but not be limited to: existing geotechnical (e.g., surface and subsurface) conditions ....

4.1.6 Design Certification The Contractor shall certifY in writing that the design of the project has been developed consistent with the site-specific geotechnical conditions. The certification shall be stamped by the geotechnical engineer or geotechnical firm and shall be submitted with the final design.

(R4, tab 103, SOW at 99-100 of 113) (Emphasis added)

7. The referenced Appendix C, "Report on Site Investigation for Dock at Urn Qasir Port at Basrah Governorate," dated May 2007, was prepared by Iraq's Andrea Engineering Tests Laboratory for a different contractor "to explore the subsoil conditions of the proposed site to facilitate the foundation design for ... new docks & related structures at Urn Qasir Port" (R4, tab 103, app'x Cat 1) (Andrea report or AR). The report addressed a field investigation that included three boreholes (BH), an in-situ Standard Penetration Test (SPT) and other tests. It contained BH locations and logs; field test results; and a summary of laboratory test results. The SPT measured soil consistency at several depths. It was performed in all types of soil, especially in "sandy clayey layers" (AR at 3). The AR included American Society for Testing and Materials (ASTM) tests: visual classification; natural moisture content and unit weight; specific gravity; grain size

3 distribution; liquid and plastic limits; shear tests, including unconfirmed and triaxial compression and direct shear; and consolidation compressibility; plus various chemical analyses on soil. (AR at 1-12 and appendices)

8. The AR stated at § IV, "DESCRIPTION OF SUBSOIL STRATA":

The subsoil strata consist mainly of a very soft, soft to medium gray to dark gray sandy silty clay layer with black traces of organic matter and white shiny traces ofsoluble salts, overlying medium, dense to very dense layer of gray fine, medium to coarse grained siltY sand, with little gravel.

The water table was encountered, as observed at the time of investigation between (0.0-1.0), below the existing ground level (NGL), at [BH] nos 2 & 3, which were in the ebb and tide zone. While at [BH] no. ( 1), which was the more distance from the sea, was between ( l.0-1.5)m ....

The fluctuation of water table with the seasons could be observed (rising during spring). The zone immediately above water table is greatly affected as far as strength and compressibility are concerned. As moisture increased the strength decreased and compressibility increased.

(AR at 4) (Emphasis added)

9. The AR stated at§ VI, "DISCUSSION OF RESULTS":

The site subsoil consists mainly from two layers, the first layer of very soft, soft to medium gray sandy silty clay with amount of soluble salts and organic matter overlying on a layer of medium, dense to very dense gray silty sand.... [T]he majority of the first top soil is classified as ... silt-sand-clay mixtures.

The water table was encountered. .. between (0.0-1.0) meter below the existing ground level.... Furthermore, the site was within the ebb and tide zone of the sea.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bender v. Williamsport Area School District
475 U.S. 534 (Supreme Court, 1986)
International Technology Corp. v. Winter
523 F.3d 1341 (Federal Circuit, 2008)
Stuyvesant Dredging Company v. The United States
834 F.2d 1576 (Federal Circuit, 1987)
H.B. Mac, Inc. v. United States
153 F.3d 1338 (Federal Circuit, 1998)
Am-Pro Protective Agency, Inc. v. United States
281 F.3d 1234 (Federal Circuit, 2002)
Road & Highway Builders, LLC v. United States
702 F.3d 1365 (Federal Circuit, 2012)
Metcalf Construction Company v. United States
742 F.3d 984 (Federal Circuit, 2014)
St. Paul Fire & Marine Insurance v. United States
4 Cl. Ct. 762 (Court of Claims, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
CCI, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/cci-inc-asbca-2014.