Stuyvesant Dredging Company v. The United States

834 F.2d 1576, 34 Cont. Cas. Fed. 75,414, 1987 U.S. App. LEXIS 742, 1987 WL 21093
CourtCourt of Appeals for the Federal Circuit
DecidedDecember 10, 1987
Docket87-1304
StatusPublished
Cited by113 cases

This text of 834 F.2d 1576 (Stuyvesant Dredging Company v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stuyvesant Dredging Company v. The United States, 834 F.2d 1576, 34 Cont. Cas. Fed. 75,414, 1987 U.S. App. LEXIS 742, 1987 WL 21093 (Fed. Cir. 1987).

Opinion

FRIEDMAN, Circuit Judge.

This is an appeal from a judgment of the United States Claims Court rejecting the appellant’s claim for an equitable adjustment of its contract price based upon two claims: that the site conditions it found in performing the contract were different from those stated in the specifications, and that the specifications were defective. The Claims Court rejected both contentions. Stuyvesant Dredging Co. v. United States, 11 Cl.Ct. 853 (1987). We affirm.

I

A. The principal facts in this case, as found by the Claims Court, are not in dispute. On June 24, 1982, the United States Army Corps of Engineers (Corps), awarded appellant Stuyvesant Dredging Company (Stuyvesant) a contract for maintenance dredging of the Corpus Christi Entrance Channel. Stuyvesant was a new company formed in 1980 to perform government dredging contracts with its new dredge.

Maintenance dredging is done periodically to restore a channel to its so-called “acceptable prism,” which is the original shape and size of the channel and always remains the same. Beneath the acceptable prism is an area known as the “prescribed prism.” Due to the inaccuracies inherent in the dredging process, material also may be removed from the prescribed prism.

The contract provided for payment based upon the amount of material removed, which could include material from both prisms. Material dredged from outside those two prisms would not be paid for. The contract required an estimated 1,028,-000 cubic yards of material to be removed from the acceptable prism of the channel. The channel was 600-700 feet wide and 20,500 feet long. The prescribed prism of the channel contained an estimated 1,970,-000 cubic yards of material, which included the 1,028,000 cubic yards in the acceptable prism that were to be removed.

All previous maintenance dredging of this channel had been performed by the Corps with its own dredges. The last maintenance dredging had been done in 1978. After Hurricane Allen, there had been “emergency dredging” in 1981 designed to open the channel to navigation until maintenance dredging could restore the channel to its acceptable prism. Stuyvesant was aware of these previous dredging operations.

Technical provision 4-1.1 of the contract, which (like the other technical provisions) *1579 was part of the invitation for bids, provided:

4-1 CHARACTER OF MATERIALS. 4-1.1 The material to be removed to restore the depths within the limits specified in Construction Technical Provision 1-1., DESCRIPTION OF WORK, is that composing [sic] of shoaling that has occurred since the channel was last dredged, however, some virgin material [earth never before dredged in that particular channel] may be encountered in the prescribed prism, and/or side slope dredging. Bidders are expected to examine the site of the work and the records of previous dredging, which are available in the Galveston District Office, 400 Barracuda Essayon Building, Galveston, Texas 77553 and Corpus Christi Area Office, No. 3 Science Park, Corpus Christi, Texas 78401 and after investigation decide for themselves the character of the materials.
Technical provision 4-1.3 stated:
In-Situ Densities. The following table details the results of a nuclear density survey conducted in the project area on 4 April 1979. the [sic] in-place density readings presented represent the average value of the density readings taken within the range indicated. The averaged values should not be interpreted as indicating the maximum or minimum density of material which may be encountered.

The table showed six places in the channel at which readings had been taken and density averages that ranged from 1.380 to 1.675 kilograms per liter.

B. Prior to bidding on the Corpus Christi Channel contract, Stuyvesant had bid on contracts to dredge two other channels: the Sabine-Neches Waterway Outer Bar Channel (Sabine-Neches) and Freeport Harbor Channel (Freeport), both located on the Texas Gulf coast. In preparing bids for those two projects, Stuyvesant reviewed the records in the Corps’ offices regarding previous dredgings, removed physical samples of the material to be dredged, and performed echo soundings of the channel bottoms. Stuyvesant was awarded the Freeport contract, which was the company’s first dredging contract for the channels of the Texas Gulf coast.

Stuyvesant prepared its bid on the Corpus Christi project while conducting the sea trials and making other preparations for, but before beginning work on, the Freeport contract. The stated purpose of the Corpus Christi contract was to restore the channel to its acceptable prism.

Unlike the other two bids, this time Stuyvesant did not review the records of previous dredgings available in the Corps’ offices, and did not visit the site to take material samples or echo soundings. In examining the government’s bid documents, Stuyvesant concluded that the wording of the technical provisions in the Corpus Christi project was “very similar, almost identical” to the technical provisions of the Sabine-Neches and Freeport bid documents that it had previously reviewed, and that it was not “warranted to go to the expense of or necessary to do any particular further investigation.” Stuyvesant also assumed that the 1981 “emergency dredging” had reestablished the acceptable prism and that it was required to remove only the material deposited since that time. It concluded that the information contained in the Corpus Christi documents therefore was sufficient to enable it to make a bid.

Stuyvesant based its bid on removing approximately 60,000 cubic yards of material a day for 33 days. After the contract was awarded, the Corps returned the contract to Stuyvesant to submit a new work plan based on the 120 days specified in the bid documents. Stuyvesant changed its work plan accordingly, but still intended to complete the project in 33 days.

For the first few weeks of the project, Stuyvesant met or exceeded its plan. Thereafter, the rate of removal fell drastically because Stuyvesant encountered large quantities of material that were difficult to dredge, which had densities of “up to, if not more than, 1.9 kilograms” per liter. Stuyvesant believed that this was material not previously dredged, but the Corps informed it that this was the same type of material the Corps’ dredges always had *1580 encountered in that channel. This information was available in the records in the Corps’ offices.

The work ultimately required 24 days more than Stuyvesant had anticipated and included approximately 302,500 cubic yards of material taken from the area beyond the prescribed prism, for which the Corps refused to pay.

Although the contract stated that average density readings at fixed places in the channel ranged from 1.380 to 1.675 kilograms per liter, the Corps’ records of previous dredgings of the channel showed densities ranging from 1.663 to more than 2.000 kilograms per liter. Density readings alone, however, do not indicate the character of the material, i.e., whether it is fine or coarse sand, or whether it is compacted. Density is only one of the factors that determines the difficulty of dredging shoal materials.

C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meltech Corporation, Inc.
Armed Services Board of Contract Appeals, 2025
Patricia I. Romero, Inc. dba Pacific West Builders
Armed Services Board of Contract Appeals, 2024
BCI Construction USA, Inc.
Armed Services Board of Contract Appeals, 2024
Sheffield Korte Joint Venture
Armed Services Board of Contract Appeals, 2023
RLB Contracting, Inc.
Armed Services Board of Contract Appeals, 2023
R.L. Persons Construction, Inc.
Armed Services Board of Contract Appeals, 2018
Innoventor, Inc.
Armed Services Board of Contract Appeals, 2017
Zafer Construction Company
Armed Services Board of Contract Appeals, 2017
Columbia State Bank (formerly Appeal of Castle-Rose, Inc.)
Armed Services Board of Contract Appeals, 2016
Meridian Engineering Company v. United States
122 Fed. Cl. 381 (Federal Claims, 2015)
Old Veteran Construction, Inc. v. United States
121 Fed. Cl. 346 (Federal Claims, 2015)
Optimum Services, Inc.
Armed Services Board of Contract Appeals, 2015
PBS&J Constructors, Inc.
Armed Services Board of Contract Appeals, 2014

Cite This Page — Counsel Stack

Bluebook (online)
834 F.2d 1576, 34 Cont. Cas. Fed. 75,414, 1987 U.S. App. LEXIS 742, 1987 WL 21093, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stuyvesant-dredging-company-v-the-united-states-cafc-1987.