BCI Construction USA, Inc.

CourtArmed Services Board of Contract Appeals
DecidedFebruary 5, 2024
Docket62657, 62975, 63200
StatusPublished

This text of BCI Construction USA, Inc. (BCI Construction USA, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BCI Construction USA, Inc., (asbca 2024).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeals of - ) ) BCI Construction USA, Inc. ) ASBCA Nos. 62657, 62975, 63200 ) Under Contract No. W912DQ-17-C-1070 )

APPEARANCES FOR THE APPELLANT: Ron Garber, Esq. Weissman Zucker Euster Morochnik & Garber, P.C. Atlanta, GA

Timothy J. Walsh, Esq. Cathleen S. Aubuchon, Esq. Norton Rose Fulbright US, LLP St. Louis, MO

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Virginia Murray, Esq. Jacob T. Simpson, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Kansas City

OPINION BY ADMINISTRATIVE JUDGE STINSON ON PARTIES’ MOTIONS FOR PARTIAL SUMMARY JUDGMENT

The United States Army Corps of Engineers (USACE), Kansas City District, entered a contract with appellant BCI Construction USA, Inc. (BCI), to perform repairs to the Tuttle Creek Stilling Basin. BCI submitted various delay, defective specification, and differing site conditions claims arising out of the project work. The contracting officer issued two final decisions denying, in part, BCI’s claims, which BCI now appeals. We have jurisdiction pursuant to the Contract Disputes Act of 1978, 41 U.S.C. §§7101-7109. The parties submitted motions for partial summary judgment, response briefs, and reply briefs for consideration in deciding these appeals. For the reasons stated below, the Board grants-in-part and denies-in-part the government’s motion for partial summary judgment, and grants-in-part and denies-in-part appellant’s motion for partial summary judgment. STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTIONS

By Board Order, the parties submitted a Joint Stipulation of Facts (JSF) in support of their motions for partial summary judgment. 1 Our statement of facts relies upon the parties’ JSF, as set forth below, as well as additional facts supported by record evidence, which we have determined are undisputed for the purpose of these motions.

Pre-Award Invitation for Bids

1. In May 2017, the USACE, Kansas City District, issued Invitation for Bid (IFB) No. W912DQ-17-B-1005, “Construction Solicitation and Specifications,” which included specifications for construction and repair of the Tuttle Creek Stilling Basin Wall located in Riley County, Kansas (R4, tab 5 at COE000002, COE000004).

2. A stilling basin, which is part of a dam’s water outlet works, is a depression in a channel or reservoir deep enough to reduce the velocity or turbulence of water flowing out of a dam (JSF ¶¶ 106-07). The Tuttle Creek Stilling Basin sits adjacent to Tuttle Creek Dam, which feeds into the Big Blue River (R4, tab 5 at COE000085, tab 6 at COE000006); (see also JSF ¶¶ 106-07). Tuttle Creek State Park is located just south of Tuttle Creek Dam and just east of the stilling basin (JSF ¶¶ 105-06; R4, tab 6 at COE000006).

3. The IFB set forth the following project description:

The work includes excavation along the landward side of the training walls along monoliths 1 through 12, demolishing and replacing the upper training wall portion to the first control joint and portions on the 1V on 0.59H slope, demolishing and replacing portions of the existing site drainage, filling the existing deep drainage system with flowable fill and replacing the drainage system with a shallower system, installation [of] new concrete columns

1 In addition to the parties’ JSF, each party submitted several iterations of additional statements of fact and competing statements of genuine issues of material fact. Appellant’s additional material facts, dated February 24, 2023, included 193 paragraphs of additional facts. The government’s opposition to appellant’s motion for partial summary judgment, dated February 24, 2023, included 79 paragraphs of additional facts. The government’s reply brief, dated March 24, 2023, included an additional 65 paragraphs of “reply facts.” 2 to provide a horizontal jacking surface for the installation of post-tensioned anchors and incidental related work.

(R4, tab 5 at COE000085)

4. An Executive Summary set forth in a May 2017 Design Documentation Report states, “[t]wo issues are identified and addressed with this project: (1) repair of the stilling basin wall drain system and (2) retrofitting the stilling basin walls due to overturning stability concerns” (JSF ¶¶ 9-10; R4, tab 315 at COE000002, COE000012).

5. The IFB incorporated by full text Federal Acquisition Regulation (FAR) 52.211-12, LIQUIDATED DAMAGES – CONSTRUCTION (SEP 2000), which stated, in part, “(a) [i]f the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $860 for each calendar day of delay until the work is completed or accepted” (JSF ¶ 7; R4, tab 5 at COE0000034). The IFB did not include any information regarding the method the government utilized to compute the daily liquidated damages rate (app. additional material facts dated Feb. 24, 2023, ¶ 192; gov’t reply ¶ 192).

6. The IFB included FAR 52.243-4 CHANGES (JUN 2007) requiring the contractor to assert its right to an adjustment within 30 days of receipt of a written change order, or by submitting to the contracting officer a written statement describing the nature and amount of its proposal (R4, tab 5 at COE00062-63). The IFB also included FAR.249-10, DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984) (id. at COE000064-66).

7. The IFB included FAR 52.216-1, TYPE OF CONTRACT (APR 1984), stating that “[t]he Government contemplates award of a Firm-Fixed Price contract resulting from this solicitation” (R4, tab 5 at COE000017; FAR 52.243-4(e)).

8. The IFB included FAR 52.236-21, SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997), concerning shop drawings (R4, tab 5 at COE000061). Section (f) provided:

If shop drawings show variations from the contract requirements, the Contractor shall describe such variations in writing, separate from the drawings, at the time of submission. If the Contracting Officer approves any such variation, the Contracting Officer shall issue an appropriate contract modification, except that, if the variation is minor

3 or does not involve a change in price or in time of performance, a modification need not be issued.

(Id. at COE000062)

9. The IFB included FAR 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995), stating that “[t]he clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation,” and that offerors “are urged and expected to inspect the site where the work will be performed”) (R4, tab 5 at COE00021).

10. The IFB included FAR 52.236-2, DIFFERING SITE CONDITIONS (APR 1984) (R4, tab 5 at COE000060).

11. The government issued a Determination of Liquidated Damages – Construction, dated January 18, 2017, finding that inclusion in the contract of FAR 52.211-12 was in the best interests of the government (R4, tab 1033). The document, prepared by Nathan McCarn, the government’s Quality Assurance Representative (JSF ¶¶ 2, 24), included a breakdown of government construction oversight staff and support personnel on the project and a formula by which the government determined the daily liquidated damages rate of $860 based upon those labor costs (id.). Mr. McCarn’s calculation sheet noted that “each Con Rep and Office Engineer should have two active contracts to administer,” and that “Project Engineer duties normally involve working new solicitations as well” (R4, tab 1035; app. reply ex. D (dep. of Nathan L. McCarn at 160-61). However, Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wise v. United States
249 U.S. 361 (Supreme Court, 1919)
First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Hercules, Inc. v. United States
516 U.S. 417 (Supreme Court, 1996)
Blue & Gold Fleet, L.P. v. United States
492 F.3d 1308 (Federal Circuit, 2007)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Stuyvesant Dredging Company v. The United States
834 F.2d 1576 (Federal Circuit, 1987)
Dj Manufacturing Corporation v. United States
86 F.3d 1130 (Federal Circuit, 1996)
Olympus Corporation v. United States
98 F.3d 1314 (Federal Circuit, 1996)
The Bubble Room, Inc. v. United States
159 F.3d 553 (Federal Circuit, 1999)
Comtrol, Inc. v. United States
294 F.3d 1357 (Federal Circuit, 2002)
Ragonese v. United States
120 F. Supp. 768 (Court of Claims, 1954)
Doninger Metal Products, Corp. v. United States
50 Fed. Cl. 110 (Federal Claims, 2001)
George Sollitt Construction Co. v. United States
64 Fed. Cl. 229 (Federal Claims, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
BCI Construction USA, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/bci-construction-usa-inc-asbca-2024.