Olympus Corporation v. United States

98 F.3d 1314, 41 Cont. Cas. Fed. 77,022, 1996 U.S. App. LEXIS 27509, 1996 WL 605112
CourtCourt of Appeals for the Federal Circuit
DecidedOctober 23, 1996
Docket96-5002
StatusPublished
Cited by44 cases

This text of 98 F.3d 1314 (Olympus Corporation v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Olympus Corporation v. United States, 98 F.3d 1314, 41 Cont. Cas. Fed. 77,022, 1996 U.S. App. LEXIS 27509, 1996 WL 605112 (Fed. Cir. 1996).

Opinion

LOURIE, Circuit Judge.

Olympus Corporation appeals from the order of the United States Court of Federal Claims, granting the government’s motion for summary judgment in this contract action. Olympus Corp. v. United States, No. 94-51C (Fed.Cl. Sept. 6, 1995). Because the court did not err in determining that Olympus was not entitled to an equitable adjustment under a Differing Site Conditions clause for delays caused by conditions that developed after the contract was executed, we affirm.

BACKGROUND

The parties do not dispute the material facts on this appeal. On March 10, 1987, Olympus entered into a fixed-price construction contract with the United States under which Olympus agreed to pave the plant yards at the Stratford Army Engine Plant in Stratford, Connecticut. 1 The contract included a standard Differing Site Conditions clause which provided, in relevant part:

(a) The Contractor [Olympus] shall promptly, and before the conditions are disturbed, give a written notice to the Contracting Officer of (1) subsurface or latent physical conditions at the site which differ materially from those indicated in this contract, or (2) unknown physical conditions at the site, of an unusual nature, which differ materially from those ordinarily eneoun-tered and generally recognized as inherent in the work of the character provided for in the contract.
(b) The Contracting Officer shall investigate the site conditions promptly after receiving the notice. If the conditions do materially so differ and cause an increase or decrease in the Contractor’s cost of, or the time required for, performing any part of the work under this contract, whether or not changed as a result of the conditions, an equitable adjustment shall be made under this clause and the contract modified in writing accordingly.

Federal Acquisition Regulation (FAR), 48 C.F.R. § 52.236-2 (1995). On April, 18, Olympus received a Notice to Proceed from the Contracting Officer. One month later, Textron Lycoming, an independent government contractor that operated the plant, accidentally cut open an underground oil pipe while clearing a trench in a plant yard. Oil escaped from the pipe, contaminating the soil and preventing Olympus from paving the plant yard.

Soon thereafter, Textron employees went on strike, picketing all entrances to the plant and preventing Olympus employees from accessing the plant yards for nearly two months. After the strike ended, Olympus spent one week assisting Textron’s environmental contractor in the removal of the contaminated sofi. On August 2, Olympus resumed paving.

Olympus timely notified the Contracting Officer of both the contamination and strike delays and requested an equitable adjustment to the contract to provide a 69-day time extension and a price modification to account for Olympus’s additional costs of $107,988.79. The Contracting Officer allowed the requested time extension, but granted a price increase of only $5,358, attributable solely to the contamination delay. Olympus rejected this proposal and submitted a claim to the Contracting Officer, demanding both additional costs and a final decision. After the Contracting Officer issued a final decision in which he rejected *1316 Olympus’s claims, Olympus filed suit in the United States Court of Federal Claims seeking to recover all of its additional costs.

The Court of Federal Claims granted the government’s motion for summary judgment and dismissed Olympus’s complaint. In reaching its decision, the court stated:

[Olympus] relies upon paragraph 45 of the contract, the Differing Site Conditions Clause, as the legal basis for recovery under both its soil contamination delay and the strike delay. The Differing Site Conditions Clause, however, governs conditions existing at the time the contract was entered into. The clause provides no foundation for [Olympus’s] delay claim, (citations omitted)
The soil contamination did not exist at the time the contract was executed. Similarly, there is no dispute that the Textron employees were not on strike at the time the contract was executed. Accordingly, [Olympus’s] reliance upon the Differing Site Conditions Clause as the basis for its recovery is incorrect as a matter of law and must be rejected.

The court also noted that Olympus could not recover the costs of delays caused by an independent contractor. Finally, the court noted that under this fixed-price contract, Olympus had assumed the risk of unexpected costs such as those associated with labor unrest. Olympus now appeals to this court.

DISCUSSION

When, as here, there is no genuine issue as to any material fact, summary judgment is appropriate if the moving party is entitled to judgment as a matter of law. Fed.R.Civ.P. 56(c); Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247, 106 S.Ct. 2505, 2509, 91 L.Ed.2d 202 (1986); Mingus Constructors, Inc. v. United States, 812 F.2d 1387, 1390 (Fed.Cir.1987). Furthermore, summary judgment is appropriate where the sole dispute concerns the proper interpretation of a public contract, a question of law which we review de novo. Muniz v. United States, 972 F.2d 1304, 1309 (Fed.Cir.1992); P.J. Maffei Bldg. Wrecking Corp. v. United States, 782 F.2d 913, 916-17 (Fed.Cir.1984). Olympus only contests the trial court’s interpretation of the Differing Site Conditions clause, in particular raising the issue whether the Differing Site Conditions clause applies only to conditions existing when the contract was executed, not to conditions that develop during performance.

Olympus argues that because the Differing Site Conditions clause was not expressly limited to conditions that existed when the contract was executed, applying such a limitation impermissibly incorporates the government’s subjective intent into the contract. Accordingly, Olympus also argues that the Differing Site Conditions clause shifted the risk of all unanticipated adverse site conditions to the government.

The government argues that the Court of Federal Claims did not err in its interpretation of the Differing Site Conditions clause. The government construes the clause to apply only to conditions existing at the time of contracting. We agree with the government’s interpretation.

The Differing Site Conditions clause and its similarly-worded predecessor, the Changed Conditions clause, have been used in government contracts and interpreted by the courts for over half a century. See United States v. Rice, 317 U.S. 61, 66-68, 63 S.Ct. 120, 123-24, 87 L.Ed. 53 (1942) (interpreting Changed Conditions clause); 32 Fed.Reg. 16,268, 16,270 (1967) (explaining changes to title and text of clause). See generally Richard J. Bednar et al., Construction Contracting 568-615 (1991).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Targe Logistic Services Company
Armed Services Board of Contract Appeals, 2024
BCI Construction USA, Inc.
Armed Services Board of Contract Appeals, 2024
Amatea/Grimberg JV
Armed Services Board of Contract Appeals, 2023
Tidewater, Inc.
Armed Services Board of Contract Appeals, 2018
Walsh Construction Company
Federal Claims, 2018
Burnham Associates, Inc.
Armed Services Board of Contract Appeals, 2017
weston/bean Joint Venture v. United States
123 Fed. Cl. 341 (Federal Claims, 2015)
Zafer Taahhut Insaat Ve Ticaret, A.S. v. United States
120 Fed. Cl. 604 (Federal Claims, 2015)
Extreme Coatings, Inc. v. United States
109 Fed. Cl. 450 (Federal Claims, 2013)
Com. v. AMEC CIVIL, LLC
699 S.E.2d 499 (Supreme Court of Virginia, 2010)
Renda Marine, Inc. v. United States
71 Fed. Cl. 378 (Federal Claims, 2006)
Orlosky Inc. v. United States
68 Fed. Cl. 296 (Federal Claims, 2005)
Short Bros. PLC v. United States
65 Fed. Cl. 695 (Federal Claims, 2005)
L.W. Matteson, Inc. v. United States
61 Fed. Cl. 296 (Federal Claims, 2004)
National Westminster Bank, PLC v. United States
58 Fed. Cl. 491 (Federal Claims, 2003)
CEMS, Inc. v. United States
59 Fed. Cl. 168 (Federal Claims, 2003)
North American Construction Corp. v. United States
56 Fed. Cl. 73 (Federal Claims, 2003)
Globe Savings Bank, F.S.B. v. United States
55 Fed. Cl. 247 (Federal Claims, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
98 F.3d 1314, 41 Cont. Cas. Fed. 77,022, 1996 U.S. App. LEXIS 27509, 1996 WL 605112, Counsel Stack Legal Research, https://law.counselstack.com/opinion/olympus-corporation-v-united-states-cafc-1996.