Arundel Corp. v. United States

96 Ct. Cl. 77, 1942 U.S. Ct. Cl. LEXIS 117, 1942 WL 4438
CourtUnited States Court of Claims
DecidedMarch 2, 1942
DocketNo. 44622
StatusPublished
Cited by13 cases

This text of 96 Ct. Cl. 77 (Arundel Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arundel Corp. v. United States, 96 Ct. Cl. 77, 1942 U.S. Ct. Cl. LEXIS 117, 1942 WL 4438 (cc 1942).

Opinion

Whitaker, Judge,

delivered the opinion of the court:

The plaintiff sues the defendant on twelve different claims, as set out in the findings of fact. These claims will be discussed in order.

CLAIM NO. 1.-ADDITIONAL COST POR CONCRETE PORMS IN DAM ON ACCOUNT OP ALLEGED CHANGES IN CONTRACT DRAWINGS

Plaintiff sues for the cost of the additional concrete forms necessitated by the installation in the dam of chain storage recesses, and recesses for a pick-up device.

The defendant defends first on the ground that plaintiff did not protest at the time it was required to put in the chain storage recesses and the recesses for the pick-up device, as required by the contract. It is true that the contract required that any claim for adjustment for a change made should be asserted within ten days from the date the change was ordered, “unless the contracting officer shall for proper cause extend such time”; but, although no protest was made, the contracting officer considered on its merits this claim set out in plaintiff’s letter of May 28, 1931. The provision requiring protest within ten days was a provision inserted for the benefit of the defendant and, of course, could be waived by it. The consideration of the claim on the merits, without any mention of the fact that it had been filed too late, was a waiver of this contract provision. Thompson v. United States, 91 C. Cls. 166, 179; Callahan Construction Company v. United States, 91 C. Cls. 538, 610.

The defendant says that our decision in Johnson v. United States, 94 C. Cls. 175, 202, is in conflict with th'e foregoing decisions and states the correct rule. It is true that in the Johnson case, as in the Thompson and Callahan Construction Company cases, the contracting officer and the head of the department did hear the plaintiff’s claims, although there had been no timely protest, but the opinion in the Johnson case states they did so without waiving the failure to protest. On the other hand, in the Thompson and Callahan Construction Company cases [111]*111there was a consideration of the claims on the merits without any reservation of the right to rely on the failure to protest. From this we held that a waiver was to be implied; but, of course, a waiver cannot be implied if there is an express statement that the provision for protest is not being waived, or if there are other facts in the case to rebut the implication of a waiver arising from the consideration of the claims on the merits. In the Johnson case we concluded there were present facts which we thought rebutted this implication.

In the case at bar the contracting officer considered the claim on its merits without any mention of the fact that the protest had not been filed as required by the contract. There was no indication that he was relying on this provision of the contract. His action in considering the claim on the merits without any mention of this provision of the contract is a clear indication that he did not intend to rely on it, but waived it.

The drawings, referred to in this case as “plates”, called for chain storage recesses and for recesses for a pick-up device. Plaintiff knew that it would be necessary for it to provide for these recesses, and with this knowledge it put in its bid for doing the work, although specifications for the recesses were not furnished. The specifications furnished later were such as plaintiff could reasonably have expected when it put in its bid. The recesses were called for by the contract and were not an addition thereto. The Chief of Engineers, therefore, correctly ruled that plaintiff was not entitled to additional compensation therefor.

On the other hand, the control rooms and the bearing plate recesses were not called for by the original contract and, therefore, the Chief of Engineers allowed plaintiff additional compensation for their installation.

It results that plaintiff is not entitled to recover on this claim.

CLAIM NO. 2-TIMBER PILE CTJT-OEES

On this claim the plaintiff sues for $1,312.50 for 9,722.22 linear feet of piling cut off above the prescribed elevation, in addition to the amount allowed. The amount of 5,911.22 linear feet of the 9,722.22 linear feet was cut off [112]*112in the storage yard before the piles were placed in the pile driver leads; the balance represents 1 foot on each of the 3,811 piles driven which was cut off on account of brooming, for which no payment was made.

As he was authorized to do by the specifications, the contracting officer on April 25,1935 prescribed that certain piles should be driven to a depth of 30 feet below the cut-off elevation, and certain others to a depth of 20 feet below the cutoff elevation, subject to change as provided for in section 4-03 (a) of the specifications, which provided in part:

* * * where driving conditions clearly indicate that piles of lengths directed cannot be satisfactorily driven shorter lengths may be furnished by mutual agreement between the contractor and the contracting officer.

When the piles were actually driven it was found that they could not be driven to the length specified by the contracting officer; whereupon, the contracting officer and plaintiff’s project manager agreed that the defendant’s resident engineer should be authorized to prescribe from time to time the depth to which the piles should be driven, and that the plaintiff should be paid for the lengths designated by the resident engineer. The plaintiff continued under this arrangement until June 8, 1935, at which time only 700 of the total of 3,811 piles remained to be driven, when the contracting officer wrote plaintiff specifying the depths to which the remaining piles should be driven, subject to change- as provided for in section N03 (a), quoted above..

Piles were placed in the pile driver leads in .accordance with the lengths designated-from time to time by the resident engineer. The defendant kept a record of these lengths, the accuracy of which the plaintiff does not dispute, and plaintiff has been paid on the basis of these lengths at the contract rate of 27 cents per linear foot driven below the cut-off elevation, and 13.5 cents per linear foot above the cut-off elevation, less 1 foot cut-off on account of brooming. The plaintiff claims, in addition, the number of feet cut off in its storage yard before the piles were placed in the pile driver leads and, in addition, for the 1 foot cut off for brooming.

[113]*113So far as plaintiff’s claim for the amount cut off in the storage yard is concerned, it seems plain to us that it is not entitled to recover, in view of the agreement between the parties that the resident engineer should designate the depth to which the piles were to be driven, and that the plaintiff should be paid on the basis of these lengths. The length of the piles placed in the pile driver leads was in accordance with the depth to which they should have been driven as prescribed by the resident engineer. The contract provided that where piles of certain lengths had been placed in the pile driver leads and it was found that they could not be driven to the depth specified, the plaintiff should be paid for them at 27 cents a linear foot below the cut-off elevation, and 13.5 cents per linear foot above the cut-off elevation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Manuel Bros. v. United States
55 Fed. Cl. 8 (Federal Claims, 2002)
Olympus Corporation v. United States
98 F.3d 1314 (Federal Circuit, 1996)
Turnkey Enterprises, Inc. v. United States
597 F.2d 750 (Court of Claims, 1979)
Blount Brothers Corporation v. The United States
424 F.2d 1074 (Court of Claims, 1970)
Morrison-Knudsen Company, Inc. v. The United States
397 F.2d 826 (Court of Claims, 1968)
John McShain, Inc. v. United States
375 F.2d 829 (Court of Claims, 1967)
Norfolk Dredging Company v. The United States
360 F.2d 619 (Court of Claims, 1966)
Penn-Ohio Steel Corporation v. The United States
354 F.2d 254 (Court of Claims, 1965)
Fox Valley Engineering Inc. v. United States
151 Ct. Cl. 228 (Court of Claims, 1960)
Arundel Corp. v. United States
103 Ct. Cl. 688 (Court of Claims, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
96 Ct. Cl. 77, 1942 U.S. Ct. Cl. LEXIS 117, 1942 WL 4438, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arundel-corp-v-united-states-cc-1942.