Penn-Ohio Steel Corporation v. The United States

354 F.2d 254, 173 Ct. Cl. 1064, 1965 U.S. Ct. Cl. LEXIS 192
CourtUnited States Court of Claims
DecidedDecember 17, 1965
Docket396-59
StatusPublished
Cited by38 cases

This text of 354 F.2d 254 (Penn-Ohio Steel Corporation v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Penn-Ohio Steel Corporation v. The United States, 354 F.2d 254, 173 Ct. Cl. 1064, 1965 U.S. Ct. Cl. LEXIS 192 (cc 1965).

Opinion

PER CURIAM:

This case was referred pursuant to Rule 45(a) (now Rule 57(a)) to Trial Commissioner Herbert N. Maletz, with directions to make findings of fact and recommendation for conclusions of law. The commissioner has done so in an opinion and report filed on September 28, 1964. Exceptions to the opinion, the recommendation for conclusion of law and certain of the findings of fact were made by the parties and, upon the filing of their briefs, the case has been submitted to the court upon oral argument of coun *256 sel. The court agrees with the commissioner's findings, his opinion, and his recommended conclusion of law, as hereinafter set forth, and hereby adopts the same as the basis for its judgment in this case. Plaintiff is therefore entitled to recover for the period November 15, 1953, to October 19, 1954, with the amount of recovery to be determined pursuant to Rule 47(c) (2) and judgment is entered accordingly.

OPINION OP COMMISSIONER

Plaintiff, Penn-Ohio Steel Corporation (Penn-Ohio), was the lessee of a Naval Industrial Reserve Plant at Birdsboro, Pennsylvania, where it engaged in the production of steel ingots and various steel products. It alleges, in essence, that in January 1952 it entered into a special or so-called “reverter agreement” of compromise and settlement with the Navy under which, among other things, (1) it was to vacate the plant within a specified time so as to permit the plant’s use in connection with the Army tank program; (2) its lease was to be suspended during this period of special use; and (3) the Navy was to afford it the right to re-occupy the plant upon completion of such special use. Penn-Ohio says that it performed all its undertakings but that the Navy breached the agreement by failing and refusing to permit it to re-enter the plant when the period of special use for the tank program came to an end. It also says that the action of the Secretary of the Navy in terminating the lease some months later was not bona fide but was arbitrary and capricious. Damages of “upwards of $3,500,000” are sought for the alleged contract breaches. Defendant contends that no such agreement as claimed by plaintiff was ever made by the parties. It further alleges that Penn-Ohio’s tenancy expired because it failed to give notice of exercise of its renewal option. Finally, defendant argues that, in any event, the Secretary of the Navy canceled the lease pursuant to lawful authority reserved to him by statute and by the lease; that he did so in good faith and that his action was not arbitrary or capricious; and that his action, in any case, is not open to judicial review.

I

The facts underlying the present controversy are, as follows: During World War II the Navy’s Bureau of Ships (BuShips) constructed at a cost of about $7,500,000 a plant at Birdsboro, Pennsylvania (hereafter referred to as “the Birdsboro plant”) for producing steel ship castings. The plant was operated in the wartime period by the Birdsboro Steel Foundry & Machine Company (hereafter referred to as “the Birdsboro company”) under a lease in the form of a facilities contract which provided it an option to purchase the plant and required it to maintain the facilities at Government expense for 20 years. After the end of the war, the Navy was unsuccessful in selling or leasing the plant at adequate rental to the Birdsboro company and, therefore, terminated the latter’s right to use the plant and advertised it for lease. Penn-Ohio was the successful bidder and entered into a lease in the form of a letter of intent with the Navy’s Bureau of Yards and Docks (BuDocks) under terms and conditions approved by the Acting Secretary of the Navy. 1 The *257 letter of intent provided for a five-year term from June 30,1948 to June 29,1953, with Penn-Ohio having the option to extend the term of the lease for two additional successive terms of five years each under the same terms and conditions, by giving notice of election to extend 120 days prior to the expiration of the then existing term. The letter of intent further provided that the lease could be terminated without prior notice during a national emergency or upon 120 days notice if the Secretary determined that the interests of national defense so required. Penn-Ohio was required to pay a cash rental of $126,600 per year, and also to expend not to exceed $150,000 a year for maintenance as directed by the Navy, with the difference between the actual expenditure for directed maintenance and $150,000 per year to be carried forward from year to year. In the event of termination or expiration of the lease, the Navy had the right to direct fulfillment of the amount reserved for accrued maintenance either by performance of maintenance or by payment of cash. In addition, the Navy had the right to redetermine at any time the allocation of the amount to be paid in cash rent and the amount to be expended for obligated maintenance, not to exceed Penn-Ohio’s obligation to pay $276,600 per year, plus accrued maintenance for previous years. The letter of intent also contained a provision that the parties understood it would be superseded by a formal lease. 2

During the first several years of its occupancy of the plant, 3 Penn-Ohio had difficulty in meeting its rental obligations, a situation which did not, however, continue after 1950. The company was regarded by the Navy as a satisfactory tenant with a good record of producing steel ingots at the plant. Withal, Bu-Ships planned in the event of mobilization to terminate Penn-Ohio’s occupancy and place the Birdsboro company in possession of the plant though it purposely refrained from telling Penn-Ohio of these plans so as to prevent the possibility of losing it as a tenant during normal peace-time operations.

After the start of the Korean war, foundry capacity for producing armor cast hulls and turrets for tanks was in seriously short supply. Army Ordnance determined that the Birdsboro plant was necessary for this production; it also determined that the plant should be operated by the Birdsboro company which would manufacture the hulls and turrets under a subcontract with the Chrysler Corporation and ship these components into the geographically close Newark, Delaware tank assembly plant where Chrysler was to make medium tanks for the Army. In June 1951 the Assistant Secretary of the Navy, pursuant to Army requests, authorized (i) termination of the Penn-Ohio lease and (ii) negotiations looking toward a lease of the facilities to the Birdsboro company.

Penn-Ohio was not made aware of this decision by the Navy but in late October 1951 was told by Army Ordnance that a determination had been made that it was to be evicted from the plant to make way for the Birdsboro company. Penn-Ohio strongly protested this proposed action to a number of Government officials and agencies. Eventually, it met with Army officials in mid-November and reached agreement (1) that it would be given two weeks to submit three alternative proposals to Chrysler whereby it rather than the Birdsboro company would manufacture the armor castings at the plant, and (2) that if its proposals were not acceptable, a phasing-out schedule of its activities at the Birdsboro plant *258

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nascent Group, J.V. v. United States
103 Fed. Cl. 338 (Federal Claims, 2012)
Lublin Corp. v. United States
84 Fed. Cl. 678 (Federal Claims, 2008)
AG Route Seven Partnership v. United States
57 Fed. Cl. 521 (Federal Claims, 2003)
Advance Bank v. United States
52 Fed. Cl. 286 (Federal Claims, 2002)
Schwartz v. Wasserburger
30 P.3d 1114 (Nevada Supreme Court, 2001)
Spivey Marine & Harbor Service Co. v. State
46 Ill. Ct. Cl. 41 (Court of Claims of Illinois, 1994)
Kollsman v. United States
37 Cont. Cas. Fed. 76,283 (Court of Claims, 1992)
Hartle v. United States
22 Cl. Ct. 843 (Court of Claims, 1991)
Edwards v. United States
36 Cont. Cas. Fed. 76,004 (Court of Claims, 1991)
Norwood Manufacturing, Inc. v. United States
36 Cont. Cas. Fed. 75,917 (Court of Claims, 1990)
Lark v. United States
17 Cl. Ct. 567 (Court of Claims, 1989)
OAO Corp. v. United States
35 Cont. Cas. Fed. 75,665 (Court of Claims, 1989)
City of El Centro v. United States
16 Cl. Ct. 500 (Court of Claims, 1989)
Johns-Manville Corp. v. United States
12 Cl. Ct. 1 (Court of Claims, 1987)
People's Bank & Trust Co. v. United States
11 Cl. Ct. 554 (Court of Claims, 1987)
Transamerica Insurance v. United States
32 Cont. Cas. Fed. 73,012 (Court of Claims, 1984)
Consortium Venture Corp. v. United States
32 Cont. Cas. Fed. 72,374 (Court of Claims, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
354 F.2d 254, 173 Ct. Cl. 1064, 1965 U.S. Ct. Cl. LEXIS 192, Counsel Stack Legal Research, https://law.counselstack.com/opinion/penn-ohio-steel-corporation-v-the-united-states-cc-1965.