Transamerica Insurance v. United States

32 Cont. Cas. Fed. 73,012, 6 Cl. Ct. 367, 1984 U.S. Claims LEXIS 1293
CourtUnited States Court of Claims
DecidedOctober 3, 1984
DocketNo. 599-82C
StatusPublished
Cited by15 cases

This text of 32 Cont. Cas. Fed. 73,012 (Transamerica Insurance v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Transamerica Insurance v. United States, 32 Cont. Cas. Fed. 73,012, 6 Cl. Ct. 367, 1984 U.S. Claims LEXIS 1293 (cc 1984).

Opinion

ORDER ON CROSS-MOTIONS FOR SUMMARY JUDGMENT

WHITE, Senior Judge.

The plaintiff, Transamerica Insurance Company (Transamerica), is a California insurance corporation that is authorized to write surety bonds for construction contracts. Transamerica sues in this action for an amount allegedly due under a takeover agreement in connection with a government contract on which it wrote payment and performance bonds, and which it completed when the contracting officer terminated the contract for default.

The case comes before the court at this time on the parties’ cross-motions for summary judgment, supplemented by oral arguments.

Agreed Facts

On December 27, 1979, George S. Rush, d/b/a Rush Engineers (Rush), was award[369]*369ed a government contract to construct a shopping center building at Arnold Air Force Station, Tennessee. The original contract price was $2,148,100, and the scheduled completion date, as amended by modification, was August 18, 1981.

Also on December 27, 1979, Rush, as required by the contract, executed performance and payment bonds, with penal sums of $2,148,100 and $859,240, respectively. The surety for these bonds was Transamer-ica, the principal was Rush, and the obligee was the United States.

On January 30, 1980, Rush received notice to proceed with the work under the contract, and commenced performance.

By August 18, 1981, which was the scheduled completion date, Rush had completed only 71 percent of the work under the contract, and progress on the project had slowed. By means of a letter dated September 9, 1981, the contracting officer notified Rush that the contract was being terminated for default.

The contracting officer and representatives of Transamerica met on September 21, 1981, to discuss completion of the contract by Transamerica under its performance bond.

On October 5, 1981, the Government and Transamerica executed a takeover agreement. This document contained the following provisions (among others):

(1) that Transamerica would engage a contractor to complete the work “under the original contract in accordance with all the terms and conditions thereof”;

(2) that the Government would pay Transamerica “in the manner provided by the contract, but not in excess of the Surety’s cost and expenses, the balance of the contract price unpaid at the time of default,” but subject to certain conditions; and

(3) that one of the conditions was to be as follows:

a. Unpaid earnings of the defaulting contractor, including retained percentages and progress estimates for work accomplished prior to termination, shall be subject to claims by the Government against the contractor, except to the extent that such unpaid earnings may be required to permit payment to the Surety of its actual costs and expenses incurred in the completion of the work, exclusive of its payments and obligations under the payment bond given in connection with the contract.

While the work of completing the contract was in progress, the Government discovered that, in making previous progress payments to Rush, it had mistakenly overpaid Rush to the extent of $79,810.74 above the amount properly due Rush on the work accomplished. This amount was subsequently withheld from a progress payment that was made to Transamerica’s contracting agent. A claim by Transamerica for the $79,810.74 was denied by the contracting officer.

In the present action, Transamerica seeks to recover the $79,810.74 mentioned in the preceding paragraph.1

The total amounts paid by the Government to Rush and to Transamerica (including its contracting agent) equalled the contract price.

The Plaintiff’s Expenses

As previously indicated, the takeover agreement between the Government and Transamerica specifically provided that Transamerica, for its work in completing the contract, was not entitled to any payment “in excess of the Surety’s cost and expenses.”

Transamerica asserts, and the defendant denies, that Transamerica’s costs and expenses in completing the work under the contract exceeded the amount which the Government paid Transamerica (including its contracting agent) for the work involved in the completion of the contract. This controversy between the parties over [370]*370a material issue of fact — quite apart from other considerations — would prevent the court from granting the plaintiffs cross-motion for summary judgment. "Under this court’s Rule 56(c), summary judgment is proper only if there is no genuine issue as to any material fact and the papers before the court show that the moving party is entitled to a judgment as a matter of law.

The Certification

In its motion for summary judgment and supporting brief, the defendant raises several objections to the plaintiff’s complaint. One of the objections is that the court does not have jurisdiction over the plaintiff’s claim because the claim (according to the defendant) was not certified by a proper official when submitted to the contracting officer.

The Contract Disputes Act provides in part as follows:

* * * For claims of more than $50,000, the contractor shall certify that the claim is made in good faith, that the supporting data are accurate and complete to the best of his knowledge and belief, and that the amount requested accurately reflects the contract adjustment for which the contractor believes the Government is liable. [41 U.S.C. § 605(c)(1) (1982).]

Proper certification is a jurisdictional prerequisite to a direct-access action by a government contractor in this court if the claim submitted to the contracting officer exceeds $50,000. W.M. Schlosser Co. v. United States, 705 F.2d 1336, 1338 (Fed.Cir.1983); W.H. Moseley Co. v. United States, 230 Ct.Cl. 405, 406, 677 F.2d 850, 851, cert. denied, 459 U.S. 836, 103 S.Ct. 81, 74 L.Ed.2d 77 (1982).

A Defense Acquisition Regulation (32 C.F.R. § 1-314(L)(2) (1983)) requires that the certification “be executed by a senior company official in charge at the contract’s plant or location involved, or by an officer and general partner of the general contractor having overall responsibility for the conduct of the contract’s affairs.”

The certification in the present case was executed on behalf of Transamerica by one Joseph Saad, who was described in the certificate merely as “Bond Claim Attorney.” An affidavit by Mr. Saad that is before the court, however, states that he was “the senior company official in charge of all matters relating to Transamerica Insurance Company involved with * * * [the] Contract,” and that he “had the overall supervision on behalf of Transamerica Insurance Co. of all the completion work on the * * * project.”

It appears, therefore, that Joseph Saad was qualified to execute the certificate in support of Transamerica’s claim before the contracting officer. Accordingly, the defendant’s jurisdictional defense, based on the alleged lack of a proper certification of the plaintiff’s claim, must be rejected.

The $79,810.74 Mistake

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lumbermens Mutual Casualty Co. v. United States
67 Fed. Cl. 253 (Federal Claims, 2005)
Davis/HRGM Joint Venture v. United States
50 Fed. Cl. 539 (Federal Claims, 2001)
Transamerica Insurance v. United States
39 Cont. Cas. Fed. 76,678 (Federal Claims, 1994)
National Surety Corp. v. United States
39 Cont. Cas. Fed. 76,679 (Federal Claims, 1994)
United Pacific Insurance v. United States
38 Cont. Cas. Fed. 76,361 (Court of Claims, 1992)
Reliance Insurance v. United States
37 Cont. Cas. Fed. 76,090 (Court of Claims, 1991)
Hartle v. United States
22 Cl. Ct. 843 (Court of Claims, 1991)
Westech Corp. v. Fireman's Fund Insurance
36 Cont. Cas. Fed. 75,885 (Court of Claims, 1990)
National Surety Corp. v. United States
36 Cont. Cas. Fed. 75,865 (Court of Claims, 1990)
Travelers Indemnity Co. v. United States
35 Cont. Cas. Fed. 75,607 (Court of Claims, 1988)
Romala Corp. v. United States
34 Cont. Cas. Fed. 75,299 (Court of Claims, 1987)
Sentry Insurance A Mutual Co. v. United States
34 Cont. Cas. Fed. 75,257 (Court of Claims, 1987)
Universal Surety Co. v. United States
33 Cont. Cas. Fed. 74,603 (Court of Claims, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
32 Cont. Cas. Fed. 73,012, 6 Cl. Ct. 367, 1984 U.S. Claims LEXIS 1293, Counsel Stack Legal Research, https://law.counselstack.com/opinion/transamerica-insurance-v-united-states-cc-1984.