Lumbermens Mutual Casualty Co. v. United States

67 Fed. Cl. 253, 2005 U.S. Claims LEXIS 238, 2005 WL 1983688
CourtUnited States Court of Federal Claims
DecidedAugust 17, 2005
DocketNo. 04-1255C
StatusPublished
Cited by7 cases

This text of 67 Fed. Cl. 253 (Lumbermens Mutual Casualty Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lumbermens Mutual Casualty Co. v. United States, 67 Fed. Cl. 253, 2005 U.S. Claims LEXIS 238, 2005 WL 1983688 (uscfc 2005).

Opinion

ORDER AND OPINION

HODGES, Judge.

Plaintiff served as surety on a construction project that was abandoned by the original contractor, Landmark. Plaintiff Lumbermens Mutual took over the contract after default and hired a contractor, Atherton Construction, to complete the job. Lumbermens incurred costs in completing the project that it alleges were caused by defendant’s contract mismanagement. Lumbermens seeks damages under theories of equitable subrogation, impairment of suretyship, and breach of the Takeover Agreement.

The Government moved to dismiss plaintiffs subrogation claims because Lumbermens did not notify the Navy that it should withhold or divert progress payments, or that the contractor was approaching default. We agree that plaintiffs failure to notify the Government of the contractor’s impending default disposes of plaintiffs equitable subrogation claims.

BACKGROUND

The Navy awarded a contract to Landmark Construction Company in April 2000, for the repair and renovation of 160 military family housing units. The initial contract price was approximately $9.9 million. The Miller Act requires contractors to post performance and payment bonds for construction contracts of value greater than $100,000. See 40 U.S.C. § 3131. Landmark obtained the required performance bond from Lum[254]*254bermens Mutual Casualty. Landmark was to complete the work by October 23, 2002.

The contract contained various payment clauses. As with many construction contracts, the Government made periodic progress payments corresponding to the work completed. The contract required Landmark to submit certified Contract Performance Statements and updated Network Analysis Schedules to show progress on the project. The contract also required the contractor to show that it had obtained title to materials before billing the Navy for them. Materials subject to deterioration or damage during transit were to be delivered to the project site before payment.

Lumbermens alleges that the Government did not hold the contractor to these provisions. For example, plaintiff claims that the Navy’s payments to Landmark exceeded progress on the project because defendant based its payments to Landmark upon the passage of time and not to completion of the units.

Landmark’s initial Network Analysis Schedule did not conform to contract requirements because it did not differentiate between the delivery of materials and the incorporation of the materials into the renovated housing. The Navy approved the Schedule nevertheless, and it paid Landmark over one-third of the contract price before having approved the construction drawings, according to Lumbermens. Plaintiff alleges that the Navy paid Landmark more than $1,276,000 for materials without documenting the “quantity, type, size, or [the whereabouts] of the materials].” (Complaint 111155-58.)

The Navy and Landmark agreed to an increase in the contract’s scope in February 2001, adding the renovation of twenty-one housing units for a price of $1,884,176. Lumbermens did not consent to this bilateral agreement between the Government and the original contractor, Landmark. The modification did not extend the completion date of the contract.

Landmark informed the Navy in July 2001 that it would be unable to complete the project. The Navy terminated the contract for default in August 2001. The Navy had paid Landmark nearly forty percent of the total contract price at termination, though Landmark had completed only twenty-two of the 181 housing units.1 The Navy estimated that the project was fourteen weeks behind schedule when it terminated the contract, and the project continued to fall behind as Lumbermens negotiated a takeover agreement with the Government.

Lumbermens and a completion contractor, Atherton Construction, entered into a Takeover Agreement with the Navy in late November 2001. The project completion date under the Takeover Agreement was the same as required by the original contract, October 2002. Atherton completed the project in June 2003. When Atherton did not complete the project on the original schedule, the Navy withheld approximately $1 million liquidated damages. Plaintiff argues that this delay was due in large part to differing site conditions and to the bilateral modification between the Navy and Landmark for additional housing units.

DISCUSSION

Lumbermens’ Complaint alleges that certain costs of performing the defaulting contractor’s work were the Government’s fault. For example, plaintiff claims that the Navy paid Landmark for services that it had not performed and paid for goods that the contractor did not deliver. Lumbermens argues that the Navy should not have withheld liquidated damages because delays in completion of the project were the Government’s fault. It also contends that the Navy purchased materials from the defaulting contractor but did not deliver the materials to Lumbermens or to Atherton.

I. Equitable Subrogation

The Miller Act requires prime contractors to post performance bonds on all federal construction contracts. See 40 U.S.C. § 270a. The surety guarantees that a contract will be completed in the event of the [255]*255principal’s default and that the Government will not have to pay more than the contract price. See United States v. Munsey Trust Co., 332 U.S. 234, 244, 108 Ct.Cl. 765, 67 S.Ct. 1599, 91 L.Ed. 2022 (1947). This court has recognized Tucker Act jurisdiction over contract-based claims brought by a Miller Act surety based upon equitable subrogation. See Ins. Co. of the West v. United States, 243 F.3d 1367, 1375 (Fed.Cir.2001). The doctrine of equitable subrogation entitles a surety taking over contract performance or financing completion of the contract to rights that the defaulting contractor would have had against the Government. Fireman’s Fund Ins. Company v. United States, 909 F.2d 495, 499 (Fed.Cir.1990). If a surety expects the Government to withhold or to divert funds prior to default, however, the surety must notify the Government that the contractor cannot complete the contract. Ransom v. United States, 17 Cl.Ct. 263, 272 (1989), aff'd, 900 F.2d 242 (Fed.Cir.1990). The Government’s equitable duty to retain contract funds for the surety is triggered upon notice from the surety that the contractor is in default or that payment should be made to the surety. See Fireman’s Fund Ins. Company, 909 F.2d at 499 (holding that “only notice by the surety triggers the government’s equitable duty”).

Plaintiff did not notify the Government that Landmark was approaching default or that the Navy should withhold or divert progress payments. As such notice is required for a surety to retain its equitable rights against the Government, we must dismiss Counts 1 through 10 of plaintiffs Complaint.

II. Impairment of Suretyship

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hartford Fire Insurance v. United States
108 Fed. Cl. 525 (Federal Claims, 2012)
Lumbermens Mutual Casualty Co. v. United States
654 F.3d 1305 (Federal Circuit, 2011)
Insurance Co. of West v. United States
83 Fed. Cl. 535 (Federal Claims, 2008)
United States Fire Insurance v. United States
78 Fed. Cl. 308 (Federal Claims, 2007)
Nova Casualty Co. v. United States
72 Fed. Cl. 755 (Federal Claims, 2006)
Lumbermens Mutual Casualty v. United States
70 Fed. Cl. 94 (Federal Claims, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
67 Fed. Cl. 253, 2005 U.S. Claims LEXIS 238, 2005 WL 1983688, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lumbermens-mutual-casualty-co-v-united-states-uscfc-2005.