American Insurance v. United States

62 Fed. Cl. 151, 2004 U.S. Claims LEXIS 248, 2004 WL 2181560
CourtUnited States Court of Federal Claims
DecidedSeptember 28, 2004
DocketNo. 99-721C
StatusPublished
Cited by67 cases

This text of 62 Fed. Cl. 151 (American Insurance v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Insurance v. United States, 62 Fed. Cl. 151, 2004 U.S. Claims LEXIS 248, 2004 WL 2181560 (uscfc 2004).

Opinion

OPINION

ALLEGRA, Judge.

The plaintiff in this ease, American Insurance Company (American), served as the Miller Act surety on an Air Force construction contract. It seeks compensation from the United States alleging that the Air Force improperly released progress payments to the construction contractor, thereby impairing plaintiffs suretyship and increasing its costs when it was required to take over performance of the contract. Defendant has filed a motion for summary judgment, asserting that, in dispensing the funds in question, it breached no legally cognizable duty to plaintiff. Based on its review of the record and the parties’ assertions, and for the reasons that follow, the court finds the latter argument persuasive and GRANTS defendant summary judgment.

I. BACKGROUND

The relevant facts are relatively uncomplicated:

This case finds it origins in a February 14, 1994, Air Force contract with G & C Enterprises, Inc. (G & C) to construct an aircraft parking apron and a jet fuel storage facility at McGuire Air Force Base, New Jersey, for the firm fixed-price of $10,380,390. The contract had a completion date of June 15, 1996. It included the following standard FAR provision regarding progress payments:

The Government shall make progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished which meets the standards of quality established under the contract, as approved by the Contracting Officer. The Contractor shall furnish a breakdown of the total contract price showing the amount included therein for each principal category of the work, which shall substantiate the payment amount requested in order to provide a basis for determining progress payments, in such detail as requested by the Contracting Officer.

It further provided that—

If the Contracting Officer finds that satisfactory performance was achieved during [153]*153any period for which a progress payment is to be made, the Contracting Officer shall authorize payment to be made in full. However, if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved.

Pursuant to the Miller Act, 40 U.S.C. §§ 270a-270d (1994), plaintiff issued payment and performance bonds on behalf of G & C in connection with this contract.

During performance of the contract, G & C periodically submitted requests for progress payments to the contracting officer together with progress reports reflecting the work it had completed. The contracting officer reviewed these documents and issued payments pursuant to the contract provisions quoted above.

Around June of 1996, G & C began experiencing difficulties in completing the contract. The parties have slightly different accounts of what happened next. American alleges that it learned that G & C was in a state of financial difficulty and that, when contacted, the Air Force confirmed that G & C was making unsatisfactory progress and technically in default. Defendant alleges that, on June 22, 1996, a windstorm damaged facilities being constructed by G & C on a separate unrelated contract with the government. It contends that, for approximately six months, G & C failed to complete work on this unrelated contract, as well as the contract for which American served as surety. Defendant avers that it informed G & C that it was considering terminating the contacts for default. Finally, it asseverates that American and the Air Force entered into negotiations, wherein American assured the Air Force that it would provide G & C with the necessary financial resources to complete the project and the Air Force, in turn, assured American that it would not terminate its contact with G & C for default.1

Sometime after June of 1996 — and the record does not disclose exactly when — -American assumed defacto managerial control over the project in order to protect its financial interest. It entered into a subcontactor/takeover agreement with G & C and contracted with C & T Associates, Inc. (C & T) to complete the project for $2.7 million. G & C remained the contractor under the contact, but in name only, with American maintaining custody and control of the remaining contract funds, which were paid over to C & T. By letter dated May 23, 1997, American informed the Air Force of this arrangement.2 But, American did not enter into a formal takeover agreement with the Air Force; instead, it was agreed upon and understood by both parties that payments under the contract would continue to be made to G & C. By the time this letter was received, the Air Force had already paid G & C about 97 percent (all but $307,118) of the contract price; however, the plaintiff alleges — and defendant does not contest — that only 80 percent of the contract performance had been completed at that time.

On August 20,1999, plaintiff filed an action in this court asserting that defendant had overpaid G & C by $842,000, representing the difference between the 97 percent of the contract price paid to G & C and the 80 percent it alleges should have paid for the amount of work G & C had actually completed by the time American assumed perform-[154]*154anee under the contract. On June 7, 2004, oral argument was heard on the defendant’s motion for summary judgment.

II. DISCUSSION

Summary judgment is appropriate when there is no genuine dispute as to any material fact and the moving party is entitled to judgment as a matter of law. RCFC 56; Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247-48, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). Disputes over facts that are not outcome-determinative under the governing law — and there a several like that here — will not preclude the entry of summary judgment. Anderson, 477 U.S. at 248, 106 S.Ct. 2505. However, summary judgment will not be granted if “the dispute about a material fact is ‘genuine,’ that is, if the evidence is such that a reasonable [trier of fact] could return a verdict for the nonmoving party.” Id.; see also Matsushita Elec. Indus. Co., Ltd. v. Zenith Radio Corp., 475 U.S. 574, 587, 106 S.Ct. 1348, 89 L.Ed.2d 538 (1986); Becho, Inc. v. United States, 47 Fed.Cl. 595, 599 (2000). When reaching a summary judgment determination, a judge’s function is not to weigh the evidence, but to determine whether there is a genuine issue for trial. Anderson, 477 U.S. at 249, 106 S.Ct. 2505; see also Agosto v. INS, 436 U.S. 748, 756, 98 S.Ct. 2081, 56 L.Ed.2d 677 (1978) (“[A] [trial] court generally cannot grant summary judgment based on its assessment of the credibility of the evidence presented”). The judge must determine whether the evidence presents a disagreement sufficient to require submission to fact finding, or whether it is so one-sided that one party must prevail as a matter of law. Anderson, 477 U.S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barlow v. United States
Federal Claims, 2020
West v. United States
Federal Claims, 2019
Reid v. United States
Federal Claims, 2019
Scruggs v. United States
Federal Claims, 2018
Pryde v. United States
Federal Claims, 2017
Hendrickson v. United States
131 Fed. Cl. 489 (Federal Claims, 2017)
Langkamp v. United States
131 Fed. Cl. 85 (Federal Claims, 2017)
Vandesande v. United States
Federal Claims, 2017
Villars v. United States
126 Fed. Cl. 626 (Federal Claims, 2016)
Alamo v. United States
122 Fed. Cl. 638 (Federal Claims, 2015)
Northrop Grumman Computing Systems, Inc. v. United States
120 Fed. Cl. 460 (Federal Claims, 2015)
Urban v. United States
119 Fed. Cl. 57 (Federal Claims, 2014)
Lakeshore Engineering Services, Inc. v. United States
110 Fed. Cl. 230 (Federal Claims, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
62 Fed. Cl. 151, 2004 U.S. Claims LEXIS 248, 2004 WL 2181560, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-insurance-v-united-states-uscfc-2004.