United States Fire Insurance v. United States

78 Fed. Cl. 308, 2007 U.S. Claims LEXIS 293, 2007 WL 2705861
CourtUnited States Court of Federal Claims
DecidedSeptember 12, 2007
DocketNo. 03-2811C
StatusPublished
Cited by4 cases

This text of 78 Fed. Cl. 308 (United States Fire Insurance v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Fire Insurance v. United States, 78 Fed. Cl. 308, 2007 U.S. Claims LEXIS 293, 2007 WL 2705861 (uscfc 2007).

Opinion

OPINION

HORN, Judge.

This case arises from a construction project to renovate an electrical distribution system at McGuire Air Force Base, New Jersey. The contract was awarded to TriGems Builders, Inc. (Tri-Gems). United States Fire Insurance Company (U.S.Fire) issued the required performance and payment bonds1 on behalf of Tri-Gems. U.S. Fire was the surety on the project. After Tri-Gems was terminated for default, the Air Force and U.S. Fire entered into a takeover agreement for U.S. Fire to complete the construction project.

U.S. Fire brought a claim in this court, alleging that the Air Force had caused contract funds to be improperly depleted when the Air Force made improper payments to Tri-Gems for unsatisfactory and partially completed work. As a result, according to U.S. Fire, the surety was prejudiced since the remaining contract funds were less than they would have been had the contract been properly administered by the defendant. The surety alleges that the contract funds remaining after Tri-Gems’ default were insufficient to properly compensate U.S. Fire to complete the project, because the defendant had not paid funds to Tri-Gems in proportion to the work actually completed, which plaintiff claims was a contract requirement. U.S. Fire alleges that the Air Force made improper payments to Tri-Gems in the amount of $394,911.79 for work not pelformed and $296,839.20 for work improperly performed, totaling $691,750.99.

The government brought an early motion to dismiss for lack of subject matter jurisdiction. This court issued an opinion denying the government’s motion to dismiss. The court concluded that jurisdiction over claims brought by a surety stems from the doctrine of equitable subrogation, citing by way of support decisions of the United States Court of Appeals for the Federal Circuit. See U.S. Fire Ins. Co. v. United States, 61 Fed.Cl. 494, 499 (2004) (citing, e.g., Ins. Co. of the West v. United States, 243 F.3d 1367, 1370 (Fed.Cir.), reh’g denied, reh’g en banc denied (2001)).2 After a trial of the facts, the parties submitted post-trial briefs, followed by additional written submissions from both parties and additional motion practice. As [310]*310discussed below, the court finds in favor of the government.

FINDINGS OF FACT

The Department of the Air Force solicited bids for the contract at issue to renovate the electrical distribution system in military family housing, at McGuire Air Force Base, New Jersey. The contract, No. F28609-96-C0003, titled “Replace Overhead Power Distribution, FCN [Falcon Court North],” had a not-to-exceed price of $1,202,800.00. The contract required Tri-Gems to renovate the electrical distribution system by removing overhead power lines and by burying those lines in conduits underground.

The contract incorporated by reference a number of Federal Acquisition Regulation (FAR) clauses. Of particular relevance to this case, the contract incorporated FAR 52.232-5 (April 1989), titled “Payments Under Fixed-Price Construction Contracts.” The provision requires the government to make payments to the contractor based “on estimates of work accomplished which meets [sic] the standards of quality established under the contract, as approved by the Contracting Officer.” 48 C.F.R. § 52.232-5(b) (Oct. 1, 1995). In addition, FAR clause 52.236-15 (April 1984), “Schedules for Construction Contracts,” required Tri-Gems to provide the contracting officer with “a practicable schedule” showing how it “proposes to perform the work, and the dates on which the Contractor contemplates stalling and completing the several salient features of the work....” 48 C.F.R. § 52.236-15(a) (Oct. 1, 1995). The schedule was to be “a progress chart” which indicated “appropriately the percentage of work scheduled for completion by any given date during the period.” 48 C.F.R. § 52.236-15(a). Subsequently, also according to the FAR provision, Tri-Gems was supposed to “enter the actual progress on the chart,” and provide it to the contracting officer to determine if Tri-Gems was staying on schedule. 48 C.F.R. § 52.236-15(b) (Oct. 1, 1995). If the contractor fell behind the approved schedule, the contractor, at the direction of the contracting officer, was to take steps to correct and improve its progress. 48 C.F.R. § 52.236-15(b).

The deputy base civil engineer at McGuire AFB, Scott Wilson, after review by his inspectors, reviewed and recommended approval to the contracting officer of the contract progress schedules, along with completion percentages submitted by TriGems. At trial, Mr. Wilson testified that the “key thing” for him in reviewing the contract progress schedule was to watch out for “a contractor’s front loading,” and whether anything “jumped out” on his review. If the progress schedule, including the percentage of the total job completed, changed for any work element, Tri-Gems was required to submit a revised progress schedule for approval before progress reports for payment purposes could be submitted. The contract progress schedules were revised several times during contract performance. The contracting officer ultimately had to approve the progress schedules.

In addition to the payment clause, the contract also incorporated FAR 52.246-12 (July 1986), titled “Inspection of Construction,” which requires the contractor to “maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to the contract requirements.” 48 C.F.R. § 52.246-12(b) (Oct. 1,1995). FAR provision 52.236-6 (April 1984), titled “Superintendence by the Contractor,” also required TriGems to have a supervisor on the work site at all times to “superintend the work.” 48 C.F.R. § 52.236-6 (Oct. 1, 1995). In addition, FAR 52.236-5 (April 1984), titled “Material and Workmanship,” required that, “[a]ll work under this contract shall be performed in a skillful and workmanlike manner.” 48 C.F.R. § 52.236-5(c) (Oct. 1,1995).

With regard to progress payments for materials delivered to the site, the contract at issue also contained Air Mobility Command FAR Supplement (AMCFARS) clause 5352.232- 1000 (May 1991), titled “Payment for Materials Stored on Site,” which complemented the payments clause included in the contract and noted earlier, FAR clause 52.232- 5 (April 1989), titled “Payments Under Fixed-Price Construction Contracts.” AMCFARS clause 5352.232-1000(b)(3)-(4) required the contractor to submit invoices for [311]*311high-cost items which must be delivered to an approved location on-site. AMCFARS clause 5352.232-1000(b)(4) also required the contractor to certify that none of the materials would be removed without written permission from the contracting officer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hartford Fire Insurance v. United States
108 Fed. Cl. 525 (Federal Claims, 2012)
United Surety & Indemnity Co. v. United States
90 Fed. Cl. 203 (Federal Claims, 2009)
Insurance Co. of West v. United States
83 Fed. Cl. 535 (Federal Claims, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
78 Fed. Cl. 308, 2007 U.S. Claims LEXIS 293, 2007 WL 2705861, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-fire-insurance-v-united-states-uscfc-2007.