Balboa Insurance Company v. The United States

775 F.2d 1158, 33 Cont. Cas. Fed. 74,051, 9 Cl. Ct. 1158, 1985 U.S. App. LEXIS 15308
CourtCourt of Appeals for the Federal Circuit
DecidedOctober 28, 1985
DocketAppeal 85-823
StatusPublished
Cited by131 cases

This text of 775 F.2d 1158 (Balboa Insurance Company v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Balboa Insurance Company v. The United States, 775 F.2d 1158, 33 Cont. Cas. Fed. 74,051, 9 Cl. Ct. 1158, 1985 U.S. App. LEXIS 15308 (Fed. Cir. 1985).

Opinion

JACK R. MILLER, Senior Circuit Judge.

This is an appeal by a Miller Act surety from a partial summary judgment by the Claims Court (No. 6-82C (Oct. 4, 1984)) denying the surety’s claim for the recovery of a progress payment of $23,163.50, alleged by the surety to have been improperly paid the prime contractor by the Government after it had notified the Government that the contractor was in default. We vacate and remand for further proceedings.

BACKGROUND

Balboa Insurance Company (“Balboa”) was the surety for the contractor, Chemical Engineers & Constructors, Inc. (“CEC”), on contract N62467-79-C-2604 (“contract”) entered into August 8, 1979, for alterations to an existing structure at the Naval Training Center, Orlando, Florida. Balboa provided CEC Miller Act (40 U.S.C. §§ 270a- *1160 270d (1982)) payment and performance bonds.

The fifth payment, at issue here, was requested from the Government by CEC on January 30, 1980. According to Navy interoffice memoranda, the amount of completed performance under the contract at that time was 91%. Payment was authorized on February 1, 1980. Balboa received written notice by early February that led it to believe that CEC was in financial straits and would not be able to fulfill its payment and performance obligations. On February 14, 1980, it addressed a letter to this effect to the Contracting Officer (received the next day) demanding that no further contract funds be released without its consent. A Government check in the amount of $23,-163.50 was issued and disbursed to CEC on February 21, 1980, nevertheless.

Subsequently, CEC authorized the Government to make future contract payments directly to Balboa. (The sixth progress payment check, also issued to CEC, was disputed in the Claims Court, but is not at issue in this appeal.) In June, 1980, the Government terminated the contract, and another firm completed the contract. Balboa asserted that it should have received the fifth payment check and, when the Government denied liability, sought recovery of that amount in the U.S. Claims Court. 1

The opinion of the Claims Court was issued from the bench. The court granted the Government’s motion for summary judgment and denied the Government’s liability to the surety. It is from this judgment that Balboa appeals.

OPINION

A. Jurisdiction

The Government argues that because it owes no duty to protect the surety from its principal, CEC, during performance, payment to the contractor is “not an appropriate subject for judicial review to determine whether the Government considered the surety’s interests.” Further, it contends that a surety is similar to a subcontractor, who is not in privity of contract with the Government. Thus, it concludes that neither the Claims Court nor this court possesses jurisdiction over the suit of a surety against the United States to recover an allegedly improperly paid progress payment.

Decisions of our predecessor court and the Supreme Court make clear that a surety is not in the same position as that of a subcontractor or materialman. E.g., United Electric Corp. v. United States, 647 F.2d 1082, 1086 (Ct.Cl.), cert. denied, 454 U.S. 863, 102 S.Ct. 322, 70 L.Ed.2d 163 (1981). A suretyship is the result of a three-party agreement, whereby one party (the surety) becomes liable for the principal’s or obligor’s debt or duty to the third party obligee, see United States v. United States Fidelity & Guaranty Co., 236 U.S. 512, 35 S.Ct. 298, 59 L.Ed. 696 (1915). Both the obligor-principal (the prime contractor)-and the surety are liable to the obligee (here, the Government), and no suretyship exists in the absence of any of the three parties. In contrast to a subcontractor, which has no obligations running directly to or from the Government, United States v. Munsey Trust Co. of Washington, D.C., 332 U.S. 234, 241, 67 S.Ct. 1599, 1602, 91 L.Ed. 2022 (1947) (and therefore possesses no enforceable rights against the United States), a surety, as bondholder, is as much a party to the Government contract as the contractor. If the surety fails to perform, the Government can sue it on the bonds. E.g., Carchia v. United States, 485 F.2d 622 (Ct.Cl. 1973).

Although it is conceivable that under certain circumstances a surety could assert rights against the Government under the *1161 third-party beneficiary rule, see Montana Bank of Circle, N.A. v. United States, 7 Cl.Ct. 601, 611 (1985), or even as one in privity in contract with the Government, see Hanover Insurance Co. v. United States, 279 F.Supp. 851, 852 (S.D.N.Y.1967); cf. Martin v. National Surety Co., 300 U.S. 588, 598, 57 S.Ct. 531, 535, 81 L.Ed. 822 (1937) (“The terms of the bond are read into the contract”), the traditional means of asserting a surety’s claim is under the equitable doctrine of subrogation. Almost ninety years ago, the Supreme Court stated: “That [plaintiff], as surety on the original contract, was entitled to assert the equitable doctrine of subrogation is elementary.” Prairie State Bank v. United States, 164 U.S. 227, 231, 17 S.Ct. 142, 144, 41 L.Ed. 412 (1896). Later, in United States Fidelity & Guaranty Co. v. United States, 475 F.2d 1377 (Ct.Cl.1973) (hereinafter United States Fidelity), the Court of Claims clarified the respective rights of subcontractors and Miller Act sureties to sue the United States by explaining:

[T]he surety was entitled to the benefit of all the rights of the laborers and materialmen whose claims it paid and those of the contractor whose debts it paid. The surety then is subrogated to the rights of the contractor who could sue the Government since it was in privity of contract with the United States. The surety is likewise subrogated to the rights of the laborers and materialmen who might have superior equitable rights to the retainage but no right to sue the [United States].

475 F.2d at 1382.

The Government further contends that neither the Claims Court nor this court has jurisdiction over a claim by a surety for non-retained funds, as opposed to those not yet disbursed. It premises this argument on the assertion that

[C]ases involving a surety’s claim to retainages, ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Argonaut Insurance v. Falcon V
44 F.4th 348 (Fifth Circuit, 2022)
Hanover Insurance Company (The) v. United States
133 Fed. Cl. 633 (Federal Claims, 2017)
Hartford Fire Insurance Co. v. United States
254 F. Supp. 3d 1333 (Court of International Trade, 2017)
United States v. American Home Assurance Co.
113 F. Supp. 3d 1297 (Court of International Trade, 2015)
Colonial Surety Co. v. United States
108 Fed. Cl. 622 (Federal Claims, 2013)
Hartford Fire Insurance v. United States
108 Fed. Cl. 525 (Federal Claims, 2012)
City of Oklahoma City v. First American Title & Trust Co.
2013 OK CIV APP 42 (Court of Civil Appeals of Oklahoma, 2012)
Lumbermens Mutual Casualty Co. v. United States
654 F.3d 1305 (Federal Circuit, 2011)
Haddon Housing Associates, LLC v. United States
92 Fed. Cl. 8 (Federal Claims, 2010)
CCA Associates v. United States
91 Fed. Cl. 580 (Federal Claims, 2010)
United Surety & Indemnity Co. v. United States
90 Fed. Cl. 203 (Federal Claims, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
775 F.2d 1158, 33 Cont. Cas. Fed. 74,051, 9 Cl. Ct. 1158, 1985 U.S. App. LEXIS 15308, Counsel Stack Legal Research, https://law.counselstack.com/opinion/balboa-insurance-company-v-the-united-states-cafc-1985.