United Surety & Indemnity Co. v. United States

87 Fed. Cl. 580, 2009 U.S. Claims LEXIS 230, 2009 WL 1916294
CourtUnited States Court of Federal Claims
DecidedJune 30, 2009
DocketNo. 08-791C
StatusPublished
Cited by5 cases

This text of 87 Fed. Cl. 580 (United Surety & Indemnity Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Surety & Indemnity Co. v. United States, 87 Fed. Cl. 580, 2009 U.S. Claims LEXIS 230, 2009 WL 1916294 (uscfc 2009).

Opinion

MEMORANDUM OPINION AND FINAL ORDER

BRADEN, Judge.

I. RELEVANT FACTUAL BACKGROUND.1

On February 6, 2001, the United States Postal Service (“USPS”) awarded Selpa Construction & Rental Equipment Corporation (“Selpa”) a contract, # 332495-00-B-0221 (“the Contract”), to construct a post office in Fajardo, Puerto Rico. See Compl. ¶ 4. The initial amount of the Contract was $2,288,000.00, but the amount was later increased to $2,568,648.60 through change orders. Id. Clause B-8, found in the USPS Procurement Manual and incorporated into the Contract, prohibited assignment of the Contract to any party other than a bank, trust company, or financial institution.2 See Gov’t Ex. B.

[584]*584As required by the Miller Act, 40 U.S.C. § 3131 et seg.,3 Selpa obtained two bonds from United Surety & Indemnity Company (“United Surety”), a performance and payment bond surety incorporated under the laws of the Commonwealth of Puerto Rico. See Compl. ¶¶ 2, 5. United Surety issued a payment bond for $1,144,000.00 and a performance bond for $2,288,000.00 in partial consideration of Selpa’s execution of an August 26, 1996 General Agreement of Indemnity (“General Agreement”). See Pl.Ex. 2, 3. Pursuant to the General Agreement, Selpa assigned and declared United Surety’s rights to be subrogated to Selpa’s rights. See PI. Ex. 3. Article 19 of the General Agreement provided that United Surety had the right to “control, administer, operate or manage any matters connected with the performance of any contract [covered by such bond or bonds] for the purpose of minimizing any possible loss or ultimate loss to [United Surety].” Pl.Ex. 3.

Pursuant to the Contract, Selpa agreed to furnish all labor and materials and perform all work. See Pl.Ex. 1. During construction of the post office, however, Selpa’s “financial condition precluded it from performing under the Contract.” Compl. ¶ 8. On October 17, 2002, USPS informed Selpa that USPS had received subcontractor requests for payment. See Pl.Ex. 8. The Complaint alleges that sometime thereafter United Surety “agreed to provide [Selpa] the necessary funds to complete the [p]roject and, thus, became a performing surety.” Compl. ¶ 8.

On November 12, 2002, United Surety advised USPS that:

On behalf of United Surety & Indemnity Company, the insurance company that issued Payment and Performance Bond No. 0172359 for the “Fajardo PR Main Post Office, New Construction Ownwd [sic] FMS # A42128; Contract No. 332495-00-B-0221”, you are hereby required that from this date on, all payments due to Selpa Construction Corp. under the construction contract for said project, be made by cheeks payable to United Surety & Indemnity Company and Selpa Construction Corp.
Pursuant to Article 19 of the General Agreement of Indemnity executed, among others, by Selpa Construction Corp., United Surety & Indemnity Company has taken control of the proceeds of the construction contract.
Should you have any questions in relation to this requirement, please call the undersigned.

Pl.Ex. 4.

On January 27, 2003, Selpa’s bank, Scotia-bank de Puerto Rico (“Seotiabank”), notified [585]*585USPS that all contract payments should be made jointly to Selpa and Seotiabank, pursuant to a valid assignment of contract payments signed by Selpa. See Pl.Ex. 5. On February 4, 2003, USPS sent Selpa a letter requesting payment instructions, in light of Scotiabank’s January 27, 2003 request for remittance of all future payments and a February 3, 2003 telephone conversation, wherein Selpa requested that all future payments be made to United Surety and Selpa. Id.

On or about March 26, 2003, USPS made a progress payment in the amount of $201,795.00 to Selpa and Seotiabank. See Compl. ¶ 12. By this time, United Surety had expended at least $168,481.01 to complete the project, and “USPS was well aware that [United Surety] had been financing the project and that multiple claims were being received from suppliers.” Id. ¶¶ 14-15. On April 3, 2003, Selpa sent a letter to reassure USPS that Selpa, with the assistance of United Surety, intended to finish the project, and requested that fifty percent of the retainage be paid to United Surety:

As we have notified you before, in the last few months we have been working hard [o]n the project with the assistance of the surety company United Surety & Indemnity Co., making the payments of payroll and suppliers of the forementioned project. Also, as you notified us some time ago, the bank, Seotiabank of Puerto Rico[,] demanded in a letter that all the remaining payments of the contract principal, not the retainage must be directed to them.
[It] is for that reason, that we are gently requesting you, that the U.S.P.S. can issue a partial check of the 50 (fifty) percent of the amount of that retainage, payment to United Surety & Indemnity Co. In that way, that check will reduce, along with another check that we have already delivered to the Surety, the amount that they have paid already for the project and is a good will gesture that shows that Selpa wants to finish his job with the USPS, pay all the people involved in this project and follow the agreements with the Surety.

Pl.Ex. 7.

By an April 8, 2003 letter, United Surety’s counsel requested that USPS reimburse United Surety for the funds disbursed on March 26, 2003 to Selpa and Seotiabank. See Pl.Ex. 9. United Surety’s counsel informed USPS that “[w]hen [United Surety] questioned Selpa regarding the receipt of the aforementioned payment it disclosed that the funds had been deposited in Seotiabank de Puerto Rico since they were allegedly assigned to said banking institution under certain Assignment of Contract Payments executed on November 17, 2000.” Id. Because United Surety informed USPS on November 12, 2002 that all future payments should be made to Selpa and United Surety, the March payment made to Selpa and Seotiabank was “null and void.” Id.

On July 8, 2003, the Contract was terminated for default. See Compl. ¶ 17. On January 28, 2004, United Surety and USPS entered into a Takeover Agreement to complete the project. Id. The Takeover Agreement “outlined the then-current contract balance of $390,239.19[,] including the payment of $201,795.00 to Selpa, and set forth the terms on which [United Surety] would complete the project.” Gov’t Mot. at 4; Gov’t Ex. C. The project was completed at a net cost to United Surety of $2,034,936.42. See Compl. ¶ 18. To date, USPS has not paid United Surety the $201,795.00 payment made to Selpa and Seotiabank. Id. ¶ 20.

II. PROCEDURAL HISTORY.

On November 4, 2008, United Surety filed a Complaint in the United States Court of Federal Claims, together with exhibits, alleging wrongful disbursement of contract funds and equitable subrogation. See Compl. ¶¶ 29-30. United Surety requests damages in the amount of $201,795.00, plus interest, as well as certain costs and expenses. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brittani Nicole Williams v. United States
112 Fed. Cl. 67 (Federal Claims, 2013)
Colonial Surety Co. v. United States
108 Fed. Cl. 622 (Federal Claims, 2013)
Hartford Fire Insurance v. United States
108 Fed. Cl. 525 (Federal Claims, 2012)
M.E.S., Inc. v. United States
104 Fed. Cl. 620 (Federal Claims, 2012)
United Surety & Indemnity Co. v. United States
90 Fed. Cl. 203 (Federal Claims, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
87 Fed. Cl. 580, 2009 U.S. Claims LEXIS 230, 2009 WL 1916294, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-surety-indemnity-co-v-united-states-uscfc-2009.