United Surety & Indemnity Co. v. United States

90 Fed. Cl. 203, 2009 U.S. Claims LEXIS 676, 2009 WL 4932729
United States Court of Federal Claims·Decided December 16, 2009·No. No. 08-791C·Published·Cited by 1 cases

Opinion

MEMORANDUM OPINION AND ORDER DENYING RECONSIDERATION

SUSAN G. BRADEN, Judge.

On July 13, 2009, Plaintiff filed a Motion For Reconsideration (“Pl.Mot.”) of the June 30, 2009 Memorandum Opinion and Final Order in United Surety and Indemnity Co. v. United States, 87 Fed.Cl. 580 (2009). For the reasons discussed herein, Plaintiffs Motion For Reconsideration is denied.

I. STANDARD OF REVIEW FOR MOTION FOR RECONSIDERATION, PURSUANT TO RCFC 59.

A motion for reconsideration must be supported “by a showing of extraordinary [205]*205circumstances which justify relief.” Caldwell v. United States, 391 F.3d 1226, 1235 (Fed.Cir.2004) (quoting Fru-Con Constr. Corp. v. United States, 44 Fed.Cl. 298, 300 (1999)). The decision to grant or deny a motion for reconsideration lies within the discretion of the court. Yuba Natural Res., Inc. v. United States, 904 F.2d 1577, 1583 (Fed.Cir.1990) (holding that “the decision whether to grant reconsideration lies largely within the discretion of the [trial] court”). A movant cannot prevail by “merely reasserting arguments which were previously made and were carefully considered by the court.” Id.; see also Bishop v. United States, 26 Cl.Ct. 281, 286 (1992) (holding that reconsideration “is not intended to give an unhappy litigant an additional chance to sway the court.”). To prevail on a motion for reconsideration, a movant must show that: (1) an intervening change in the controlling law has occurred; (2) new evidence is now available; or (3) the motion is necessary to prevent manifest injustice. Fru-Con Constr. Corp., 44 Fed.Cl. at 301.

II. DISCUSSION.

A. The Parties’ Arguments.

1. Plaintiffs Argument.

Plaintiff argues that the court’s holding in United Surety did not address Plaintiffs “pleading that the Government had to take [Plaintiffs] interest into account prior to disbursing funds to the Bank and the [Third-Party Defendant], and that by not doing so it abused its discretion causing damages.” PI. Mot. at 4. Plaintiff contends that “the Government owed it some consideration in the managing of funds in addition to and regardless of, any duty that might arise after notice of default or imminent default.” Id. at 10 (emphasis in the original). As the United States Court of Appeals for the Federal Circuit held in Balboa Ins. Co. v. United States, 775 F.2d 1158, 1160 (Fed.Cir.1985), “a surety, as a bondholder, is as much a party to the Government contract as the contractor.” Therefore, Plaintiff concludes that, “even if the heightened standard of care towards a surety’s interest is not triggered if notification by the surety is not adequate, as the court has concluded, or by actual performance, as [Plaintiff] argued, the Government could not ignore the surety’s interest.” PL Mot. at 11. Plaintiff asserts that this claim specifically was pled in the November 4, 2008 Complaint (“Compl.”). Id. at 12 (citing Compl. ¶ 25) (“The [Government] was required to take into account prior to disbursing the Check to Scotiabank the Former Contractor. By not doing so the USPS abused its discretion and caused damages to USIC in the amount of $201,795.00.”).

Plaintiff also argues that the Government has a duty to exercise discretion in the administration of the contract “for the purpose of promoting performance.” Id. at 15 (citing United States Fire Ins. v. United States, 78 Fed.Cl. 308, 334 (2007)). The Government abused this discretion when it disbursed the progress payment, knowing it would not be used to complete the construction project, but instead to satisfy the Third-Party Defendant’s debt. Id. at 16-18. Therefore, Plaintiffs claims should survive a motion to dismiss. Id.

In addition, the court failed to address Plaintiffs claim that the Government, in making the disputed progress payment, violated the duty to administer the contract in a responsible manner. Id. at 18. Plaintiff contends that the Government had a duty “to administer the contract, during the course of its performance, in a way that does not materially increase the risk that was assumed by the surety when the contract was bonded.” Id. (citing to National Surety Corp. v. United States, 118 F.3d 1542, 1546 (Fed.Cir.1997)). This duty is “implicit in the three-party relationship between [the Government], the contractor, and the surety.” PL Mot. at 19. The Government acted unlawfully when it made a progress payment to the contractor and did not consider the surety’s interests as a third-party to the contract, “regardless of any notice of default or possibility of default.” Id. at 18-19 (emphasis omitted).

2. The Government’s Response.1

The Government responds that Plaintiffs Motion For Reconsideration argues “one of [206]*206the same arguments” made in Plaintiffs March 2, 2009 “Response To The Government’s Motion To Dismiss.” Gov’t Opp. at 2. Therein, Plaintiff devoted eight pages to the same arguments reasserted in Plaintiffs Motion For Reconsideration. Id. The court considered and rejected Plaintiffs theory that notice is unnecessary, where the surety already was performing under the contract. Id. at 3 (citing United Surety, 87 Fed.Cl. at 589). As the court concluded, “the disposi-tive question is not whether notice was necessary, but whether or not the surety exercised its duty to provide the Government with adequate notice to trigger the Government’s stakeholder duty.” Id. (quoting United Surety, 87 Fed.Cl. at 589). Therefore, Plaintiffs Motion For Reconsideration simply restates an argument that was fully considered and rejected by the court. Id. at 3-4.

Plaintiff also fails to establish any manifest error or mistake of fact. Id. Plaintiff relies on dicta from Balboa that has been subsequently overruled. Id. at 4. As the United States Court of Appeals for the Federal Circuit explained in Ins. Co. of the West v. United States, 243 F.3d 1367 (Fed.Cir.2001), “[a]lthough in Balboa we reserved the question whether there was a contract or privity between the [Gjovernment and a surety ... we have since held that there is no such relationship.” Id. at 1370. In addition, in Balboa the surety gave adequate notice of default before the allegedly improper payments. Gov’t Opp. at 4-5 (citing 775 F.2d at 1160). Balboa’s discussion of the Government’s duty to exercise discretion in making payments to the contractor or surety arose only after the surety had given adequate notice of default to the Government. Id. at 5.

Plaintiff also misreads National Surety to create a duty to make payments to the surety. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

United Surety & Indemnity Co. v. United States, 90 Fed. Cl. 203, 2009 U.S. Claims LEXIS 676, 2009 WL 4932729 (uscfc 2009).

90 Fed. Cl. 203 (United Surety & Indemnity Co. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Magnum Opus Technologies, Inc. v. United States
94 Fed. Cl. 553 (Federal Claims, 2010)