National American Insurance v. United States

498 F.3d 1301, 78 Fed. Cl. 1301, 2007 U.S. App. LEXIS 20058, 2007 WL 2388896
CourtCourt of Appeals for the Federal Circuit
DecidedAugust 23, 2007
Docket2007-5016
StatusPublished
Cited by39 cases

This text of 498 F.3d 1301 (National American Insurance v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National American Insurance v. United States, 498 F.3d 1301, 78 Fed. Cl. 1301, 2007 U.S. App. LEXIS 20058, 2007 WL 2388896 (Fed. Cir. 2007).

Opinion

PROST, Circuit Judge.

The United States appeals a September 6, 2006, decision by the United States Court of Federal Claims granting summary judgment that the government violated its duty as stakeholder in a Miller Act payment bond case by making final *1303 payment to a government contractor after being notified by the payment bond surety, National American Insurance Company (“NAICO”), that it was asserting a right to contract funds after having fully discharged the debt of the contractor. Nat’l Am. Ins. Co. v. United States, 72 Fed.Cl. 451 (2006). Because the Court of Federal Claims correctly held that NAICO was equitably subrogated to the rights of the contractor whose debt it discharged, we affirm.

I. BACKGROUND

On June 11, 1996, Innovative PBX Services, Inc. (“IPBX”) contracted with the United States Small Business Administration to replace the telephone system at the Department of Veterans Affairs Medical Center in Palo Alto, California. IPBX subcontracted part of this work to Nortel Communications Systems, Inc., which was succeeded by Wiltel Communications, LLC (“Wiltel”). As required by the Miller Act, 40 U.S.C. § 3131(b), IPBX executed payment and performance bonds in favor of the United States, with NAICO as the surety. 1

After completion of its contract work, Wiltel notified NAICO that it was owed approximately $675,000 for labor and materials that IPBX had failed to pay. Wiltel then asserted a Miller Act claim under the payment bond issued to NAICO. NAICO settled Wiltel’s claim, notified the government that no additional payments were to be made to IPBX due to the Miller Act claim, and requested that all remaining contract funds be held for NAICO’s benefit. The government, however, did not follow NAICO’s request and made its final contract payment to IPBX. As a result, NAICO filed a complaint in the Court of Federal Claims seeking damages of approximately $280,000 from the government. The Court of Federal Claims granted summary judgment in favor of NAICO, holding that: (1) NAICO, as a surety that had made payments on a payment bond and satisfied all outstanding claims, was equitably subrogated to the rights of IPBX; (2) the Tucker Act’s waiver of sovereign immunity extended to NAICO as an equitable subrogee of IPBX; and (3) the government violated its duty as stakeholder in the payment bond by making final payment to IPBX after being notified by NAICO that it was asserting a right to contract funds. The United States appeals to this court. We have jurisdiction pursuant to 28 U.S.C. § 1295(a)(3).

II. DISCUSSION

A. Standard of Review

Summary judgment is properly granted when, viewing the evidence in the light most favorable to the non-movant, the record indicates there is “no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56(c); Celotex Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). We review a grant of summary judgment by *1304 the Court of Federal Claims de novo to determine whether the summary judgment standard has been correctly applied. Cienega Gardens v. United States, 194 F.3d 1231, 1238 (Fed.Cir.1998).

B. Payment Bond Surety Subrogation Rights

On appeal, the United States asserts that NAICO can only stand in the shoes of the subcontractor whom it paid, and since the subcontractor has no privity with the United States, there can be no Tucker Act waiver of sovereign immunity. If we disagree, the United States does not contest its liability to NAICO on the facts of this case. Thus, this case involves only the subrogation rights of a payment bond surety. Generally, “[a] surety bond creates a three-party relationship, in which the surety becomes liable for the principal’s debt or duty to the third party obligee (here, the government).” Ins. Co. of the W. v. United States, 243 F.3d 1367, 1370 (Fed.Cir.2001) (“ICW”) (citing Balboa Ins. Co. v. United States, 775 F.2d 1158, 1160 (Fed.Cir.1985)). If a surety is unable to rely on privity of contract as the jurisdictional basis for a claim against the government, the surety may be able to invoke the doctrine of equitable subrogation to step into the shoes of the contractor for the purpose of satisfying the jurisdictional requirements of the Tucker Act, 28 U.S.C. § 1491(a). See ICW, 243 F.3d at 1373 (stating that the Tucker Act is not limited to claims asserted by the original claimant). Equitable subrogation “ ‘is a creature of equity; is enforced solely for the purpose of accomplishing the ends of substantial justice; ... is independent of any contractual relations between the parties,’ ” Pearlman v. Reliance Ins. Co., 371 U.S. 132, 136 n. 12, 83 S.Ct. 232, 9 L.Ed.2d 190 (1962) (quoting Memphis & L.R.R. Co. v. Dow, 120 U.S. 287, 301-02, 7 S.Ct. 482, 30 L.Ed. 595 (1887)), and has a long history in settled case law.

In 1896, the Supreme Court held that a surety could apply the doctrine of equitable subrogation in seeking retained funds from the government for completing performance of a government contract under a performance bond. Prairie State Nat’l Bank v. United States, 164 U.S. 227, 240, 32 Ct.Cl. 614, 17 S.Ct. 142, 41 L.Ed. 412 (1896). The Court extended its holding to a payment bond surety in Henningsen v. United States Fidelity & Guaranty Co., 208 U.S. 404, 411, 28 S.Ct. 389, 52 L.Ed. 547 (1908).

In United States v. Munsey Trust Co., 332 U.S. 234, 108 Ct.Cl. 765, 67 S.Ct. 1599, 91 L.Ed. 2022 (1947), the Supreme Court revisited the rights of sureties under the doctrine of equitable subrogation. In that case, the government, prior to releasing retained funds due a payment bond surety, deducted a portion of the amount that the contractor owed the government for failing to complete the contract. Id. at 238, 67 S.Ct. 1599.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pressly v. United States
Federal Claims, 2021
Oldham v. United States
Federal Claims, 2021
Bradley v. United States
Federal Claims, 2021
Ats Ford Drive Investment, LLC
Federal Claims, 2021
Bailey v. United States
Federal Claims, 2019
Kelly Services, Inc. v. Creative Harbor, LLC
846 F.3d 857 (Sixth Circuit, 2017)
Adams v. United States
125 Fed. Cl. 608 (Federal Claims, 2016)
Salter v. United States
119 Fed. Cl. 359 (Federal Claims, 2014)
Casitas Municipal Water District v. United States
708 F.3d 1340 (Federal Circuit, 2013)
Colonial Surety Co. v. United States
108 Fed. Cl. 622 (Federal Claims, 2013)
M.E.S., Inc. v. United States
104 Fed. Cl. 620 (Federal Claims, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
498 F.3d 1301, 78 Fed. Cl. 1301, 2007 U.S. App. LEXIS 20058, 2007 WL 2388896, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-american-insurance-v-united-states-cafc-2007.