United Electric Corp. v. United States

647 F.2d 1082, 28 Cont. Cas. Fed. 81,334, 227 Ct. Cl. 236, 1981 U.S. Ct. Cl. LEXIS 198
CourtUnited States Court of Claims
DecidedApril 22, 1981
DocketNo. 10-80C
StatusPublished
Cited by38 cases

This text of 647 F.2d 1082 (United Electric Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Electric Corp. v. United States, 647 F.2d 1082, 28 Cont. Cas. Fed. 81,334, 227 Ct. Cl. 236, 1981 U.S. Ct. Cl. LEXIS 198 (cc 1981).

Opinion

DAVIS, Judge,

delivered the opinion of the court:

[237]*237We are faced, once again, with the uneasy problem of whether a subcontractor has standing to sue the United States for compensation due it under a subcontract with a government contractor where both the prime and the surety have failed or refused to make the payment, and the Government retains funds owing on the contract. This time the question arises on the following claim (as asserted in the petition): In 1978, plaintiff United Electric Corporation (United) made a contract with Standard Conveyor Co. (Standard) to supply over $100,000 worth of electrical components which were to become part of a mechanized materials-handling system that Standard contracted with the United States Air Force to fabricate, test and install at McClellan Air Force Base. The Air Force required Standard to post a payment bond of $494,665.50 under the Miller Act, 40 U.S.C. § 270a, an amount which United alleges was legally inadequate. Plaintiff says it performed its contractual obligations but did not receive payment from Standard which had filed a petition in bankruptcy in 1979, and is allegedly unable to pay. United then attempted to recover its compensation from Standard’s surety, but the surety also refused compensation on the ground that the bond did not cover the materials provided by plaintiff.1 However, plaintiff alleges the Government still retains a percentage of the contract in an amount ($550,000) much greater than United’s demand ($107,958.42).

Plaintiff seeks judgment in this court from the United States for its contract price, asserting that the Air Force acted negligently and failed to comply with the requirements of the Miller Act, thus creating an equitable lien in United’s favor on contract retainages (or other funds which should have been but were not retained by defendant). Defendant has moved to dismiss the petition, saying that the subcontractor has no claim within this court’s jurisdiction.

The obvious difficulty for plaintiff is that the full court has already decided, in a comparable context, that we cannot entertain a subcontractor’s claim which the prime [238]*238(or a higher sub) and the surety have not paid. United States Fidelity & Guaranty Co. v. United States, 201 Ct. Cl. 1, 475 F.2d 1377 (1973) (USF&G). There, the Miller Act surety had fully met its obligations under the payment and performance bonds, but certain laborers and materialmen remained unpaid. The surety and the unpaid subcontractors sued here, raising claims against contract retainages in the hands of the Government, and also alleging improper progress payments. The Government claimed priority to the retained funds on the basis of a tax lien and other unmet obligations owing to it by the prime contractor. After satisfaction of these debts, approximately $4,000 in unex-pended contract funds remained — an amount far smaller than that still owed to the subcontractors. On these facts we held that (1) the surety did not have priority against the United States for amounts necessary to satisfy tax and other obligations running from the prime to the Government; (2) the surety could not share in unexpended sums retained under the contract because it had not fully paid all of the laborers and materialmen (although it had completely satisfied its payment bond obligation to them); and (3) the subcontractors did not have standing to sue the United States on their own behalf.

The USF&G issue which is now critical concerns the last of these holdings — the right of subcontractors to sue the United States directly for their compensation. Relying on precedent from this court as well as the Supreme Court, we ruled specifically that such a right does not exist. This en banc holding is of course, binding on this panel.2 But we can ask the full en banc court to reconsider that decision if we now think it wrong or questionable. We heard oral argument on the present case because a post -USF&G ruling of the Tenth Circuit could be thought to undermine our decision in USF&G (and is so presented by United). Kennedy Electric Co. v. United States Postal Service, 508 F.2d 954 (10th Cir. 1974). Because of Kennedy, which United emphasizes strongly, we have recanvassed the ground and now conclude that that case is quite distinguishable and that we have no reason to question USF&G.

[239]*239In Kennedy, an electrical subcontractor which had performed work on a building for the Post Office Department (predecessor to the United States Postal Service) brought suit against the Postal Service for its compensation. That claimant had not been paid for its labor and materials because the prime had become insolvent and no Miller Act bonds had been posted. The Tenth Circuit, affirming a district court judgment in plaintiffs favor, held that the subcontractor had an equitable lien on contract retainages and amounts which had been improperly paid to the contractor’s assignee in violation of Postal Service regulations.

Kennedy is quite different from both USF&G and the present case on a crucial point. In Kennedy the Postal Service, rather than the United States, was the defendant. The Postal Service is an independent establishment with the general capacity (given it by Congress) to "sue and be sued,” see 39 U.S.C. § 401,3 not a subordinate unit of the Federal Government like the Air Force. In Kennedy, therefore, there was no bar of sovereign immunity to the subcontractor’s suit, and the Postal Service was found to be "just as amenable to the judicial process as is a private enterprise.” Id. at 957, 960. See also, F.H.A. v. Burr, 309 U.S. 242, 245 (1940). Indeed, while discussing our decision in USF&G, the Kennedy court specifically stated:

USF&G is a different case from that at bar. We do not have a standing question. Our suit is against an independent establishment having the power to sue and be sued. [508 F.2d at 959.]

The broad, unlimited legislative declaration that the Postal Service could "be sued” left the Tenth Circuit free to apply doctrines applicable to private persons, including principles of restitution, tort-law, and "contracts implied in law,” and thereby to conclude that the equities of that subcontractor were paramount to those of the Postal Service, and that "[i]n like circumstances a private enterprise could not take [240]*240advantage of the misconduct of its transferor.” 508 F.2d at 960.

The foundation of USF&G, to the contrary, is that suit here against the United States under 28 U.S.C. § 1491 is not unlimited and does not put the United States on the same plane, in all respects, as if it were a private entity.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Telzrow v. United States
127 Fed. Cl. 115 (Federal Claims, 2016)
Kenneth Earman v. United States
114 Fed. Cl. 81 (Federal Claims, 2013)
Vladimir Kogan, Md v. the United States of America 1
112 Fed. Cl. 253 (Federal Claims, 2013)
Aeroplate Corp. v. United States
112 Fed. Cl. 88 (Federal Claims, 2013)
Colonial Surety Co. v. United States
108 Fed. Cl. 622 (Federal Claims, 2013)
North Hartland, L.L.C. v. United States
78 Fed. Cl. 172 (Federal Claims, 2007)
National American Insurance v. United States
498 F.3d 1301 (Federal Circuit, 2007)
Travelers Indemnity Co. v. United States
72 Fed. Cl. 56 (Federal Claims, 2006)
Liberty Mutual Insurance v. United States
70 Fed. Cl. 37 (Federal Claims, 2006)
Insurance Co. of the West v. United States
55 Fed. Cl. 529 (Federal Claims, 2003)
Quality Mechanical Contractors, Inc. v. Moreland Corp.
19 F. Supp. 2d 1169 (D. Nevada, 1998)
International Fidelity Insurance v. United States
42 Cont. Cas. Fed. 77,368 (Federal Claims, 1998)
Intercargo Insurance v. United States
42 Cont. Cas. Fed. 77,356 (Federal Claims, 1998)
Blue Fox Inc. v. Small Business Administration
121 F.3d 1357 (Ninth Circuit, 1997)
Janowsky v. United States
36 Fed. Cl. 148 (Federal Claims, 1996)
Federal Insurance v. United States
39 Cont. Cas. Fed. 76,576 (Federal Claims, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
647 F.2d 1082, 28 Cont. Cas. Fed. 81,334, 227 Ct. Cl. 236, 1981 U.S. Ct. Cl. LEXIS 198, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-electric-corp-v-united-states-cc-1981.