Quality Mechanical Contractors, Inc. v. Moreland Corp.

19 F. Supp. 2d 1169, 1998 U.S. Dist. LEXIS 14663, 1998 WL 643583
CourtDistrict Court, D. Nevada
DecidedSeptember 3, 1998
DocketCV-S-98-00414-PMP (RJJ)
StatusPublished
Cited by3 cases

This text of 19 F. Supp. 2d 1169 (Quality Mechanical Contractors, Inc. v. Moreland Corp.) is published on Counsel Stack Legal Research, covering District Court, D. Nevada primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Quality Mechanical Contractors, Inc. v. Moreland Corp., 19 F. Supp. 2d 1169, 1998 U.S. Dist. LEXIS 14663, 1998 WL 643583 (D. Nev. 1998).

Opinion

*1171 ORDER

PRO, District Judge.

Presently before the Court is Defendant United States Department of Veterans Affairs’ (“VA”) Motion to Dismiss or for Summary Judgment (# 30) filed on May 15,1998. On May 19, 1998, the VA filed an Erratum to its Motion to Dismiss or for Summary Judgment (# 32). Plaintiff Quality Mechanical Contractors, Inc. (“Quality”) filed a Response/Opposition (#44) on June 9, 1998. On June 26, 1998, the VA filed a Reply (# 56). On July 2, 1998, Quality filed a Notice of Errata Re: Plaintiffs Response/Opposition (# 59).

I. Factual Background

Quality was a subcontractor on the Department of Veterans Affairs (“VA”) Las Vegas Ambulatory Care Center in Las Vegas, Nevada (“the Project”). Defendants Moreland Corporation (“Moreland”) and/or Las Vegas VAI, L.L.C. (“Las Vegas L.L.C.”) own the project, and the VA leases it for use as an outpatient client. Quality claims that it is owed $1,744,712.87 for its work on the Project and has brought suit against the VA, Moreland, Las Vegas L.L.C., RMA Corporation (“RMA”), various insurance and surety companies and R.M. Andersons & Sons, Inc. seeking recovery. As to the VA, Quality claims that it is entitled to recovery under equitable lien and unjust enrichment theories.

The parties involved built the Project to suit the needs of the VA. Moreland hired RMA as the prime contractor, and RMA in turn hired Quality to perform subcontracting plumbing and heating/air conditioning work on the Project. The VA did not require RMA to post a bond in favor of the subcontractors under the Miller Act. 1 The nature of the VA’s involvement in the construction of the Project is disputed.

Quality claims that the VA’s was heavily involved in construction, while VA maintains that it is just a lessee and had minimal involvement with the construction. According to Quality, the VA was active in soliciting offers for the construction of the Project. (Burnthon Decl. ¶ 3, attached to Pl.’s Opp’n.) In contrast, the VA insists that the VA did not negotiate with any contractors for construction of the Project. (Hill Decl. ¶4, attached to Def.’s Mot. To Dismiss.)

Quality also contends that the VA was actively involved with the day to day process of construction. The VA appointed a resident engineer whose duties included acquiring contract specifications, holding construction meetings, inspecting work, and issuing change orders. (Burnthon Decl. ¶ 4. and attached exhibits.) According to Quality, the VA also followed its normal contract procurement procedures and contract regulations, was heavily involved in the Project’s design, and issued numerous change orders. (Bum-thon Decl. ¶ 4.) While not directly disputing Quality’s contentions, the VA claims that it did not review the construction contracts between Moreland and any of the contractors, nor does it even have a copy of any construction contract. (Hill Decl. ¶ 4.)

Quality finished its work in July 1998, and the VA began its occupancy of the Project in the summer of 1998 under a fifteen year lease. 2 (Hill Decl. ¶ 3.) Quality claims that RMA did not pay it for all the extra work it was required to complete. Moreover, Quality insists it was required to perform this extra work partially as a result of VA’s action during the construction process. On November 25, 1997, Quality sent a letter to the VA notifying the VA that it had not been paid and would be requesting payment from the VA. (Letter from Spilsbury to Hill, Hayborn and Tyler of 11/25/97, Ex. 1, attached to Pl.’s Opp’n.) In the instant suit, Quality seeks an *1172 equitable lien on funds currently held by the YA as part of its lease obligation. It also seeks recovery for unjust enrichment that it claims occurred as a result of the VA enjoying the fruits of Quality’s labor and the materials provided by Quality.

II. Discussion

The VA seeks to dismiss Quality’s claims against the VA for two reasons. First, the VA argues that the Court lacks subject matter jurisdiction. Second, the VA argues that the Court should dismiss or grant summary judgment on the claims because Quality fails to state a claim upon which relief can be granted.

A. Motion to Dismiss for Lack of Jurisdiction

The VA contends that the Court lacks subject matter jurisdiction because Quality has not pled a waiver of sovereign immunity and because the United States has not waived immunity in this case. Quality counters that it adequately pled a waiver and that the Ninth Circuit Court of Appeals found that the United States has waived immunity.

Federal Rule of Civil Procedure 12(b)(1) allows a court to dismiss a Complaint for a lack of subject matter jurisdiction. Under the principle of sovereign immunity, the United States may only be sued where it has expressly consented to such suit by statute. Block v. North Dakota ex rel. Bd. of University and School Lands, 461 U.S. 273, 287, 103 S.Ct. 1811, 75 L.Ed.2d 840 (1983). Therefore, whether the United States has consented to be sued is a question of this Court’s subject matter jurisdiction. United States v. Sherwood, 312 U.S. 584, 586, 61 S.Ct. 767, 85 L.Ed. 1058 (1941) (“[T]he terms of [the United States’] consent tq be sued in any court define that court’s jurisdiction to entertain the suit.”); McCarthy v. United States, 850 F.2d 558, 560 (9th Cir.1988). A suit against a federal agency which seeks relief against the sovereign is, in effect, a suit against the sovereign. Larson v. Domestic & Foreign Commerce Corp., 337 U.S. 682, 687-88, 69 S.Ct. 1457, 93 L.Ed. 1628 (1949). Accordingly, the principles of sovereign immunity apply to that agency. Id.

In considering whether the Court has subject matter jurisdiction, the Court may review affidavits and other evidence to resolve factual disputes on the issue of jurisdiction without converting the Defendant’s Motion to Dismiss into one for summary judgment. McCarthy, 850 F.2d at 560; see Capitol Indus.-EMI, Inc. v. Bennett, 681 F.2d 1107, 1118 n. 29 (9th Cir.1982); Thornhill Publishing Co. v. General Telephone & Electronics Corp., 594 F.2d 730, 733 (9th Cir.1979). Due to the limited jurisdiction of federal courts, the plaintiff bears the burden of proving that this Court has jurisdiction. Kokkonen v. Guardian Life Ins. Co., 511 U.S. 375, 377, 114 S.Ct. 1673, 128 L.Ed.2d 391 (1994).

1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
19 F. Supp. 2d 1169, 1998 U.S. Dist. LEXIS 14663, 1998 WL 643583, Counsel Stack Legal Research, https://law.counselstack.com/opinion/quality-mechanical-contractors-inc-v-moreland-corp-nvd-1998.