Intercargo Insurance v. United States

42 Cont. Cas. Fed. 77,356, 41 Fed. Cl. 449, 1998 U.S. Claims LEXIS 183, 1998 WL 437340
CourtUnited States Court of Federal Claims
DecidedAugust 4, 1998
DocketNo. 96-467C
StatusPublished
Cited by2 cases

This text of 42 Cont. Cas. Fed. 77,356 (Intercargo Insurance v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Intercargo Insurance v. United States, 42 Cont. Cas. Fed. 77,356, 41 Fed. Cl. 449, 1998 U.S. Claims LEXIS 183, 1998 WL 437340 (uscfc 1998).

Opinion

OPINION

LYDON, Senior Judge.

In this contract case, plaintiff, acting as a Miller Act surety for a Government contractor, seeks enforcement of its right of equitable subrogation against the Government as a result of its payment, by way of a settlement under the payment bond it issued to the contractor, to the supplier of specially manufactured materials ordered by the .contractor, who never paid said supplier and the materials were never delivered to the work site.

Defendant has moved to dismiss plaintiffs complaint for lack of. jurisdiction on two grounds. First, defendant contends that plaintiff, under the facts of this case, does not and cannot establish any right to equitable subrogation and thus no privity exists to support its claim against the Government. Second, defendant argues plaintiff lacks authority to assert any claim on behalf of the contractor. The contractor filed for bankruptcy (Chapter 7) before the dismissal of the contractor’s case (No. 94-121C) in this court involving the same contract which underscores this litigation. Accordingly, defendant argues that the Trustee appointed by the bankruptcy court is the sole representative of the contractor’s estate and further argues there is no assertion, suggestion, or any intimation that the Trustee abandoned any claim, or cause of action the contractor might have against the Government. On the merits, plaintiff has moved for summary judgment and defendant also has moved, in the alternative, for summary judgment.

FACTS

The parties have filed a Stipulation of Facts, supported by a Joint Appendix, which are deemed admitted for purposes of resolving the matters at issue as reflected in the briefs of the parties.1

On September 24, 1993, the Department of the Army (Army) awarded Contract No. DABT01-93-C-0134 (Contract No. 0134) to Leonard Wills d/b/a Wills Construction Co. (WCC or Contractor) in the amount of $406,-619.00. This award was made pursuant to the Small Business Competitiveness Demonstration Program. The contract incorporated by reference a number of Federal Acqui[451]*451sition Regulation (FAR) clauses, e.g., Changes, Termination For Convenience, Default, Bankruptcy, Insurance-Work on a Government Installation, Disputes, etc. The Special Contract Requirements portion of the contract contained, inter alia, the following clause:

10. Preconstruction Conference: A Preconstruction Conference will be scheduled by the Contracting Officer after contract award and prior to the time and date set for commencement of work which will be held at Fort Rucker. At this meeting, the contractor will be oriented with respect to Government procedures and line of authority, as well as contractual, administrative, and construction matters. The contractor is required to furnish a current Certificate of Insurance and a Letter appointing a construction superintendent at the meeting.

The contract required WCC to maintain certain minimum insurance coverage, including workmen’s compensation. Indeed, before commencing work the contract required the contractor to certify in writing that the required insurance coverage had been obtained. The Special Contract Requirements portion of the contract also required the contractor to obtain performance and payment bonds.

The contract called for the demolition of existing doors and frames and installation of new specified doors and frames in some 204 family housing units at Fort Rucker, Alabama.

Intercargo Insurance Company (plaintiff), a Corporate Surety, issued Miller Act performance and payment bonds to WCC, as Principal, on October 6,1993.

Following receipt of a Notice to Proceed, issued by the Army on November 18, 1993, WCC sent out on December 13, 1993, its Purchase Order No. 93037001 to H & H Doors and Hardware, Inc. (H & H) for hollow metal doors and frames (all galvanized materials) and related components, i.e., frames, screens, storm doors, louvers, thresholds, weather stripping and door bottoms. The Purchase Order price was $253,-000 plus sales tax, “F.O.B. Our Office [WCC’s office].” The Purchase Order also provided in pertinent part, “Please ship the following via Best Way To Job Site. It is agreed that the shipment will be made on or before 1-21-94 or right is reserved to cancel order.”

On December 7, 1993, WCC submitted its proposed contract schedule designed to plan performance of the contract work so as to meet the June 16, 1994 contract completion date called for in the contract. The Government accepted this schedule on December 22, 1993.

On December 15, 1993, Maryland Insurance Group notified the Contracting Officer, Betty Ritter, that WCC’s insurance coverage regarding the contract for removal of existing doors and frames, etc., would be canceled effective January 14, 1994. This notice did not state the reason for the cancellation.

On December 22, 1993, WCC submitted a request to the Contracting Officer for a progress payment of $8,632.00, and the Contracting Officer approved such a payment to WCC on January 4, 1994. No other request for progress payments was received from WCC prior to termination of the contract by the Army. Plaintiff makes no claim relative to the above progress payment.

On January 4, 1994, H & H issued a Purchase Order to CECO Door Products for various materials required to comply with the terms of its contract with WCC. The scheduled shipping date for these materials was February 18, 1994. By letter dated February 3, 1994, H & H advised WCC that based on shipping dates received from its supplier, H & H anticipated that it would begin shipment of the specified materials to the Fort Rucker job site during the week beginning March 7, 1994. On January 18, 1994, H & H issued a Purchase Order to Falcon Lock Company for various materials needed to comply with the terms of its contract with WCC. The scheduled shipping date for these materials was apparently February 14, 1994.

By letter dated January 25,1994, the Contracting Officer wrote WCC in pertinent part as follows:

Reference Contract No. DABT01-93-C0134, Install New Doors and Frames, [452]*452Family Housing Areas, Fort Rucker, Alabama.
CURE NOTICE
You are notified that the Government considers your failure to furnish renewal certificates of insurance (workmen’s compensation, general liability, etc.) a condition that is endangering performance of the contract. Therefore, unless this condition is cured within ten (10) days after receipt of this notice, the Government may terminate for default under the terms and conditions of the “Default — Fixed Price Construction” clause of this contract.
If you have any questions, you may contact Fred Witcher at (205) 255-4771.

Plaintiff was sent a copy of this letter.

By letter dated January 28, 1993 (sic) [obviously 1994] WCC wrote Fred Witcher, Directorate of Contracting in pertinent part as follows:

Concerning the conversation between you and I on January 26, 1994 on the above named project, all material has not been received at this time. The information that I am getting from my supplier is that the material necessary to start will not be received until the second week in February. Mr. Witcher at this time we are trying to get a earlier ship date in order to start this project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hartford Fire Insurance v. United States
108 Fed. Cl. 525 (Federal Claims, 2012)
Westchester Fire Insurance v. United States
52 Fed. Cl. 567 (Federal Claims, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
42 Cont. Cas. Fed. 77,356, 41 Fed. Cl. 449, 1998 U.S. Claims LEXIS 183, 1998 WL 437340, Counsel Stack Legal Research, https://law.counselstack.com/opinion/intercargo-insurance-v-united-states-uscfc-1998.