Hartford Fire Insurance v. United States

42 Cont. Cas. Fed. 77,269, 40 Fed. Cl. 520, 1998 U.S. Claims LEXIS 52, 1998 WL 127063
CourtUnited States Court of Federal Claims
DecidedMarch 20, 1998
DocketNo. 97-167C
StatusPublished
Cited by8 cases

This text of 42 Cont. Cas. Fed. 77,269 (Hartford Fire Insurance v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hartford Fire Insurance v. United States, 42 Cont. Cas. Fed. 77,269, 40 Fed. Cl. 520, 1998 U.S. Claims LEXIS 52, 1998 WL 127063 (uscfc 1998).

Opinion

OPINION

MARGOLIS, Judge.

This equitable subrogation action is currently before the court on defendant’s motion to dismiss for failure to state a claim pursuant to RCFC 12(b)(4), or in the alternative for summary judgment pursuant to RCFC 56(b). Plaintiff, Hartford Fire Insurance Company, claims that it is entitled to judgment against defendant because the government breached its equitable duty to exercise reasonable discretion in administering contract funds, which, in turn forced plaintiff to make payment on a surety bond. After carefully considering the written and oral arguments of both parties, the court concludes that a government duty toward plaintiff never arose because plaintiff failed to give the government proper notice that the contractor was in danger of default. Defendant’s motion for summary judgment is therefore granted.

FACTS

On June 8, 1994, the defendant United States acting through the Small Business [521]*521Administration (“SBA”) awarded a contract for the construction of the Criminal Investigation Division Field Operations Center (“CIDC”) in Fort Leonard Wood, Missouri to K & K Construction Company (“K & K”) under the SBA’s section 8(a) program.1 On June 21, 1994, the SBA apprised the U.S. Army Corps of Engineers (“Corps”) of this contract and delegated administration and payment authority to the Corps. The SBA also informed the Corps that it would monitor performance of the CIDC contract through its own resources and requested that all actions taken in connection with the CIDC project be in strict coordination with the SBA. The contract named Edgar Poindexter as the contracting officer on behalf of the SBA.

On June 16, 1994, K & K entered into a subcontract agreement with Rau Construction Company (“Rau”) to perform various administrative tasks on the CIDC project, including obtaining a surety. Article 8 of this subcontract agreement provided that in the event the government determined that K & K was in default of its obligations or that claims were made against the performance and payment bonds, Rau would have the right to complete the project and resolve any claims against the bonds as representative for the surety. Plaintiff, Hartford Fire Insurance Company, issued performance and payment bonds for K & K’s contract on July 22, 1994. Rau agreed to indemnify plaintiff for any loss incurred by reason of executing the performance and payment bonds. According to plaintiff, Rau could not guarantee the bond directly because it was not on the list of sureties approved by the Department of the Treasury. Consequently, plaintiff, an approved company, issued the bonds that Rau then guaranteed.

According to plaintiff, beginning on June 1, 1995, representatives of Rau informed contracting officer Poindexter that K & K had not deposited the last two progress payments in the CIDC project account and that Rau believed the subcontractors and suppliers on the CIDC project were in danger of not being paid. Representatives of Rau, including Rau’s president, Gus Rau Meyer, met with Poindexter on June 5, 1995 to inform him that K & K had made over $100,000 in unauthorized withdrawals from the CIDC project funds and that K & K was placing progress payments in unauthorized bank accounts. Additionally, at this meeting Meyer told Poindexter that Rau had not been paid money it was due under its subcontract with K & K and that K & K lacked adequate funds to pay the other subcontractors. Finally, representatives of Rau asked Poindexter to intervene to ensure that K & K paid its subcontractors.

On June 30, 1995, the Corps conducted a final inspection of the CIDC project and a contracting officer representative signed and approved K & K’s final progress payment request for $208,190. On July 3,1995, Rau’s attorney sent a letter to Poindexter informing him that K & K had submitted a payment request to the Corps for $208,190 in contravention of the subcontract requirements, that Rau was concerned that this payment would not be used to pay the subcontractors and suppliers, and that Rau would like Poindexter to take immediate action to ensure that K & K would use the progress payments for the correct purpose. The Corps notified K & K on July 6, 1995 that the Corps accepted the project as substantially complete, with deficiencies that remained to be corrected. The Corps retained the balance of the amount due on the contract pending correction of deficiencies and other administrative details required to complete the contract. K & K’s progress payment number ten, in the amount of $208,190, was made by check on July 14,1995. On July 19,1995, Rau’s attorney wrote Poindexter again to inform him that K & K had not deposited the $208,190 progress payment in the designated project account.

During June and July of 1995, Poindexter made numerous attempts to contact the president of K & K, Kenneth Kelly, to resolve Poindexter’s concern that K & K might not pay its subcontractors and suppliers on the [522]*522CIDC project. Kelly failed to respond to Poindexter’s inquiries. Poindexter did not, however, take action against K & K until July 14, 1995, when he notified Kelly that he was recommending termination of K & K from the section 8(a) program. On July 26, 1995, Poindexter withdrew the Corps’ authority to make payments directly to K & K and asked that all pending and future payment requests be sent to the SBA for approval.

By letter dated August 9, 1995, plaintiff advised the Corps that it was in receipt of claims on the payment bond it issued in the CIDC contract. Plaintiff requested that the Corps withhold any remaining contract funds and stop payment on the $208,190 progress payment. Additionally, the letter advised the Corps of plaintiffs right to equitable subrogation should plaintiff have to make payments on the bond. On September 26, 1995, Rau’s attorney informed the Corps that Rau provided the guarantee for the project and would therefore be held accountable for payment to the subcontractors. Rau also asked the Corps not to make the final payment of $103,694 to K & K. The contract was documented as fully completed on April 22, 1996. On May 22, 1996, the final payment check for $103,694 was issued payable to K & K, but delivered to plaintiff. Pursuant to its surety bond, plaintiff paid all the subcontractors and suppliers in August 1996.

Plaintiff filed this suit on March 17, 1997 alleging that defendant acted unreasonably and abused its discretion to the detriment of plaintiff by failing to take reasonable steps to determine whether K & K had the capacity and the intention to pay the subcontractors and suppliers from the $208,190 progress payment, by failing to prevent the $208,190 progress payment from being made directly to K & K, and by failing to take reasonable steps to prevent the $208,190 progress payment from being used for purposes other than paying the subcontractors and suppliers. Plaintiff claims that through the doctrine of equitable subrogation it is entitled to judgment in an amount in excess of $200,000, plus attorneys’ fees, interest, and costs.

DISCUSSION

The case is currently before the court on defendant’s motion to dismiss for failure to state a claim, or in the alternative for summary judgment. Because materials beyond the pleadings are contained in the parties’ appendices, defendant’s motion to dismiss ■will be treated as a motion for summary judgment. See RCFC 12(b)(4).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hanover Insurance Company (The) v. United States
133 Fed. Cl. 633 (Federal Claims, 2017)
Hartford Fire Insurance v. United States
108 Fed. Cl. 525 (Federal Claims, 2012)
Insurance Co. of West v. United States
83 Fed. Cl. 535 (Federal Claims, 2008)
United States Fire Insurance v. United States
78 Fed. Cl. 308 (Federal Claims, 2007)
Nova Casualty Co. v. United States
69 Fed. Cl. 284 (Federal Claims, 2006)
International Fidelity Insurance v. United States
42 Cont. Cas. Fed. 77,368 (Federal Claims, 1998)
Intercargo Insurance v. United States
42 Cont. Cas. Fed. 77,356 (Federal Claims, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
42 Cont. Cas. Fed. 77,269, 40 Fed. Cl. 520, 1998 U.S. Claims LEXIS 52, 1998 WL 127063, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hartford-fire-insurance-v-united-states-uscfc-1998.