Westech Corp. v. Fireman's Fund Insurance

36 Cont. Cas. Fed. 75,885, 20 Cl. Ct. 745, 1990 U.S. Claims LEXIS 252, 1990 WL 91095
CourtUnited States Court of Claims
DecidedJuly 2, 1990
DocketNo. 726-88C
StatusPublished
Cited by23 cases

This text of 36 Cont. Cas. Fed. 75,885 (Westech Corp. v. Fireman's Fund Insurance) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Westech Corp. v. Fireman's Fund Insurance, 36 Cont. Cas. Fed. 75,885, 20 Cl. Ct. 745, 1990 U.S. Claims LEXIS 252, 1990 WL 91095 (cc 1990).

Opinion

ORDER

MOODY R. TIDWELL, III, Judge:

This case is before the court on defendant's motion to dismiss for lack of subject matter jurisdiction. For purposes of this motion, the court will accept plaintiffs’ allegations as true and draw all reasonable inferences in plaintiffs’ favor. Mortensen v. First Fed. Sav. and Loan Ass’n, 549 F.2d 884, 891 (3d Cir.1977).

FACTS

In March of 1982, the United States, through the Department of the Army, awarded the Westech Corporation a contract for $5,892,000 to build a pressure recovery system for the High Energy Laser System Test Facility (HELSTF) at White Sands Missile Range, New Mexico. A completion date was set for August 24, 1983. Fireman’s Fund Insurance Co. became the surety pursuant to the Miller Act, 40 U.S.C. §§ 270a-270d (1976), and issued a $5,892,000 performance bond and a $2,500,-000 payment bond. Both bonds named Westech as principal and the United States as obligee.1

Defendant provided Westech with construction plans for the pressure recovery system which included the design specifications of certain condenser/scrubbers and steam jet injectors. After studying the plans, Westech concluded that the performance specifications of the scrubbers and steam jet injectors could not be met using defendant’s design. Therefore, on June 10, 1982, Westech wrote to defendant to explain the design problems and to request direction how to proceed. Defendant responded to Westech’s letter by stating merely that the plans were being studied and that defendant would notify Westech how to proceed at a later date.

In July of 1982, Westech submitted alternative design specifications for the condenser/scrubbers, steam jet injectors, and various other components of the pressure recovery system. Some months later, but before defendant made any response, Wes-tech sent defendant two additional letters. One requested a reply to its design submissions and the other advised defendant of its delay in not responding. Defendant finally responded to these submissions in early January of 1983, but stated only that it had taken no action. In mid-January of 1983, Westech again wrote to defendant complaining of the delay. Defendant responded to the latter complaint by stating that a decision would be made within ten days. On February 3, 1983, eight months after the issue had been initially raised, defendant directed Westech to begin construction using the original plans.

On February 8, 1983, Westech advised defendant that the government-caused delays were viewed as material and substantial changes to the original contract and that defendant’s order to meet the original August 24, 1983 completion date was considered an acceleration order. On April 14, 1983, Westech requested an extension of the August deadline for 240 days. Defendant allowed 36 days. Westech did not consider the 36-day extension an equitable adjustment to its 240-day extension request, and advised defendant that the new order to complete by September 30, 1983 was also an acceleration order. Defendant denied that the new order constituted acceleration but, nonetheless, offered to reimburse Westech for all reasonable costs incurred in meeting the September 1983 deadline.

In September of 1983, defendant made several changes to the contract and extended the completion date to December 31, 1983. Prior to the latter extension, Wes-[748]*748tech had experienced cash flow problems that eventually required Fireman’s Fund, as surety, to make payments to Westech’s subcontractors. Thereafter, Fireman’s Fund requested that defendant not make any payments to Westech without their consent. This request was honored and defendant withheld the December progress payment.

Two weeks before the December 31,1983 completion date, Westech abandoned the project. On December 29, 1983, after giving Westech and Fireman’s Fund notice, defendant terminated the contract for default. Shortly thereafter Westech ceased doing business. Due to the urgent need to complete the project, defendant requested Fireman’s Fund to resume work no later than January 9, 1984. Fireman’s Fund could not comply in the short time period allowed and defendant awarded a repro-curement contract to another firm. Fireman’s Fund was assessed for reprocurement costs in excess of the original contract price. The reprocurement contractor substantially completed the contract work in April of 1984.

On June 22, 1984, Fireman’s Fund, on behalf of Westech, submitted a claim to the contracting officer for the recovery of delay and acceleration damages.2 The claim was certified by Westech’s on-site project manager who we are told, and assume, was the senior company official at the job site. The contracting officer denied the claim and plaintiffs filed suit in this court.

DISCUSSION

Congress has defined this court’s jurisdiction under the Tucker Act, 28 U.S.C. § 1491 (1988), to encompass only those claims “founded either upon the Constitution, or any Act of Congress, or any regulation of an executive department, or upon any express or implied contract with the United States, or for liquidated or unliquidated damages in cases not sounding in tort.” 28 U.S.C. § 1491(a)(1) (1988); see Aetna Casualty & Sur. Co. v. United States, 655 F.2d 1047, 1051, 228 Ct.Cl. 146 (1981). Nothing in this Act, however, creates, in and of itself, a substantive right of recovery against the United States. Rather, the Act merely vests the Claims Court with jurisdiction when such a right independently exists. United States v. Testan, 424 U.S. 392, 398, 96 S.Ct. 948, 953, 47 L.Ed.2d 114 (1976); United States v. Connolly, 716 F.2d 882, 885 (Fed.Cir.1983) (en banc), cert. denied, 465 U.S. 1065, 104 S.Ct. 1414, 79 L.Ed.2d 740 (1984). A claimant must look beyond the Tucker Act to discover and plead a money-mandating predicate upon which to complete jurisdiction. Connolly, 716 F.2d at 885.

Plaintiff, Fireman’s Fund, has looked to the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 601-613 (1988), for independently existing rights over which this court may exercise jurisdiction.3 Defendant’s challenge to plaintiffs’ claims is that they do not fall within the ambit of the CDA. Specifically, defendant has asserted: (a) the court does not have jurisdiction over the claim of Fireman’s Fund, as surety, under the CDA; (b) the court does not have jurisdiction over Fireman’s Fund through the doctrine of subrogation or estoppel; and (c) the court does not have jurisdiction to hear Westech’s claim due to an improper certification. The court will examine defendant’s allegations seriatum.

A. Jurisdiction Under the CDA to Hear a Surety’s Claim for Breach of Contract Damages

The legislative history of the CDA indicated that its purpose and design was to provide a comprehensive system for adjudicating contract claims against the government.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brinkman v. United States
Federal Claims, 2022
Lumbermens Mutual Casualty Co. v. United States
654 F.3d 1305 (Federal Circuit, 2011)
Nelson Construction Co. v. United States
79 Fed. Cl. 81 (Federal Claims, 2007)
Lumbermens Mutual Casualty Co. v. United States
67 Fed. Cl. 253 (Federal Claims, 2005)
Westchester Fire Insurance v. United States
52 Fed. Cl. 567 (Federal Claims, 2002)
Taylor v. United States
49 Fed. Cl. 598 (Federal Claims, 2001)
Johnson Controls World Services, Inc. v. United States
44 Fed. Cl. 334 (Federal Claims, 1999)
Hartford Fire Insurance v. United States
42 Cont. Cas. Fed. 77,269 (Federal Claims, 1998)
United Sales, Inc. v. United States
40 Cont. Cas. Fed. 76,842 (Federal Claims, 1995)
Transamerica Insurance v. United States
39 Cont. Cas. Fed. 76,671 (Federal Claims, 1994)
Hannon v. United States
29 Fed. Cl. 142 (Federal Claims, 1993)
Miller v. United States
29 Fed. Cl. 107 (Federal Claims, 1993)
Blake Construction Co. v. United States
38 Cont. Cas. Fed. 76,537 (Federal Claims, 1993)
Markey v. United States
27 Fed. Cl. 615 (Federal Claims, 1993)
Shook v. United States
38 Cont. Cas. Fed. 76,424 (Court of Claims, 1992)
Buffalo National Bank v. United States
26 Cl. Ct. 1436 (Court of Claims, 1992)
Ward v. United States
26 Cl. Ct. 680 (Court of Claims, 1992)
George W. Kane, Inc. v. United States
38 Cont. Cas. Fed. 76,385 (Court of Claims, 1992)
Choggiung Ltd. v. United States
37 Cont. Cas. Fed. 76,200 (Court of Claims, 1991)
KDH Corp. v. United States
37 Cont. Cas. Fed. 76,087 (Court of Claims, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
36 Cont. Cas. Fed. 75,885, 20 Cl. Ct. 745, 1990 U.S. Claims LEXIS 252, 1990 WL 91095, Counsel Stack Legal Research, https://law.counselstack.com/opinion/westech-corp-v-firemans-fund-insurance-cc-1990.