Triax Co. v. United States

36 Cont. Cas. Fed. 75,869, 20 Cl. Ct. 507, 1990 U.S. Claims LEXIS 205, 1990 WL 70810
CourtUnited States Court of Claims
DecidedMay 25, 1990
DocketNo. 626-85C
StatusPublished
Cited by23 cases

This text of 36 Cont. Cas. Fed. 75,869 (Triax Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Triax Co. v. United States, 36 Cont. Cas. Fed. 75,869, 20 Cl. Ct. 507, 1990 U.S. Claims LEXIS 205, 1990 WL 70810 (cc 1990).

Opinion

OPINION

SMITH, Chief Judge.

On July 21,1989, the court dismissed the Triax Company’s appeal from the contracting officer’s final decision denying its claim, on the ground that the individuals who had certified the claims on behalf of Triax did not meet the requirements of FAR 33.207(c)(2). The case is presently before the court on Triax’s motion for reconsideration. For the reasons given below, the court’s order of dismissal is vacated.

FACTS

On August 5, 1982, the Navy awarded contract N62467-80-G-0099 to Triax at a firm fixed price of $4,688,400. The contract called for the renovation of military housing units at the Naval Air Station in Millington, Tennessee.

At the preconstruction conference, Navy officials informed Triax that there would be some changes to the contract. It was agreed that Triax would be given a list of additional work items to be performed on a given unit, on the day before work was to begin on that unit. Triax began renovation on the first increment of housing on November 1, 1982, and over the term of the contract, Triax performed some 22,000 additional work items. Triax and the Navy negotiated several modifications to the contract, providing for additional compensation for increased materials and labor. However, a dispute arose regarding whether modification No. 7 constituted an accord and satisfaction with respect to all previous changes, or whether Triax retained the right to seek additional compensation for delays caused by the changes.

On April 1, 1985, Triax submitted a certified claim to the contracting officer (CO), requesting a $2.8 million upward adjustment in the contract price. The claim was signed by Ronald Carter, who at the time was the Secretary of the Triax Company, as well as Triax’s attorney. The claim was denied by the CO on September 17, 1985. Triax filed the present direct access appeal of the CO’s denial of the claim on October 22, 1985.

On June 19, 1987, Triax submitted a second certified claim to the CO, this time requesting an additional $4.1 million. This claim was signed by William Simmons, Financial Vice President of Triax.

After extensive discovery and pretrial briefings on evidentiary issues, Judge Napier held a four-week long trial in early 1989. During trial, Judge Napier raised the issue of whether either claim was properly certified under section 6(c) of the Contract Disputes Act, 41 U.S.C. § 605(c) (1988 ed.), and asked that the parties file post-trial briefs addressing the issue. Specifically, [509]*509Judge Napier was concerned that the certified claims submitted by Carter and Simmons did not meet the requirements of FAR 33.207(c)(2), which provides:

If the contractor is not an individual, the certification shall be executed by—
(i) A senior company official in charge at the contractor’s plant or location involved; or
(ii) An officer or general partner of the contractor having overall responsibility for the conduct of the contractor’s affairs.

48 C.F.R. § 33.207(c)(2) (1988).1

The parties filed their post-trial briefs on March 31, 1989; replies were filed on April 24, 1989. On July 7, 1989, the Federal Circuit issued its decision in Ball, Ball & Brosamer, 878 F.2d 1426 (Fed.Cir.1989), which construed FAR 33.207(c)(2). On July 21, 1989, relying heavily on the Federal Circuit’s decision in Ball, Ball & Brosamer, Judge Napier dismissed Triax’s claim upon his own motion, on the ground that under FAR 33.207(c)(2), neither Mr. Carter nor Mr. Simmons could submit certified claims on behalf of Triax. Triax Co. v. United States, 17 Cl.Ct. 653 (1989). The current motion for reconsideration was timely filed.2

DISCUSSION

It is well-settled that the submission of a properly certified claim to the CO is a jurisdictional prerequisite to a direct-access appeal of the CO’s denial of the claim. Contract Disputes Act, 41 U.S.C. § 605(c); Thoen v. United States, 765 F.2d 1110 (Fed.Cir.1985); Paul E. Lehman, Inc. v. United States, 673 F.2d 352, 230 Ct.Cl. 11 (1982). Subject-matter jurisdiction can be questioned at any time, Bender v. Williamsport Area School Dist., 475 U.S. 534, 106 S.Ct. 1326, 89 L.Ed.2d 501 (1986), and no consensual action of the parties can confer jurisdiction on a federal court where none exists according to preexisting law, California v. LaRue, 409 U.S. 109, 93 S.Ct. 390, 34 L.Ed.2d 342 (1972).

Triax asserts in its motion for reconsideration that the certifications at issue met the test of FAR 33.207(c)(2). Alternatively, Triax asks that it at least be allowed to supplement the record, to include “bench memos” that Judge Napier apparently considered when he dismissed the case, but which were not made part of the record.

RUSCC 59(a)(1) provides:

A new trial or rehearing or reconsideration may be granted to all or any of the parties and on all or part of the issues for any of the reasons established by the rules of common law or equity applicable as between private parties in the courts of the United States. On a motion under this rule, the court may open the judgment if one has been entered, take additional testimony, amend findings of fact and conclusions of law or make new findings and conclusions, and direct the entry of a new judgment.

A motion for reconsideration is addressed to the discretion of the trial court. Eyre v. McDonough Power Equipment, 755 F.2d 416 (5th Cir.1985) (construing Fed.R.Civ.P. 59); Grumman Aircraft Engineering v. Renegotiation Bd., 482 F.2d 710 (D.C.Cir.1973), rev’d on other gds., 421 U.S. 168, 95 S.Ct. 1491, 44 L.Ed.2d 57 (1974) (construing Fed.R.Civ.P. 59). A motion under rule 59 is not to be viewed as an additional chance for a dissatisfied litigant to sway a judge. Frito-Lay of Puerto Rico, Inc. v. Canas, 92 F.R.D. 384 (D.Puerto Rico 1981). “A motion for a new trial in a nonjury case or a petition for rehearing should be based upon manifest error of law or mistake of fact.” Wright & Miller, Federal Practice and Procedure, Civil § 2804.

Allowing Triax an opportunity to be heard on the issue of the validity of the certifications at this stage is appropriate, for three reasons.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State ex rel. Louie v. JP Morgan Chase & Co.
921 F. Supp. 2d 1059 (D. Hawaii, 2013)
Precision Pine & Timber, Inc. v. United States
81 Fed. Cl. 235 (Federal Claims, 2007)
Phillips/May Corp. v. United States
76 Fed. Cl. 671 (Federal Claims, 2007)
Holland v. United States
75 Fed. Cl. 492 (Federal Claims, 2007)
Thorndike v. United States
72 Fed. Cl. 580 (Federal Claims, 2006)
American Airlines, Inc. v. United States
71 Fed. Cl. 744 (Federal Claims, 2006)
Aerolease Long Beach v. United States
31 Fed. Cl. 342 (Federal Claims, 1994)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
M.A. Mortenson Co. v. United States
39 Cont. Cas. Fed. 76,555 (Federal Claims, 1993)
Triax Co. v. United States
39 Cont. Cas. Fed. 76,554 (Federal Claims, 1993)
Bishop v. United States
26 Cl. Ct. 281 (Court of Claims, 1992)
Kiewit/Tulsa-Houston v. United States
37 Cont. Cas. Fed. 76,255 (Court of Claims, 1992)
Choggiung Ltd. v. United States
37 Cont. Cas. Fed. 76,200 (Court of Claims, 1991)
Aleman Food Services, Inc. v. United States
37 Cont. Cas. Fed. 76,199 (Court of Claims, 1991)
Universal Coatings/Won Ill Co. v. United States
37 Cont. Cas. Fed. 76,173 (Court of Claims, 1991)
Reliance Insurance v. United States
37 Cont. Cas. Fed. 76,090 (Court of Claims, 1991)
KDH Corp. v. United States
37 Cont. Cas. Fed. 76,087 (Court of Claims, 1991)
The United States v. Grumman Aerospace Corporation
927 F.2d 575 (Federal Circuit, 1991)
Westech Corp. v. Fireman's Fund Insurance
36 Cont. Cas. Fed. 75,885 (Court of Claims, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
36 Cont. Cas. Fed. 75,869, 20 Cl. Ct. 507, 1990 U.S. Claims LEXIS 205, 1990 WL 70810, Counsel Stack Legal Research, https://law.counselstack.com/opinion/triax-co-v-united-states-cc-1990.