Paul E. Lehman, Inc. v. United States

673 F.2d 352, 29 Cont. Cas. Fed. 82,266, 230 Ct. Cl. 11, 1982 U.S. Ct. Cl. LEXIS 68
CourtUnited States Court of Claims
DecidedFebruary 24, 1982
DocketNo. 270-81C
StatusPublished
Cited by109 cases

This text of 673 F.2d 352 (Paul E. Lehman, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Paul E. Lehman, Inc. v. United States, 673 F.2d 352, 29 Cont. Cas. Fed. 82,266, 230 Ct. Cl. 11, 1982 U.S. Ct. Cl. LEXIS 68 (cc 1982).

Opinion

FRIEDMAN, Chief Judge,

delivered the opinion of the court:

The question before us, raised by defendant’s motion for summary judgment, is whether under the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-613 (Supp. Ill 1979),1 a contractor may obtain in this court direct judicial review of a contracting officer’s decision, where (1) the contract was entered into before the effective date of the Act, (2) the contractor filed his claim after the effective date, (3) the contractor did not certify its claim, as the Act requires, but (4) the contracting officer entertained the claim and decided the merits. We hold that the contractor’s failure to certify precludes it from challenging directly the contracting officer’s decision in this court. We therefore dismiss the petition.

I.

A. Prior to the Contract Disputes Act of 1978 ("the Act”), a contractor wishing to challenge a contracting officer’s decision was required to appeal the decision to the agency’s board of contract appeals, where a trial de novo was held. If the contractor was dissatisfied with the board’s decision, it could challenge that decision in this court. Under the Wunderlich Act, 41 U.S.C. § 321 (1976), review in this court is based upon the record before the board. The decision of the board is "final and conclusive unless the same is fraudulent or capricious or arbitrary or so grossly erroneous as necessarily to imply bad faith, or is not supported by substantial evidence.” Id.

One of the major changes the Act made in the litigation of claims by government contractors was to give contractors challenging a contracting officer’s decision the election of either following the old procedures, 41 U.S.C. §606, or of bypassing the contract appeals board and filing suit on the [13]*13claim directly in this court, id. § 609(a)(1). In those judicial proceedings the court conducts a trial de novo. Id. § 609(a)(3).

Section 6(c)(1), 41 U.S.C. § 605(c)(1) requires that:

For claims of more than $50,000, the contractor shall certify that the claim is made in good faith, that the supporting data are accurate and complete to the best of his knowledge and belief, and that the amount requested accurately reflects the contract adjustment for which the contractor believes the government is liable.

The Act then provides that within 60 days of receipt of "a submitted certified claim,” the contracting officer "shall . . . issue a decision; or . . . notify the contractor when the decision will be issued.” Section 6(c)(2), 41 U.S.C. § 605(c)(2).

The Act applies to all contracts entered into 120 days after its enactment. It further provides that when a contract has been entered into before the effective date of the Act (March 1, 1979), the "contractor may elect to proceed under this Act with respect to any claim then pending before the contracting officer or initiated thereafter.” Section 16, 41 U.S.C. § 601 note.

B. The plaintiff in this case seeks additional compensation under a construction contract with the United States Department of Agriculture for the extra cost it allegedly incurred because of construction delays resulting from bad weather. The contract was entered into in June 1976, almost three years before the effective date of the Act. The plaintiff filed its claim with the contracting officer in December 1979, more than nine months after the effective date of the Act. It sought an additional $267,320. The contractor did not certify its claim, as section 6(c)(1) requires.

The contracting officer, however, entertained and denied the claim. When the plaintiff notified the contracting officer that it intended to appeal, the officer forwarded the case to the Department of Agriculture Board of Contract Appeals ("the Board”). The plaintiff decided to seek direct review before this court. When it so informed the Board, the latter dismissed the appeal without prejudice.

[14]*14The plaintiff then filed suit here. Although originally it asserted jurisdiction under both the Contract Disputes Act and the Tucker Act, 28 U.S.C. § 1491 (1976), apparently it now recognizes that we have no jurisdiction under the Tucker Act because the plaintiff has not exhausted its administrative remedies before the Board. The defendant has moved for summary judgment on the ground that we cannot entertain the suit under the Contract Disputes Act because the plaintiff failed to certify its claim.

II.

The requirement for certification of claims of more than $50,000 is an important part of the new procedures Congress provided in the Act for the handling of claims by government contractors. An important objective of Congress was to "discourag[e] the submission of unwarranted contractor claims.” S. Rep. No. 1118, 95th Cong., 2d Sess. 5, reprinted in [1978] U.S. Code Cong. & Ad. News 5235, 5239. One method of accomplishing this purpose was provided in section 5 of the Act, 41 U.S.C. §604, which makes a contractor liable for the amount of any portion of its claim that it is unable to support because of misrepresentation or fraud. Another was the certification requirement.

"The purposes of the certification requirement are to discourage the submission of unwarranted contractor claims and to encourage settlements.” Folk Construction Co. v. United States, 226 Ct. Cl. 602 (1981). The importance Congress attached to the certification requirement is reflected not only in section 6(c)(1), which states that the contractor "shall” certify, but also in the provision in section 6(c)(2) that the contracting officer’s obligation within 60 days to issue a decision or inform the contractor when he will do so arises only after the officer has received a "certified claim.”

The legislative history of the certification requirement confirms the importance Congress ascribed to it. Since the certification requirement was added to the bill on the floor of the Senate on the day on which the Senate passed the legislation, October 12, 1978, 124 Cong. Rec. 36266 (1978), [15]*15which was the day before the House passed it, id. at 37074-76, the committee reports do not discuss the provision. The explanation of the amendments, however, offered by Senator Byrd, the amendments’ sponsor, said that section 6(c) of the Act was "amended due to the concerns expressed by . . . [among others] Admiral Rickover” about time constraints. The amendments dealt also with Admiral Rickover’s other concerns. Id. at 36267.

Admiral Rickover suggested the certification requirement on June 14, 1978, at hearings on the bill. Contract Disputes Act of 1978: Joint Hearings on S. 2292, S. 2787 & S.3178 Before the Subcomm.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JAAAT Technical Services, LLC
Armed Services Board of Contract Appeals, 2021
Wright Brothers, the Building Company, Eagle LLC
Armed Services Board of Contract Appeals, 2020
Kamaludin Slyman CSC
Armed Services Board of Contract Appeals, 2020
Csx Transportation, Inc. v. United States
123 Fed. Cl. 244 (Federal Claims, 2015)
Tokyo Company
Armed Services Board of Contract Appeals, 2014
J & E Salvage Co. v. United States
41 Cont. Cas. Fed. 77,079 (Federal Claims, 1997)
United Sales, Inc. v. United States
40 Cont. Cas. Fed. 76,842 (Federal Claims, 1995)
Oroville-Tonasket Irrigation District v. United States
40 Cont. Cas. Fed. 76,746 (Federal Claims, 1995)
Alvarado Construction, Inc. v. United States
39 Cont. Cas. Fed. 76,708 (Federal Claims, 1994)
Fidelity & Deposit Co. of Maryland v. United States
39 Cont. Cas. Fed. 76,675 (Federal Claims, 1994)
Hamza v. United States
39 Cont. Cas. Fed. 76,687 (Federal Claims, 1994)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
M.A. Mortenson Co. v. United States
39 Cont. Cas. Fed. 76,555 (Federal Claims, 1993)
T.L. Roof & Associates Construction Co. v. United States
38 Cont. Cas. Fed. 76,534 (Federal Claims, 1993)
City of Tacoma v. United States
38 Cont. Cas. Fed. 76,532 (Federal Claims, 1993)
Reliance Insurance v. United States
38 Cont. Cas. Fed. 76,494 (Federal Claims, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
673 F.2d 352, 29 Cont. Cas. Fed. 82,266, 230 Ct. Cl. 11, 1982 U.S. Ct. Cl. LEXIS 68, Counsel Stack Legal Research, https://law.counselstack.com/opinion/paul-e-lehman-inc-v-united-states-cc-1982.