JAAAT Technical Services, LLC

CourtArmed Services Board of Contract Appeals
DecidedJune 7, 2021
DocketASBCA No. 61792, 61793, 61794, 61795, 61796, 61797, 61798, 61799, 61800
StatusPublished

This text of JAAAT Technical Services, LLC (JAAAT Technical Services, LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
JAAAT Technical Services, LLC, (asbca 2021).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of - ) ) JAAAT Technical Services, LLC ) ASBCA Nos. 61792, 61793, 61794 ) 61795, 61796, 61797 ) 61798, 61799, 61800 ) Under Contract No. W912HN-10-D-0063 )

APPEARANCES FOR THE APPELLANT: Mr. Rickey B. Barnhill 1 Director of Finance Andrew T. Bodoh, Esq. 2 Thomas H. Roberts & Associates, P.C. Richmond, VA

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Justin P. McCorcle, Esq. Aaron A. Bloemsma, Esq. Engineer Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE CATES-HARMAN

Pending before the Board is the government’s motion for summary judgment, or in the alternative, a motion to dismiss for lack of jurisdiction in all but one of the nine appeals. The Board sua sponte raised questions relating to the subject matter jurisdiction of the ninth and largest appeal (ASBCA No. 61792). During the period of 2014 to 2015, appellant, JAAAT Technical Services, LLC (JAAAT, appellant) submitted nine Requests for Equitable Adjustment (REA) to the contracting officer; the form and substance of the CO’s responses will be discussed below. On September 11, 2018, appellant filed a Notice of Appeal for each of the nine REAs based upon a deemed denial. The government maintains that the Board lacks subject matter jurisdiction over eight of the nine appeals because the REAs were never converted to a claim, that each failed to request a contracting officer’s final decision, and for those REAs exceeding $100,000, lacked a certification as required by the Contract Disputes

1 By Order dated October 3, 2018, the Board accepted Mr. Rickey B. Barnhill as appellant’s representative. In support of these appeals, he has filed pleadings, briefs, and an affidavit under the name of either “Rickey” or “Rick” Barnhill. For purposes of this decision, he will be referred to as “Rickey” Barnhill. 2 Mr. Bodoh has entered an appearance on June 30, 2020, to represent appellant in

ASBCA No. 61799 only. Act (CDA), 41 U.S.C. §§ 7101-7109. In one appeal, the government asserts that a written claim was never submitted to the contracting officer. Where the appeals have similar issues, they will be grouped together for decision.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION 3

1. Contract No. W912HN-10-D-0063 (contract), was awarded to JAAAT on September 30, 2010, by the U.S. Army Corps of Engineers, Savannah District (USACE). This was a multiple award contract (MATOC) for the design/build or construction type task orders (R4, tab 4a at 2030). The contract recited FAR 52.233-1, DISPUTES (JUL 2002) and FAR 52.243-4, CHANGES (JUN 2007) (R4, tab 4a at 2141, 2151-52).

2. On September 17, 2012, USACE issued task order DQ01 (task order) to JAAAT for the design and construction of PN 69758 Special Operation Forces Brigade Headquarters Facility at Fort Bragg, North Carolina. The task order was awarded for the firm-fixed price of $15,649,974. The appellant was required to:

Design/Construct a Brigade Headquarters facility for the 95th Civil Affairs Brigade to include administrative space, conference rooms, classrooms, sensitive compartmented information facility, group operations center, logistics, network operation center, headquarters company, enlarged arms room vault, secure storage, unit storage, lockers, toilets, showers, and required mechanical, electrical and communication rooms, protected distribution system (PDS), intrusion detection, surveillance, and electronic access control.

(R4, tab 4b at 2213-15, 2220)

3. The contract also required JAAAT to furnish both performance and payment bonds, each with good and “sufficient surety or sureties acceptable to the Government” (R4, tab 4a at 2121). On September 21, 2012, Safeco Insurance Company of America (Safeco) issued the Performance and Payment Bond No. 024048098, on behalf of JAAAT, as Bond Principal, and in favor of the United States of America as Bond Obligee in the amount of $15,649,741, on the task order (referred to in the September 21, 2012 document as the “SOF Brigade Headquarters Contract”). (Gov’t mot., ex. G-2 at 1-2, ¶¶ 1.2 - 1.3)

3 This decision is comprised of nine appeals, ASBCA Nos. 61792-61800. Each appeal will have a separate statement of facts for purposes of the government’s motion. 2 4. The task order includes FAR 52.228-15(b)(3), PERFORMANCE AND PAYMENT BONDS--CONSTRUCTION (NOV 2006), which provides for additional bond protection and states that “[t]he Government may require additional performance and payment bond protection if the contract price is increased. The increase in protection generally will equal 100 percent of the increase in contract price.” (R4, tab 4a at 2126-27)

5. FAR 52.243-4, CHANGES (JUN 2007), provides—

(a) The Contracting Officer may, at any time, without notice to the sureties, if any, by written order designated or indicated to be a change order, make changes in the work within the general scope of the contract, including changes—

(1) In the specifications (including drawings and designs);

(2) In the method or manner of performance of the work;

(3) In the Government-furnished property or services; or

(4) Directing acceleration in the performance of the work.

....

(d) If any change under this clause causes an increase or decrease in the Contractor's cost of, or the time required for, the performance of any part of the work under this contract, whether or not changed by any such order, the Contracting Officer shall make an equitable adjustment and modify the contract in writing. However, except for an adjustment based on defective specifications, no adjustment for any change under paragraph (b) of this clause shall be made for any costs incurred more than 20 days before the Contractor gives written notice as required. In the case of defective specifications for which the Government is responsible, the equitable adjustment shall include any increased cost reasonably incurred by the Contractor in attempting to comply with the defective specifications.

(e) The Contractor must assert its right to an adjustment under this clause within 30 days after (1) receipt of a

3 written change order . . . or (2) the furnishing of a written notice under paragraph (b) . . .

(R4, tab 4a at 2151-52)

6. On September 11, 2018, JAAAT filed nine appeals based on USACE denial of eight (8) Requests for Equitable Adjustments (REAs), ASBCA Nos. 61792, 61794, 61795, 61796, 61797, 61798, 61799, 61800; and one (1) deemed denial assigned ASBCA No. 61793, where the government had no records. The nine REAs are dated between September 30, 2014, and April 5, 2017, and requested an increase to the task order totaling $10,217,851 4 and a time extension of 847 days. 5 (R4, tab 3a at 3; gov’t mot. at 1; app. resp. at 1-2)

ASBCA NO. 61792 (STORMWATER) 6 SOF

7. On April 17, 2014, the contracting officer issued Modification No. 4 addressing work associated with the CS003 Stormwater requirements. The modification provided for a decrease to the contract price in the amount of $75,973.61 and an extension of 156 calendar days, extending the contract to October 11, 2014 (R4, tab 4f at 2232).

8. By letter dated May 20, 2014, JAAAT submitted a request for equitable adjustment (REA alleging a defective USACE Master Plan and a “defective [RFP/]Specification” that did not identify the installation of roadways and stormwater features, and estimating the cost impact to be at least $5,300,000 and a time impact of at least 376 calendar days (R4, tab 7m at 2353, 2360, 2366, 2378, 2393, 2397, 2401).

9. In response to the Board’s April 11, 2019 Order, to address the parties’ positions on jurisdiction in Appeal No. 61792, the government responded by

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mollan v. Torrance
22 U.S. 537 (Supreme Court, 1824)
United States v. Callahan Walker Construction Co.
317 U.S. 56 (Supreme Court, 1942)
First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Lujan v. National Wildlife Federation
497 U.S. 871 (Supreme Court, 1990)
Keene Corp. v. United States
508 U.S. 200 (Supreme Court, 1993)
Scott v. Harris
550 U.S. 372 (Supreme Court, 2007)
M. Maropakis Carpentry, Inc. v. United States
609 F.3d 1323 (Federal Circuit, 2010)
Barefoot Architect, Inc. v. Bunge
632 F.3d 822 (Third Circuit, 2011)
States Roofing Corporation v. Winter
587 F.3d 1364 (Federal Circuit, 2009)
LAI Services, Inc. v. Gates
573 F.3d 1306 (Federal Circuit, 2009)
Bell Bci Co. v. United States
570 F.3d 1337 (Federal Circuit, 2009)
Renda Marine, Inc. v. United States
509 F.3d 1372 (Federal Circuit, 2007)
Lutz v. United States Postal Service
485 F.3d 1377 (Federal Circuit, 2007)
Teg-Paradigm Environmental, Inc. v. United States
465 F.3d 1329 (Federal Circuit, 2006)
Bruce Construction Corporation v. The United States
324 F.2d 516 (Court of Claims, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
JAAAT Technical Services, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jaaat-technical-services-llc-asbca-2021.