Renda Marine, Inc. v. United States

509 F.3d 1372, 2007 U.S. App. LEXIS 28552, 2007 WL 4302725
CourtCourt of Appeals for the Federal Circuit
DecidedDecember 11, 2007
Docket2006-5127
StatusPublished
Cited by67 cases

This text of 509 F.3d 1372 (Renda Marine, Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Renda Marine, Inc. v. United States, 509 F.3d 1372, 2007 U.S. App. LEXIS 28552, 2007 WL 4302725 (Fed. Cir. 2007).

Opinion

SCHALL, Circuit Judge.

This is a government contract case. Renda Marine, Inc. (“Renda”), entered into Contract No. DACW64-99-C-0001 (“contract”) with the United States Army Corps of Engineers (“Corps”) for the dredging of a portion of the Houston-Galveston Navigation Channel (“navigation channel”). The contract was governed by the Contract Disputes Act of 1978, as amended (“CDA”). 41 U.S.C. §§ 601-13 (2000). Upon completion of the dredging work, Renda submitted various claims to the contracting officer (“CO”) seeking additional compensation under the contract. Following the denial of those claims, Ren-da filed suit in the United States Court of Federal Claims pursuant to 41 U.S.C. § 609(a)(1). On July 28, 2005, following a trial, the Court of Federal Claims issued a decision holding that Renda was not entitled to recover on its claims. Renda Marine, Inc. v. United States, 66 Fed.Cl. 639 (2005) (“Merits Decision”). Subsequently, on June 30, 2006, the court issued a decision denying Renda’s motion for reconsideration of certain prior rulings of the court. Renda Marine, Inc. v. United States, 71 Fed.Cl. 782 (2006) (“Reconsideration Decision”). In those prior rulings, the court had denied Renda’s motion for leave to amend its complaint to challenge a decision of the CO asserting government claims against Renda. The court did so on the ground that Renda’s challenge to the CO’s decision was untimely. Following its denial of Renda’s motion for reconsideration, the Court of Federal Claims entered final judgment in the case in favor of the United States. Renda has timely appealed from that judgment. We affirm.

BACKGROUND

I.

Renda is a marine dredging contractor. Under the contract, it was required to increase the depth of the navigation channel to -45 feet Mean Low Tide (“MLT”). Merits Decision at 657. This means that the channel had to be dredged to a depth 45 feet below its level at MLT.

During the period between January and October of 2001, Renda submitted various claims to the CO, including seven differing site condition claims. Reconsideration Decision at 784. After its claims were denied, on April 11, 2002, Renda filed suit in the Court of Federal Claims. Id. In its suit, Renda challenged the CO’s denial of its seven differing site condition claims, as well as the CO’s denial of an additional claim that was based upon the Corps’ alleged constructive modification of the contract. See Merits Decision at 642. Based upon its claims, Renda sought additional compensation under the contract in the total amount of $14,244,848. Id.

*1375 During the period between February 28, and April 7, 2005, the Court of Federal Claims conducted a trial on Renda’s eight claims. Id. at 643. Thereafter, on July 28, 2005, the court issued a decision in favor of the government, holding that Ren-da was not entitled to recover on any of its claims. Id. at 721.

II.

On November 26, 2002, while Renda’s suit was pending in the Court of Federal Claims, the CO issued a final decision under the contract asserting six separate government claims against Renda, in the total amount of $11,860,016. Reconsideration Decision at 784. In his final decision, the CO informed Renda that it had the right to appeal the decision to the Armed Services Board of Contract Appeals (“ASBCA”) within 90 days of receipt of the decision, see 41 U.S.C. § 606, or to initiate an action in the Court of Federal Claims within twelve months of receipt of the decision, see Id. § 609(a)(3). Reconsideration Decision at 784.

Renda received the CO’s final decision on or about November 26, 2002. Id. at 784-85. Thus, it had until February 24, 2003 to challenge the decision in the board of contract appeals and until November 26, 2003 to do so in the Court of Federal Claims. Renda, however, did not pursue either course. Instead, on July 1, 2004, roughly nineteen months after the approximate date on which it received the final decision, it sought leave to amend its complaint in the ongoing Court of Federal Claims litigation in order to challenge the validity of the decision there. Id. at 785. The Court of Federal Claims denied Ren-da’s motion on July 30, 2004, on the ground that Renda’s challenge to the CO’s decision was untimely. Id. Subsequently, on April 19, 2005, the court denied a second motion by Renda to amend its complaint to challenge the CO’s decision, again on the ground that Renda’s challenge to the decision was untimely. Id.

On June 1, 2005, following the completion of trial, but prior to the issuance of the Merits Decision, Renda sought reconsideration of the Court of Federal Claims’ decision denying its motion for leave to amend its complaint. Id. at 786. In its motion, Renda asserted that the government claims in the CO’s November 26, 2002 decision were related to the claims in Renda’s suit in the Court of Federal Claims. Starting from this premise and relying upon our decision in Sharman Co. v. United States, 2 F.3d 1564 (Fed.Cir.1993), overruled on other grounds by Reflectone, Inc. v. Dalton, 60 F.3d 1572 (Fed. Cir.1995) (en banc), Renda argued that its suit divested the CO of authority to render a final decision on the government’s claims, thereby rendering the CO’s November 26, 2002 decision a nullity inasmuch as it issued after the initiation of litigation by Renda. Reconsideration Decision at 786. On June 30, 2006, the court denied Renda’s motion, holding that, because Renda had failed to appeal the CO’s final decision within the twelve-month period set forth in the CDA, 41 U.S.C. § 609(a)(3), Renda was precluded from challenging the validity of the decision. Reconsideration Decision at 797.

On June 30, 2006, based upon the Merits Decision and the Reconsideration Decision, the court entered final judgment in favor of the United States. As noted, Renda has timely appealed from that judgment. We have jurisdiction pursuant to 28 U.S.C. § 1295(a)(3).

DISCUSSION

On appeal, Renda challenges both the Merits Decision and the Reconsideration Decision. As far as the former is concerned, Renda argues that the Court of Federal Claims erred insofar as it denied *1376 Renda compensation for one of its seven differing site condition claims. That claim involved a section of the navigation channel known as the “Flare Area.” Turning to the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Maverick Constructors, LLC
Armed Services Board of Contract Appeals, 2025
Nova group/tutor-saliba v. United States
87 F.4th 1375 (Federal Circuit, 2023)
Greene v. United States
Federal Circuit, 2023
Martin v. United States
Federal Circuit, 2023
Peretz v. United States
Federal Circuit, 2022
Matter of Prismatic Dev. Corp. v. New York City Tr. Auth.
2021 NY Slip Op 07072 (Appellate Division of the Supreme Court of New York, 2021)
Harry Pepper and Associates, Inc.
Armed Services Board of Contract Appeals, 2021
JAAAT Technical Services, LLC
Armed Services Board of Contract Appeals, 2021
Corinthian-WBCM, a Joint Venture
Armed Services Board of Contract Appeals, 2021
Peretz v. United States
Federal Claims, 2020
Mooney v. United States
Federal Circuit, 2020
Maehr v. United States
Federal Circuit, 2019

Cite This Page — Counsel Stack

Bluebook (online)
509 F.3d 1372, 2007 U.S. App. LEXIS 28552, 2007 WL 4302725, Counsel Stack Legal Research, https://law.counselstack.com/opinion/renda-marine-inc-v-united-states-cafc-2007.