Maverick Constructors, LLC

CourtArmed Services Board of Contract Appeals
DecidedFebruary 19, 2025
Docket61989
StatusPublished

This text of Maverick Constructors, LLC (Maverick Constructors, LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maverick Constructors, LLC, (asbca 2025).

Opinion

DOCUMENT FOR PUBLIC RELEASE. The decision issued on the date below is subject to an ASBCA Protective Order. This version has been approved for public release.

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Maverick Constructors, LLC ) ASBCA No. 61989 ) Under Contract No. W912EP-13-C-0033 )

APPEARANCES FOR THE APPELLANT: James E. Krause, Esq. James E. Krause, P.A. Jacksonville, FL

Joseph W. Lawrence, II, Esq. Vezina, Lawrence & Piscitelli, P.A. Fort Lauderdale, FL

Devin Maxwell, Esq. Law Offices of Devin Maxwell Okeechobee, FL

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Kristin Bigham, Esq. Sharon Shim, Esq. Catherine Awasthi, Esq. James M Zaleski, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Jacksonville

OPINION BY ADMINISTRATIVE JUDGE WILSON

This appeal arises from a construction project in Hendry County, Florida. Appellant, Maverick Constructors, Inc. (Maverick or appellant), challenges the contracting officer’s denial of all nine of its certified claims. Within these claims, appellant argues that it is entitled to monetary compensation and time extensions for delays associated with certain issues that it allegedly encountered during construction, including a differing site condition, a constructive change, a design defect, and the government’s alleged decision to delay the contract closing date. DOCUMENT FOR PUBLIC RELEASE. The decision issued on the date below is subject to an ASBCA Protective Order. This version has been approved for public release.

The Board conducted six hearing dates between January and August 2022, at which Vice Chairman Shackleford presided 1. For the reasons stated below, the Board denies the appeal in its entirety.

FINDINGS OF FACT

1. On August 9, 2013, the United States Army Corps of Engineers (USACE or Corps) issued Solicitation No. W912EP‐13‐B‐0006 for the construction of “water resource area levees, canals, pumping stations, control structures, siphon, access roadways, and associated appurtenant work” in connection with the Big Cypress Seminole Indian Reservation Western Water Conservation Restoration Project, Basin 2 and Siphon 2 (“the Project”) in Hendry County, Florida (R4, tab 5 at 1044, 1289).

2. The Project aimed to “rehydrate wetlands, improve water quality and water storage capacity on the Seminole Tribe’s Big Cypress Basin Reservation, the Big Cypress National Preserve, and the Everglades Protection Area” (compl. ¶ 29).

3. The Solicitation stated that the scope of work to be performed in Basin 2 would include:

a. Clearing and grubbing of right‐of‐ways for levee and canal construction. b. Excavation of canals and placement of compacted embankment fill for levees, berms, and access roadways for Water Resource Areas 2E and 2W. c. Excavation of new drainage canals and cleaning of existing drainage canals. d. Installation of Siphon 2 including inlet and outlet control structures, 60" diameter piping, and excavation of spreader canals. e. Construction of four pumping stations. f. Installation of water control structures fabricated from corrugated aluminum culverts. Structures may include light duty sluice gates, concrete headwalls, and access catwalks. g. Installation of 42" diameter piping for a level equalizing structure between Water Resource Areas 2E and 2W.

1 Although Vice Chairman Shackleford was the presiding judge at the hearing, he retired prior to the issuance of this decision. 2 DOCUMENT FOR PUBLIC RELEASE. The decision issued on the date below is subject to an ASBCA Protective Order. This version has been approved for public release.

h. Installation of new culverts and citrus grove bed drainage pipes along the alignments of new canals. i. Installation of barbed wire fencing, cattle gates, guardrail, and fabricated security gates. j. Construction of lime rock surfaced access roads where indicated for subsequent operation of the project.

(id. ¶ 32)

4. Along with the Solicitation, the government provided potential bidders with information regarding a pre-bid site visit, a bid schedule, design drawings and specifications drafted by the government, engineering and soil studies, a pricing schedule and measurement of quantities, and soil investigation information (id. ¶¶ 32- 33). Contractors had no input in drafting any of the specifications and were not permitted to deviate from the solicitation's requirements (see R4, tab 5 at 1067) (“DESIGN AUTHENTICATION This project was designed by Burns & McDonnell Inc. for the Jacksonville District, U.S. Army Corps of Engineers”).

5. On September 27, 2013, the government awarded firm-fixed-price Contract No. W912EP-13-C-0033 (contract) to Maverick (R4, tab 5 at 1042-2019). Mr. Carlos Rodriguez is the president of Maverick (tr. 1/33).

6. Maverick hired Close Construction, LLC (Close) to serve as the project’s first tier subcontractor. Mr. Thomas Close is the president of Close (app. supp. R4, tab 192 at 12367-12416; tr. 1/40-41; 3/9).

7. The subcontract between Maverick and Close allowed pass-through claims as needed (app. supp. R4, tab 192 at 12378, 12382). Specifically, the subcontract stated that “[t]he Contractor agrees to permit the Subcontractor to prosecute and claim, in the name of the Contractor, for the use and benefit of the Subcontractor in the manner provided in the Contract Documents for similar claims by the Contractor upon the Agency” (id. at 12378). In addition, the subcontract stated that the subcontractor shall have the full responsibility for the preparation and presentation of such pass- through claims (id. at 12382).

8. Close hired Cliff’s Trucking, Inc. (Cliff’s) to serve as its subcontractor; Mr. Clifford Lakeman is Cliff’s vice president (tr. 1/40-41, 61, 63-66; app. supp. R4, tab 344 at 21564).

9. On December 6, 2013, Maverick received the Notice to Proceed establishing a project completion date of April 20, 2015 (R4, tab 6 at 2020-21; see also R4, tab 5

3 DOCUMENT FOR PUBLIC RELEASE. The decision issued on the date below is subject to an ASBCA Protective Order. This version has been approved for public release.

at 1129).

10. The contract incorporated the following Federal Acquisition Regulation (FAR) clauses by reference: FAR 52.233-1, DISPUTES (JUL 2002); FAR 52.236-2, DIFFERING SITE CONDITIONS (APR 1984); FAR 52.242-14, SUSPENSION OF WORK (APR 1984); FAR 52.236-16, QUANTITY SURVEYS (APR 1984), paragraph (b); and FAR 52.243-4, CHANGES (JUN 2007) (R4, tab 5 at 1110; compl. ¶ 36).

11. The contract also incorporated FAR 252.201-7000, CONTRACTING OFFICER’S REPRESENTATIVE (DEC 1991) (R4, tab 5 at 1220). Specifically, the contract stated that the contracting officer may designate a contracting officer’s representative (COR) to perform “specific technical or administrative functions” and that the contractor shall not accept any instructions issued by any person other than the CO or the COR acting within the limits of the COR’s authority (id. at 1220, 1246). In addition, the notice of contract award provided that only a warranted contracting officer, defined as either a Procuring Contracting Officer (PCO) or an Administrative Contracting Officer (ACO), “acting within their designated limits, has the authority to issue modifications or otherwise change the terms and conditions of this contract” (id. at 1042).

Contract Provisions Regarding Excavation and Levee Construction

12. The contract directed Maverick to excavate canals and place specified quantities of compacted embankment fill for levees (R4, tab 5 at 1289, 1948, 1956; tr. 2/89; see also gov’t br. at 7).

13. Specifically, the contract required Maverick to use “satisfactory materials” in the completion of this task, including “imported fill . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Precision Pine & Timber, Inc. v. United States
596 F.3d 817 (Federal Circuit, 2010)
United States v. Spearin
248 U.S. 132 (Supreme Court, 1918)
Hercules, Inc. v. United States
516 U.S. 417 (Supreme Court, 1996)
Renda Marine, Inc. v. United States
509 F.3d 1372 (Federal Circuit, 2007)
Centex Corp. v. United States
395 F.3d 1283 (Federal Circuit, 2005)
The Len Company and Associates v. The United States
385 F.2d 438 (Court of Claims, 1967)
Metcalf Construction Company v. United States
742 F.3d 984 (Federal Circuit, 2014)
Agility Public Warehousing Co. KSCP v. Mattis
852 F.3d 1370 (Federal Circuit, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Maverick Constructors, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maverick-constructors-llc-asbca-2025.