Nova group/tutor-saliba v. United States

CourtUnited States Court of Federal Claims
DecidedMarch 17, 2022
Docket15-885
StatusPublished

This text of Nova group/tutor-saliba v. United States (Nova group/tutor-saliba v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nova group/tutor-saliba v. United States, (uscfc 2022).

Opinion

Sn the Anited States Court of Federal Clauns

Nos. 15-885C, 16-925C (Reissued: March 17, 2022)!

MM Re eK Contract Disputes Act; Construction; Type I Differing Site Condition; Type II Differing Site Condition; Defective Specifications;

NOVA GROUP/TUTOR-SALIBA, A Joint Venture,

Design Specifications; Suspension of Critical Path Work; Excusable Delay; Constructive Acceleration; Damages; Overtime; Lost Productivity; Modified Total Cost Approach; Equipment Expense; Reopening the Record to Admit an Exhibit Post-Trial; FAR 52.244-4; FAR 52.243-4(d).

Gerald Scott Walters, Smith Currie & Hancock, LLP, 245 Peachtree Center Avenue, NE, 2700 Marquis One Tower, Atlanta, GA 30303-1227, and Brian S. Wood, and Sarah K. Carpenter, Smith Currie & Hancock, LLP, 1025 Connecticut Avenue, NW, Suite 600, Washington, DC, 20036, for Plaintiff.

Plaintiff, Vv. THE UNITED STATES,

Defendant.

x + & + &£ © & £ & & H& HF X

RAK ARK KKK KK ARK AKA KAKAKRAKRAKRAKR AKER

Joseph H. Hunt, Robert E. Kirschman, Jr., Steven J. Gillingham, and Adam E. Lyons, United States Department of Justice, Civil Division, Commercial Litigation Branch, P.O. Box 480, Ben Franklin Station, Washington, D.C. 20044, for Defendant. David M. Marquez, Naval Litigation Office, Office of General Counsel, United States Department of the Navy, 720 Kennon St., Room 223, Washington Navy Yard, D.C. 20374, and Melissa L. Baker, Andrew J. Hunter, and Kristin B. McGrory, United States Department of Justice, Civil Division, Commercial Litigation Branch, P.O. Box 480, Ben Franklin Station, Washington, D.C. 20044, of Counsel.

POST-TRIAL OPINION AND ORDER

WILLIAMS, Senior Judge.

These consolidated Contract Disputes Act (“CDA”) cases come before the Court following atrial on liability and damages. Plaintiff Nova Group/Tutor-Saliba (“NTS”), a joint venture raises two claims. First, Plaintiff seeks $1,881,900 for a constructive change due to the Government’s

! The Court issued this opinion under seal on February 28, 2022 and directed the parties to

file any proposed redactions by March 14. Because the parties requested no redactions, the Court reissues the opinion as is. questioning of its design of a pier at the Puget Sound Naval Shipyard. The Government’s issue with the design caused a stoppage of critical path work, an independent review after the Government previously approved that design, and an ensuing acceleration of work. Second, Plaintiff seeks $10,498,284.85 for extra work caused by differing site conditions or defective specifications. For the reasons stated below, the Court grants Plaintiff's design-related claim in part and denies its differing site conditions/defective specifications claim.

Findings of Fact?

The Pier B Project

The P-356 Carrier Vessel Nuclear (“CVN”) Maintenance Pier Replacement Project (“Project”) at the Puget Sound Naval Shipyard and Intermediate Maintenance Facility was a design and construction project for the replacement and upgrade of various waterfront substructures at Naval Base Kitsap, Bremerton, Washington. JX 2.1; DX 2.5. The Project involved the demolition of the existing Pier B (“Old Pier”), a 60-foot wide and 1,175-foot long pier, and the design and construction of an 85-foot wide and 1,325-foot long replacement pier (“Pier B”) for the berthing of CVN-class aircraft carriers, supporting vessels, and submarines for repair operations. JX 2.536, .2618; Tr. 78.

The Old Pier extended south into Puget Sound from the east-west shoreline. See JX 2.1216; PX 39.36. Pier B was to partially overlap the area of the Old Pier. While Pier B would share its western border with the entire Old Pier, it was to be longer to the south, and wider to the east. See PX 39.36; Tr. 82-84. The Project also contemplated that the contractor would join Pier B and a new parallel structure to the east, the Mole Quaywall, to create a contiguous surface. JX 2.537, .1220; compare JX 2.1219 with JX 2.1220. The drawing below indicates the location of Pier B (outlined in red) as compared to the Old Pier:

These findings of fact are derived from the record developed during a 12-day trial.

Additional findings of fact are in the Discussion. The Court uses “PX” to cite Plaintiffs exhibits, “DX” to cite Defendant’s exhibits, “JX” to cite joint exhibits, and “Tr.” to cite testimony. The Court does not correct grammatical errors in quotations from the record.

« ?

“ i Wi6-67

| & weer Gp Wre-68166

Approximate Location

ices-203 oc Mole Quaywall

oe GpHces-P6o

B2 =~ j (Sincere e

Approxi ion Pie! Approximate Location Pier B Frierto Demolition:

4 foe

5155 >

3END

id, Octagonal, Pre

ce-i@ ~

a n. Solid, Octagonal 1K a CMD te Pile withaut Stes jgnation and Ap

NB ® in. Borings NB-1 tl

Previous Boring Designaton and I Location by Shannon & Wilson P-366 CVN Pier Replacement Naval Ba >

Bremerton

SW06-B-1 @

Previous Horing Designaton and

HC06-104 @

gton

bonng locations were e considered apon

Designation ang

SITE AND EXPLORATION PLAN

3. Shannon & Wilson boring locations perfo SWO6-B-5) were surveyed by KPFF Seale in Feet

May 2011 21-1-21017-101

SHANNON & WILSON, INC. FIG. 4 Cesta and Ervioamenil Gonmuliat

4 Barings performed for the current study were taped from existing features

PX 39.36.

In addition to work on Pier B, the Project required that the contractor construct a new Mole Quaywall -- a continuous steel-coated sheet pile bulkhead with solid prestressed concrete piles, approximately 22-feet, 6-inches wide by 1,000-feet long, that would buttress the west side of Dry Dock 6, which ran parallel to the Old Pier. Under this Project, the contractor was also to demolish and replace portions of Quaywall 729 -- “a two-level reinforced concrete structure consisting of a concrete deck, columns, and framing members, supported by timber piles.” JX 2.536; Tr. 79-80, 88; Tr. 1947-48.

The Shannon & Wilson 2006 Report

Prior to seeking proposals for the Project, the Navy hired a construction engineering firm, KPFF Consulting Engineers (“KPFF”), and its geotechnical subcontractor, Shannon & Wilson, Inc. (“Shannon & Wilson’), to conduct a preliminary geological study. DX 2.1, .5; Tr. 456. On April 24, 2006, Shannon & Wilson provided its conclusions to KPFF in its Preliminary Geotechnical Report (“2006 Report”). DX 2.1; Tr. 541.

The 2006 Report contained “the results of the geotechnical baseline information for the use by design-build (DB) contractors, and conceptual geotechnical engineering recommendations for use by KPFF Consulting Engineers (KPFF) in evaluating potential structure configurations for the project.” DX 2.5. The 2006 Report specified: “[t]he recommendations provided in this report should not be used for final design.” DX 2.7. In addition, the 2006 Report expressly stated that it “was prepared for the exclusive use of KPFF and NAVFAC NW,” and that it “should be made available to prospective DB contractors for information on factual data only, and not as a warranty

of subsurface conditions such as those interpreted from the subsurface profile and presented in the discussion of subsurface conditions.” Id.

For its evaluation and findings regarding Pier B, Shannon & Wilson relied on “existing subsurface information from previous projects performed at or near the project site,” as well as drilling and sampling five borings during a two-and-a-half-week field exploration. DX 2.7-.8, .37. “[T]he subsurface explorations were performed along the east side of the existing Pier B,” and “no borings were performed overwater in the slip between the drydock mole and the pier, or to the south of the existing pier.” DX 2.9.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Precision Pine & Timber, Inc. v. United States
596 F.3d 817 (Federal Circuit, 2010)
Globe Refining Co. v. Landa Cotton Oil Co.
190 U.S. 540 (Supreme Court, 1903)
United States v. Spearin
248 U.S. 132 (Supreme Court, 1918)
Renda Marine, Inc. v. United States
509 F.3d 1372 (Federal Circuit, 2007)
Ace Constructors, Inc. v. United States
499 F.3d 1357 (Federal Circuit, 2007)
International Data Products Corp. v. United States
492 F.3d 1317 (Federal Circuit, 2007)
J. L. Simmons Company, Inc. v. The United States
412 F.2d 1360 (Court of Claims, 1969)
Blinderman Construction Co., Inc. v. The United States
695 F.2d 552 (Federal Circuit, 1982)
Stuyvesant Dredging Company v. The United States
834 F.2d 1576 (Federal Circuit, 1987)
Neal & Company, Inc. v. United States
121 F.3d 683 (Federal Circuit, 1997)
H.B. Mac, Inc. v. United States
153 F.3d 1338 (Federal Circuit, 1998)
Comtrol, Inc. v. United States
294 F.3d 1357 (Federal Circuit, 2002)
Scott Timber Company v. United States
333 F.3d 1358 (Federal Circuit, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
Nova group/tutor-saliba v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nova-grouptutor-saliba-v-united-states-uscfc-2022.