Lockheed Martin Ir Imaging Systems, Inc. v. Togo D. West, Jr., Secretary of the Army

108 F.3d 319, 41 Cont. Cas. Fed. 77,052, 1997 U.S. App. LEXIS 3829, 1997 WL 88998
CourtCourt of Appeals for the Federal Circuit
DecidedMarch 4, 1997
Docket96-1087
StatusPublished
Cited by92 cases

This text of 108 F.3d 319 (Lockheed Martin Ir Imaging Systems, Inc. v. Togo D. West, Jr., Secretary of the Army) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lockheed Martin Ir Imaging Systems, Inc. v. Togo D. West, Jr., Secretary of the Army, 108 F.3d 319, 41 Cont. Cas. Fed. 77,052, 1997 U.S. App. LEXIS 3829, 1997 WL 88998 (Fed. Cir. 1997).

Opinion

PAULINE NEWMAN, Circuit Judge.

Lockheed Martin IR Imaging Systems, Inc. appeals from the final decision of the Armed Services Board of Contract Appeals, Loral Infrared & Imaging Systems, Inc. v. West, ASBCA No. 45744, 95-2 BCA ¶ 27,803, holding that Loral 1 is not entitled to recover certain increased costs incurred in its contract to provide certain products to the Army. We conclude that the Army constructively changed the contract by departing from its option terms, and that Loral is entitled to an appropriate adjustment. The Board’s decision as to liability is reversed; we remand for determination of quantum.

THE SEALED BID OPTION PROVISION

The United States Army Communications-Electronics Command (CECOM) issued fixed-price sealed bid Solicitation No. DAAB07-91-B-M152. In sealed bid procurements the government solicits bids by issuing an Invitation For Bids (IFB). The IFB is not an offer by the government to purchase goods or services: the prospective contractor’s bid is the offer, and the government’s award of the contract is the acceptance. J. Cibinic & R. Nash, Formation of Government Contracts 153 (2d ed.1986). In sealed bid procurements, acceptance by the government is made without negotiation or material variation from the terms of the contractor’s offer. 10 U.S.C. § 2305(b)(3); Federal Acquisition Regulation 14.101(e); CRF v. United States, 224 Ct.Cl. 312, 624 F.2d 1054, 1060 (1980).

The solicitation was for the fabrication and delivery of 779 Detector Cooler Assemblies and 779 accompanying Warranty of Supplies, and an option provision whose meaning is the subject of this dispute. Contract Line Item No. (CLIN) 0001 of the solicitation included the following statement concerning the option:

A 100% OPTION TO INCREASE QUANTITY PROVISIONS IS INCLUDED. SEE CLIN 0018.

CLIN 0018, in Section B of the solicitation, repeated this aspect of CLIN 0001 as follows:

THIS IS A 100% OPTION FOR CLIN 0001 FOR A QUANTITY OF 779 EACH. SEE SECTION H, ‘OPTION REQUIREMENTS’ AND SECTION M, ‘EVALUATION OF OPTIONS.’

Sub Line Item No. (SLIN) 0018AA stated the “Deliveries or Performance” of the option quantity, as follows:

*321 DEL REL CD QUANTITY DEL DATE

001 779 Undefinitized

The Board found that the solicitation required the bidder to submit a price for the entire option quantity, that is, for “the option included in the solicitation.” The Board found that although not required to do so, the bidder was permitted to offer various prices for varying option quantities. Paragraph M-2, entitled “EVALUATION OF OPTIONS,” states:

M-2. If varying option prices are offered depending on the quantities actually ordered and/or the dates when ordered, only the price offered for the maximum option quantity, to be ordered on the last day on which the option may be exercised, will be considered in the evaluation for award. Regardless of the price considered in the evaluation for award, however, the Government may exercise the option for quantities less than the maximum and prior to the last day for exercise, at the option price offered for that particular quantity and order date.

Section H-4 of the solicitation, by provision entitled “OPTION FOR INCREASED QUANTITY-SEPARATELY PRICED LINE ITEM,” states:

H-4a. The Government may require delivery of the option numbered CLIN/SLIN identified in Section B in the quantity and at the unit price specified in Section B. The contracting officer may exercise this option at any time and from time to time, from date of award until 120 DAYS PRIOR TO LAST SCHEDULED PRODUCTION DELIVERY, by giving written notice to the contractor.

In its response to the solicitation, Loral offered the “100% option” for 779 Assemblies at a unit price of $9,415, and the accompanying warranty for 779 Assemblies at a unit price of $389. These were the same prices as for the principal contract quantity of 779. Loral did not offer lesser quantities or varying option prices depending on quantities or order dates. Loral’s offer was for the 100% option set forth in CLIN 0018: “This is a 100% option for CLIN 0001 for a quantity of 779 each.”

The Army accepted Loral’s sealed bid, and sent Loral the signed contract containing the terms as bid. However, the Army also sent Loral a document entitled “Supplemental Information, AWARD/CONTRACT ADDENDUM,” which stated:

1. SECTION B, STANDARD FORM 36, ATTACHED TO THIS ADDENDUM, IS DEFINITIZED TO REFLECT:
A. THE ITEM PRICE AND QUANTITIES BEING PROCURED.
B. THE ACCEPTABLE DELIVERY SCHEDULE DATES FOR THE ITEMS PURCHASED.
C. THE ACCOUNTING CLASSIFICATION AND THE AMOUNT OF FUNDS OBLIGATED BY THE GOVERNMENT TO PROCURE THE ITEMS SET FORTH IN THIS ADDENDUM.
2. OPTION FOR INCREASED QUANTITY UP TO 779 EACH SHALL BE AT A UNIT PRICE OF $9,415.00 EACH.

The Army states that this Addendum “clarified” that the contract was not for the 100% option, but was for “up to” the 100% option quantity at the unit price in Loral’s bid. Loral states that the contract award, by statute and regulation, was complete in accordance with its terms. Loral states that it was impermissible for the Army, unilaterally, to change the terms of the sealed bid solicitation after the contract had been bid and awarded, and that the Addendum is of no contractual significance.

The Army duly sought less than 100% option quantities. The contracting officer issued unilateral contract modification P00001, titled “partial exercise” of the option, for a total of 131 assemblies at the unit price of $9,415, which was the 100% option price. Loral protested this exercise of less than the 100% option. The Army insisted, and Loral complied while reserving its right to recompense, asserting constructive change. Two months later the Army issued unilateral modification P00002 for 4 additional assemblies, again at the 100% option unit price. Loral again complied under protest. No other quantities were ordered.

*322 Loral submitted a claim for additional compensation. The contracting officer, denying the claim, stated the Army’s position that the contract was not for a 100% option and that any quantity, at the Army’s choice, could have been ordered at the same unit price Loral had offered for the 100% option. The Army relies on Section M-2 of the solicitation, quoted supra, as notifying Loral that this was not a 100% option contract. The Army states that Loral was required by Section M-2 to offer varying option prices to accommodate any quantity up to 779, and that since Loral did not do so, it meant that Loral’s option price was the same for any quantity the Army might decide to order and any order date.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cynthia Caputo v. Department of Defense
Merit Systems Protection Board, 2024
Vigor Works, LLC
Armed Services Board of Contract Appeals, 2023
Martin Andersen v. Department of Defense
Merit Systems Protection Board, 2022
Flint v. United States
Federal Claims, 2022
Fluor Federal Solutions, Inc.
Armed Services Board of Contract Appeals, 2022
Richardson v. United States
Federal Claims, 2021
Kiewit Infrastructure West Co. v. United States
972 F.3d 1322 (Federal Circuit, 2020)
Omran Holding Group, Inc. v. United States
134 Fed. Cl. 561 (Federal Claims, 2017)
Stromness Mpo, LLC v. United States
134 Fed. Cl. 219 (Federal Claims, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
108 F.3d 319, 41 Cont. Cas. Fed. 77,052, 1997 U.S. App. LEXIS 3829, 1997 WL 88998, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lockheed-martin-ir-imaging-systems-inc-v-togo-d-west-jr-secretary-of-cafc-1997.