Coffman Specialties, Inc. v. United States

CourtUnited States Court of Federal Claims
DecidedOctober 31, 2019
Docket18-1882
StatusPublished

This text of Coffman Specialties, Inc. v. United States (Coffman Specialties, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coffman Specialties, Inc. v. United States, (uscfc 2019).

Opinion

In the United States Court of Federal Claims No. 18-1882C

(E-Filed: October 31, 2019)

) COFFMAN SPECIALTIES, INC., ) ) Plaintiff, ) ) v. ) Motion to Dismiss; RCFC 12(b)(6). ) THE UNITED STATES, ) ) Defendant. ) )

William J. Braun, La Jolla, CA, for plaintiff.

Daniel K. Greene, Trial Attorney, with whom were Joseph H. Hunt, Assistant Attorney General, Robert E. Kirschman, Jr., Director, Lisa L. Donahue, Assistant Director, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, DC, for defendant. Ellen Evans, Navy Litigation Office, Washington, DC, of counsel.

OPINION

CAMPBELL-SMITH, Judge.

On December 7, 2018, plaintiff filed its complaint alleging claims for relief related to its performance under a construction contract with the United States Department of the Navy, at Naval Air Facility El Centro, California. See ECF No. 1. Defendant moved the court to dismiss the first cause of action in plaintiff’s complaint on April 8, 2019. See ECF No. 7. Plaintiff filed its opposition to defendant’s motion for partial dismissal on May 6, 2019, see ECF No. 8; and defendant filed its reply in support of its motion on May 20, 2019, see ECF No. 9. The motion is fully briefed and ripe for decision by the court. For the following reasons, defendant’s motion is DENIED. I. Background

On or about September 28, 2015, plaintiff entered into Contract No. N62473-14- D-0044 with the Navy. See ECF No. 1 at 2. Under the contract, plaintiff was “required . . . to, among other things, repair Runway 12/30 including full depth runway reconstruction, repair of asphalt shoulders, demolition, and re-striping of pavement markings, along with pavement repairs . . . .” Id. (emphasis in original). Plaintiff was to “complete the work within 545 days after the Notice of Award, or by March 27, 2017.” Id.

In the complaint, plaintiff alleges two causes of action, only the first of which is the subject of defendant’s motion for partial dismissal. 1 Plaintiff claims, in its first cause of action, that it is entitled to recover costs associated with the disposal of excess soil because defendant improperly imposed expensive restrictions on plaintiff with regard to such disposal, which were contrary to the terms of the contract. See ECF No. 1 at 2-5. Plaintiff alleges that it relied on the contract terms when it arranged “to haul excess soil generated on the Project to a commercial farm located in El Centro owned and operated by Joe Heger (hereinafter the ‘Joe Heger Farms’).” Id. at 3. Defendant objected to plaintiff’s plan to “dispose of soil materials at Joe Heger Farms because it was not licensed or permitted.” Id. Plaintiff notified defendant that it considered defendant’s objection to be a “constructive change to the contract.” Id.

On June 15, 2016, plaintiff notified defendant that it would comply, “under protest,” with defendant’s “directive that the excess soil materials be hauled to either a licensed landfill facility or to a commercial recycling facility.” Id. Plaintiff hauled the excess soil to Republic Services, a commercial landfill. Id. at 4. Republic Services tested the soil, and deemed it contaminated, though plaintiff contends that the testing standards were “more stringent” than required by local, state, or federal regulations. Id. Plaintiff provided the testing data to defendant, “reflecting that the soil was contaminated with heavy metals and petroleum hydrocarbons, increasing Republic Services’ disposal costs by an estimated $17.00 to $19.00 per ton.” Id. The soil disposal effort was concluded by July 11, 2016, and plaintiff estimates that it incurred increased fees “in the approximate amount of $1,415,800.00 above what it would have paid had the material been hauled to Joe Heger Farms.” Id.

On October 31, 2016, plaintiff filed a Request for Equitable Adjustment in an effort to recover the $1,415,800.00, based on what it viewed as a constructive change to the contract. Id. Defendant denied plaintiff’s equitable adjustment request on December 14, 2016, on the basis that “Republic Services had not charged additional sums since they

1 For this reason, the court will focus on the facts relevant only to the first cause of action in this opinion.

2 considered the soil to be contaminated.” Id. Plaintiff submitted additional documentation to support their request the same day defendant denied the claim. See id. Thereafter, on February 28, 2017, defendant “informed [plaintiff] that its basic denial of the Request had not changed but that it would consider compensation of some expenses, and requested a cost breakdown ‘since the specifications did not identify potential contamination of the soils.’” Id. (quoting an uncited document). In response, plaintiff submitted a cost proposal on or about March 16, 2017, which defendant treated as a second Request for Equitable Adjustment. See id. at 5. Defendant denied the second equitable adjustment request on October 2, 2017. See id.

Plaintiff submitted a Contract Disputes Act Claim, pursuant to 41 U.S.C. § 601- 613, to the contracting officer on February 13, 2018. See id. 2 In its claim, plaintiff sought $1,409,254.00 in compensation “for its increased costs of disposing of the excess soil at a commercial landfill.” Id. The contracting officer issued her final decision denying plaintiff’s claim on April 11, 2018. Id.

On May 6, 2019, plaintiff filed the instant complaint. See ECF No. 1. Rather than file an answer, on April 4, 2019, the government moved for partial dismissal of the first cause of action in plaintiff’s complaint. See ECF No. 7. In their briefing on defendant’s motion for partial dismissal, the parties cite to a variety of contract provisions they believe are relevant to the court’s analysis. Plaintiff did not attach a copy of the contract to the complaint, see ECF No. 1; defendant attached excerpts of the contract to the motion for partial dismissal, see ECF No. 7 at 12-119; and plaintiff attached a separate excerpt of the contract to its response, see ECF No. 8-1. Neither party has provided the court with a complete copy of the contract.

II. Legal Standards

When considering a motion to dismiss brought under RCFC 12(b)(6), the court “must presume that the facts are as alleged in the complaint, and make all reasonable inferences in favor of the plaintiff.” Cary v. United States, 552 F.3d 1373, 1376 (Fed. Cir. 2009) (citing Gould, Inc. v. United States, 935 F.2d 1271, 1274 (Fed. Cir. 1991)). It is well-settled that a complaint should be dismissed under RCFC 12(b)(6) “when the facts asserted by the claimant do not entitle him to a legal remedy.” Lindsay v. United States, 295 F.3d 1252, 1257 (Fed. Cir. 2002). “To survive a motion to dismiss, a complaint must contain sufficient factual matter, accepted as true, to ‘state a claim to relief that is plausible on its face.’” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (quoting Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570 (2007)). In evaluating a motion to dismiss for

2 Plaintiff cites the Contract Disputes Act as set forth in 41 U.S.C. §§ 601-613, see ECF No. 1 at 5, but the relevant statutes are now codified at 41 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Cary v. United States
552 F.3d 1373 (Federal Circuit, 2009)
Gould, Inc. v. The United States
935 F.2d 1271 (Federal Circuit, 1991)
Daniel A. Lindsay v. United States
295 F.3d 1252 (Federal Circuit, 2002)
Dimare Fresh, Inc. v. United States
808 F.3d 1301 (Federal Circuit, 2015)
Lee's Ford Dock, Inc. v. Secretary of the Army
865 F.3d 1361 (Federal Circuit, 2017)
Merando, Inc. v. United States
475 F.2d 603 (Court of Claims, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
Coffman Specialties, Inc. v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coffman-specialties-inc-v-united-states-uscfc-2019.