Precision Standard, Inc.

CourtArmed Services Board of Contract Appeals
DecidedJuly 13, 2015
DocketASBCA No. 59116
StatusPublished

This text of Precision Standard, Inc. (Precision Standard, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Precision Standard, Inc., (asbca 2015).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Precision Standard, Inc. ) ASBCA No. 59116 ) Under Contract No. SPM4A7-08-M-B239 )

APPEARANCE FOR THE APPELLANT: Nancy M. Camardo, Esq. Camardo Law Firm, P.C. Auburn, NY

APPEARANCES FOR THE GOVERNMENT: Daniel K. Poling, Esq. DLA Chief Trial Attorney Robert E. Sebold, Esq. Trial Attorney DLA Aviation Richmond, VA

OPINION BY ADMINISTRATIVE JUDGE HARTMAN ON THE GOVERNMENT'S MOTION FOR SUMMARY JUDGMENT

The government moves for summary judgment, asserting that its contracting officer (CO) appropriately terminated appellant's contract for default because Precision Standard, Inc. (PSI) was delinquent in submitting the contractually required first article and PSI has provided no evidence of excusable delay. Appellant asserts the government's motion should be denied because there are genuine issues of material fact regarding: ( 1) why the CO did not exercise her discretion to terminate the contract at "no cost" and (2) why its lack of delivery of the first article here was not "excusable." According to PSI, it could not schedule the quality assurance representative (QAR) inspection necessary for first article delivery due to QAR scheduling problems arising from the "sequester" and furlough of government employees.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTION

In June 2008, the Defense Supply Center, Richmond (which has been renamed Defense Logistics Agency Aviation), a field activity of the Defense Logistics Agency (DLA), awarded a contract, No. SPM4A7-08-M-B239, for the supply of 32 aircraft "formers" for A-10 aircraft, National Stock Number (NSN) 1560-01-553-7553, part number 160414007-74, to appellant, PSI (R4, tab 1at1, 3). Aircraft "formers" are a "CRITICAL APPLICATION ITEM," where "failure ... could injure personnel or jeopardize a vital agency mission" (R4, tab 1 at 5; Federal Acquisition Regulation (FAR) 46.203(c)).

The parties' contract required PSI to submit a first article for testing by the Engineering Support Activity (ESA) for the A-10 aircraft program at Hill Air Force Base in Ogden, Utah (R4, tab 1 at 4-5, 10, 13-14). The first article was due 9 February 2009, and ESA had 120 days to evaluate that article. If ESA approved the article, the production quantity of 32 was due 200 days after the approval. (R4, tab 1 at 2, 9)

The parties' contract incorporated by reference various standard clauses, including FAR 52.209-4, FIRST ARTICLE APPROVAL - GOVERNMENT TESTING (SEP 1989); and FAR 52.249-8, DEFAULT (FIXED-PRICE SUPPLY AND SERVICE) (APR 1984). (R4, tab 1at15; FAR 52.252-2, CLAUSES INCORPORATED BY REFERENCE (FEB 1998)) The initial clause states:

(a) The Contractor shall deliver _ _ unit(s) of Lot/Item _ _ within _ _ calendar days from the date of this contract to the Government at [insert name and address of the testing facility] for first article tests ....

(b) Within _ _ calendar days after the Government receives the first article, the Contracting Officer shall notify the Contractor, in writing, of the conditional approval, approval, or disapproval of the first article ....

( c) If the first article is disapproved, the Contractor, upon Government request, shall submit an additional first article for testing .... The Contractor shall furnish any additional first article to the Government under the terms and conditions and within the time specified by the Government ....

( d) If the Contractor fails to deliver any first article on time, or the Contracting Officer disapproves any first article, the Contractor shall be deemed to have failed to make delivery within the meaning of the Default clause of this contract.

The latter clause states:

(a)(l) The Government may, subject to paragraphs (c) and (d) of this clause, by written notice of default to the

2 Contractor terminate this contract in whole or in part ifthe Contractor fails to -

(i) Deliver the supplies ... within the time specified in this contract or any extension;

(c) [Unless] the failure to perform the contract arises from causes beyond the control and without the fault or negligence of the Contractor.

PSI did not submit the first article by its due date, 9 February 2009 (R4, tab 8 at 6). Over three months after the due date, on 21May2009, PSI submitted a first article but material certifications, as well as process specifications for the passivate and heat treatment, were missing (R4, tab 8 at 6-21, tab 9 at 1-2). When PSI did not respond to requests for the missing materials, ESA disapproved the first article (R4, tab 10). By letter dated 17 November 2009, DLA's CO advised PSI that ifit paid extra costs incurred for government testing and offered DLA some other consideration for its contractor-caused delay, it could re-submit the disapproved first article after it had corrected the following discrepancies:

1. Print requirement is .32 R +/- .03; Actual measurement is one side is .28[,] the other is .32. 2. As per the contract page 4 item numbers 4, and 5 require that all material certs, and process certs and purchase orders; None were sent with the First Article, and these certifications were requested again through the DLA contracting office. The contractor sent none of the requested certifications.

The CO added that, on resubmission of the first article, a new delivery date would be established and memorialized in a contract modification. The CO further advised that PSI could alternatively: ( 1) submit a rebuttal letter regarding the first article test for review by both DLA and ESA or (2) request a no-cost cancellation/termination of the parties' contract and, if the request was acceptable to DLA, the parties' contract would be "cancelled or terminated." The CO stated PSI shall respond to her letter within ten workdays after receipt of her letter and, if it did not, the "contract may be cancelled or terminated without further notification." (R4, tab 10)

PSI submitted a rebuttal in January 2010 asserting, among other things, that it rejected any "no-cost" termination; the disparity in first article dimension could be readily corrected in production at minimal cost; and the sole material certification was

3 attached to the test report it submitted with the first article. It did not, however, furnish a copy of that certification (R4, tabs 13, 16). In June 2011, DLA's CO gave PSI the opportunity to submit a second first article and propose a revised delivery schedule for the contract (R4, tab 17 at 2).

By bilateral contract Modification No. POOOOl executed 18 December 2012, the parties established a new delivery date of 22 January 2013 for the first article (R4, tab 2 at 1-2, tabs 18, 19). PSI, however, did not submit a second first article by the specified date (R4, tab 21 ).

By letter dated 29 July 2013, DLA's CO sent PSI a letter stating she was considering terminating the parties' contract for default and PSI was being given the opportunity to present facts bearing on the question within ten days after receipt (R4, tab 21). While PSI received the CO's letter, it did not respond within the time specified (R4, tabs 22, 23).

DLA, however, provided PSI a third opportunity to submit a first article. By bilateral contract Modification No. P00002, the parties established a new delivery of 18 October 2013 for the first article. The parties also modified their contract to provide:

[I]fthe First Article re-submission is not delivered by the date ... [due] or ifthe First Article is disapproved, (second disapproval), this contract may be terminated in its entirety at no cost to the Government.

(R4, tab 3)

PSI again failed to submit a first article by the specified date (R4, tab 23 at 3, tab 24).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Jerome H. Lemelson v. Trw, Inc., and Conco, Inc.
760 F.2d 1254 (Federal Circuit, 1985)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Lisbon Contractors, Inc. v. The United States
828 F.2d 759 (Federal Circuit, 1987)
Gould, Inc. v. The United States
935 F.2d 1271 (Federal Circuit, 1991)
C. Sanchez and Son, Incorporated v. United States
6 F.3d 1539 (Federal Circuit, 1993)
Dcx, Inc. v. William J. Perry, Secretary of Defense
79 F.3d 132 (Federal Circuit, 1996)
King v. United States
37 Ct. Cl. 428 (Court of Claims, 1902)
Churchill Chemical Corp. v. United States
602 F.2d 358 (Court of Claims, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
Precision Standard, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/precision-standard-inc-asbca-2015.