Kiewit Infrastructure West Co. v. United States

972 F.3d 1322
CourtCourt of Appeals for the Federal Circuit
DecidedAugust 26, 2020
Docket19-2125
StatusPublished
Cited by9 cases

This text of 972 F.3d 1322 (Kiewit Infrastructure West Co. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kiewit Infrastructure West Co. v. United States, 972 F.3d 1322 (Fed. Cir. 2020).

Opinion

Case: 19-2125 Document: 30 Page: 1 Filed: 08/26/2020

United States Court of Appeals for the Federal Circuit ______________________

KIEWIT INFRASTRUCTURE WEST CO., Plaintiff-Appellant

v.

UNITED STATES, Defendant-Appellee ______________________

2019-2125 ______________________

Appeal from the United States Court of Federal Claims in No. 1:16-cv-00045-EJD, Senior Judge Edward J. Damich. ______________________

Decided: August 26, 2020 ______________________

JOHN SPENCER STEWART, Stewart Sokol & Gray, LLC, Portland, OR, for plaintiff-appellant. Also represented by TYLER J. STORTI.

SOSUN BAE, Commercial Litigation Branch, Civil Divi- sion, United States Department of Justice, Washington, DC, for defendant-appellee. Also represented by ETHAN P. DAVIS, ALLISON KIDD-MILLER, ROBERT EDWARD KIRSCHMAN, JR. ______________________ Case: 19-2125 Document: 30 Page: 2 Filed: 08/26/2020

Before PROST, Chief Judge, MAYER and LOURIE, Circuit Judges. MAYER, Circuit Judge. Kiewit Infrastructure West Co. (“Kiewit”) appeals the judgment of the United States Court of Federal Claims granting the government’s motion for summary judgment and denying Kiewit’s request for an equitable adjustment for the cost of purchasing certain wetland mitigation cred- its. See Kiewit Infrastructure West Co. v. United States, No. 1:16-cv-00045, 2019 WL 2156459 (Fed. Cl. May 15, 2019) (“Federal Claims Decision”). For the reasons discussed be- low, we reverse and remand. I. BACKGROUND On June 19, 2012, the Western Federal Lands High- way Division of the Federal Highway Administration (“FHA”) issued a solicitation for a road design and recon- struction project (the “Deweyville project”). See J.A. 321– 30; see also J.A. 331–32, 337. The project consisted of rea- ligning and reconstructing approximately twelve miles of road running through the Tongass National Forest, a forest located on Prince of Wales Island in Alaska. See J.A. 292– 93. In conjunction with the issuance of the solicitation, the FHA provided offerors with a copy of a Waste Disposal Sites Investigation Report (“Waste Site Report”), which identified sites that a contractor could use to dispose of waste materials generated during road reconstruction. See J.A. 369–83. This report, which indicated that many of the potential waste disposal sites were located in existing rock quarries, contained estimates of the volume of waste each location could accommodate. J.A. 372. It also stated that “[t]he criteria for establishing waste disposal sites included identifying locations that would minimize negative impacts Case: 19-2125 Document: 30 Page: 3 Filed: 08/26/2020

KIEWIT INFRASTRUCTURE WEST CO. v. UNITED STATES 3

to wetlands, wildlife, fisheries, streams, and karst for- mations.” J.A. 372. 1 The FHA also provided offerors with access to the “Cat- egorical Exclusion,” see J.A. 324–25, 341–59, a document that the agency had prepared in connection with its efforts to comply with the National Environmental Policy Act of 1969 (“NEPA”), 42 U.S.C. §§ 4321–70. 2 The Categorical Exclusion 3 stated that the FHA had determined that the Deweyville project would “not have a significant effect on the human environment,” J.A. 352, and that “[t]he project was designed . . . to minimize the amount of fill placed into wetlands wherever possible,” J.A. 350. 4 It further asserted

1 The Waste Site Report was not created for the Dew- eyville project, but instead for a previous highway project in the Tongass National Forest. See J.A. 369, 372. 2 “NEPA was passed by Congress to protect the en- vironment by requiring that federal agencies carefully weigh environmental considerations and consider potential alternatives to the proposed action before the government launches any major federal action.” Lands Council v. Pow- ell, 395 F.3d 1019, 1026 (9th Cir. 2005); see 42 U.S.C. § 4321. When an agency identifies proposed actions that likely will “not have any significant effect on the environ- ment, the agency may classify those actions as categorical exclusions.” Colo. Wild, Inc. v. U.S. Forest Serv., 435 F.3d 1204, 1209 (10th Cir. 2006). 3 The Categorical Exclusion issued in May 2012 but was amended in both July 2012 and April 2013. See J.A. 341, 347, 353. 4 The solicitation for the Deweyville project stated that the data contained in the Categorical Exclusion was “for the Contractor’s information” and that the FHA would “not be responsible for any interpretation of or conclusion drawn from the data . . . by the Contractor.” J.A. 324; see also J.A. 325. Case: 19-2125 Document: 30 Page: 4 Filed: 08/26/2020

that approximately forty-three acres of wetlands would be “permanently impacted by the proposed action.” J.A. 350. Additionally, the Categorical Exclusion referred to the Waste Site Report and stated that: Material and waste sites are expected to be sourced at existing . . . quarries in the area as identified in the [Waste Site Report]. The sites identified in that report will serve as both material sources and waste sites and are included in this analysis of en- vironmental resource impacts. No further analysis of the environmental impacts of using these sites for material and wasting is necessary at the sites identified in the report unless an expansion of a site is proposed. J.A. 348. The solicitation for the Deweyville project placed re- sponsibility for “obtaining any necessary licenses and per- mits” on the contractor. J.A. 325. Specifically, it stated that the contractor was required to obtain “all permits and clearances needed for completion of the project,” including permits required by the Clean Water Act, 33 U.S.C. § 1344. 5 J.A. 328. The solicitation further provided that the contractor was “responsible for purchasing [wetland]

5 An entity or individual who seeks to obtain a sec- tion 404 permit under the Clean Water Act can provide compensation for the unavoidable impacts that a project will have on wetlands through an in-lieu fee program, which allows for the purchase of compensatory wetland mitigation credits. See 33 C.F.R. §§ 332.1, 332.8; see also id. § 320.4(b)(2)(i) (stating that “[w]etlands . . . serve signif- icant natural biological functions, including food chain pro- duction, general habitat and nesting, spawning, rearing and resting sites for aquatic or land species”). Case: 19-2125 Document: 30 Page: 5 Filed: 08/26/2020

KIEWIT INFRASTRUCTURE WEST CO. v. UNITED STATES 5

mitigation credits, if necessary.” J.A. 337; see also J.A. 327. 6 The solicitation also contained a provision, Revised Standard Specification 105.06 (“RSS 105.06”), which, like the Categorical Exclusion, referred to the Waste Site Re- port and stated that “[n]o further analysis of the environ- mental impacts of using [government-designated waste] sites [would be] needed unless an expansion of a site [were] proposed.” J.A. 330. RSS 105.06 further stated that the government-designated waste sites had “received NEPA clearance.” J.A. 330. Prior to bid submission, Kiewit employees made a two- day visit to the Deweyville project site. J.A. 396, 425. Kie- wit’s total bid included approximately $1,000,000 for wet- land mitigation fees. 7 See J.A. 125, 432, 583–84. The FHA awarded the contract for the Deweyville project to Kiewit on August 2, 2012. J.A. 125. On March 7, 2013, Kiewit wrote a letter to the Dew- eyville project manager, Jane Traffalis, requesting an

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Case Healthcare Solutions, Inc. d/b/a Case HCS of Reston, Virginia
Armed Services Board of Contract Appeals, 2024
Red Bobtail Transportation
Armed Services Board of Contract Appeals, 2024
Derian, Inc.
Armed Services Board of Contract Appeals, 2023
ACC Construction Co., Inc.
Armed Services Board of Contract Appeals, 2022
Barlovento, LLC v. AUI, Inc.
D. New Mexico, 2020

Cite This Page — Counsel Stack

Bluebook (online)
972 F.3d 1322, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kiewit-infrastructure-west-co-v-united-states-cafc-2020.