David Boland, Inc. v. United States

CourtUnited States Court of Federal Claims
DecidedAugust 12, 2022
Docket17-166
StatusPublished

This text of David Boland, Inc. v. United States (David Boland, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
David Boland, Inc. v. United States, (uscfc 2022).

Opinion

In the United States Court of Federal Claims No. 17-166C (Filed: August 12, 2022) FOR PUBLICATION *************************************** DAVID BOLAND, INC., * * Plaintiff, * * v. * * THE UNITED STATES, * * Defendant. * * *************************************** Mark Gerard Jackson, Jackson Holcomb LLP, Seattle, Washington, for Plaintiff. With him on briefs were Stowell Holcomb, Jackson Holcomb LLP, Seattle, Washington, Christopher P. Sobba, James Sobba, LLC, Kansas City, Missouri, and Dennis L. Durkin, Baker & Hostetler LLP, Orlando, Florida. Meen Geu Oh, Senior Trial Counsel, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, D.C., for Defendant, United States. With him on briefs were Jeffrey Bossert Clark, Acting Assistant Attorney General, Robert E. Kirschman, Jr., Director, Patricia M. McCarthy, Assistant Director, as well as Kanale Sadowski, Assistant District Counsel, U.S. Army Corps of Engineers, Honolulu District. OPINION AND ORDER Plaintiff David Boland, Inc. (“Boland”) contracted with the U.S. Army Corps of Engineers (“Corps”) to build infrastructure supporting a planned aviation complex at Wheeler Army Airfield (“Wheeler”) in Oahu, Hawaii. Some of Boland’s work did not comply with the terms of the contract — a fact the parties do not dispute — and the Corps ordered Boland to remove and replace the non-conforming work at Boland’s expense. Boland claims that the Corps’ order was economically wasteful, and so seeks recovery of the costs of replacing its original work. Boland has moved for partial summary judgment as to liability, and the government has moved for summary judgment.1 For the reasons discussed below, both motions are DENIED.

FACTS In 2009, the U.S. Army began planning an additional aviation complex to support a military brigade at Wheeler. Defendant’s Statement of Undisputed Facts (“DSUF”) ¶ 1 (ECF 55-1).2 The Corps awarded Boland a contract for infrastructure development at the site. Ex. 1 at BOL_000836. Among other things, Boland was to install concrete sewer manholes for a wastewater collection system. Appx43 § 3.1.4; see also Ex. 94 (Rasmussen Dep.) at 48:5–49:5. Boland undisputedly breached the contract by installing non-conforming manholes. But the parties dispute the engineering and business consequences of the breach. A. The Contract Three aspects of the contract are most relevant to the case. First, although the contract was between Boland and the Corps, the completed wastewater collection system was to be owned and operated by a private firm — Aqua Engineers, Inc. (“Aqua”). Appx16, “Sewer Notes” n. 14; Supp. Appx108; Supp. Appx113 §§ C.1–C.2. Boland’s work was supposed to be incorporated within a larger, pre-existing sewer system that Aqua already operated under a separate contract with the U.S. Army Garrison Hawaii, Directorate of Public Works (“DPW”). See Supp. Appx108; 10 U.S.C. § 2688. Aqua’s contract provided that upon completion of underground infrastructure work by a contractor (i.e., Boland), Aqua “shall allow” a service connection to its existing system, and that it would own the newly constructed

1 Pl.’s Corrected Mot. for Partial Summ. J. (ECF 71) (“Pl.’s Mot.”); Def.’s Resp. to Pl.’s Mot. for Partial Summ. J. (ECF 63) (“Def.’s Resp.”); Pl.’s Reply to Def.’s Resp. to Pl.’s Mot. for Partial Summ. J. (ECF 67) (“Pl.’s Reply”); Def.’s Mot. for Summ. J. (ECF 55) (“Def.’s Mot.”); Pl.’s Resp. to Def.’s Mot. for Summ. J. (ECF 64) (“Pl.’s Resp.”); Def.’s Reply to Pl.’s Resp. to Def.’s Mot. for Summ. J. (ECF 68) (“Def.’s Reply”). I heard oral argument on March 3, 2022. Tr. of Oral Arg. (“Tr.”) (ECF 74). The parties filed supplemental briefs on an issue raised at argument. Pl.’s Suppl. Br. (ECF 75); Def.’s Suppl. Resp. (ECF 77); Pl.’s Suppl. Reply (ECF 78). 2 Plaintiff’s summary judgment evidence is collected primarily in several exhibits (designated “Ex.”)

to declarations accompanying its motion for partial summary judgment (ECF 50–54) and response to Defendant’s motion (ECF 64). Plaintiff also submitted several exhibits accompanying its motion in limine to exclude Defendant’s expert (ECF 38). Defendant’s evidence is submitted via an appendix (designated “Appx”) attached to its motion for summary judgment (ECF 55; ECF 55-2–55-3). Defendant has also submitted its DSUF and a supplemental appendix (designated “Supp. Appx”) (ECF 63-3).

-2- sewer lines and manage their operation. Supp. Appx114 § C.4.1; Supp. Appx117 § C.24. Second, the contract required that the sewer manholes be reinforced with steel. In more than one provision, the contract incorporated ASTM C478, a manufacturing standard developed by ASTM International. See, e.g., Appx37 § 2.3.1; Appx39 § 2.3.6.1; Appx71 § 2.3.5. The parties agree that ASTM C478 requires steel reinforcement. See Tr. at 17; Def.’s Mot. at 3; see also Appx2–3 (ASTM C478 §§ 4.1.1, 4.1.6).3 The ASTM standard also provides that manhole components failing to conform to any of its requirements (including the requirement for steel reinforcement) are subject to rejection.4 Appx8 (ASTM C478 § 14.8.1); Appx9 (ASTM C478 § 15.7.1). ASTM compliance was also required by Aqua’s Collection System Design and Construction Protocol (“Aqua Protocol”), which the contract incorporated by reference. Appx36 § 1.7; Appx16, “Sewer Notes” n. 14. Aqua’s Protocol mandated that Boland follow “the requirements of the City and County of Honolulu Design standards.” Supp. Appx46. Honolulu’s standards, in turn, required that concrete manholes conform to ASTM standards. Ex. 40 at AE-002832 § 23.2D. Third, the contract required Boland to strictly comply with the contract’s terms. See Def.’s Reply, Add2 (requiring that Boland perform “in strict accordance with the terms of [the] solicitation”). It authorized the Corps to order “immediate corrective action” if Boland did not comply. Appx26 § 3.10; see also Ex. 111 at 15. Relatedly, Aqua’s own contract conditioned its obligation to accept new wastewater service connections on “conformance to all of … the ‘Aqua Protocol,’” see Supp. Appx117 § C.24, meaning that the contract permitted Aqua to reject Boland’s work if Boland did not comply with the Aqua Protocol. B. Boland’s Breach The parties agree that Boland breached the contract by mistakenly installing manholes that were reinforced not with steel, but with synthetic fiber. Pl.’s Mot. at 5–6; Def.’s Mot. at 4. When the breach was discovered, Boland agreed to immediately

3 The citation here is to an ASTM edition contemporaneous with events giving rise to litigation, approved as of Feb. 1, 2009. Appx2. The contract references C478M, the metric equivalent of C478, see Ex. 7 (ASTM C478M - 15a), the record’s version of which post-dates the contract. The parties have not addressed the difference in effective dates, so I assume for purposes of this opinion that it is not material to the motions. 4 Under a section on “Modified or Special Design,” ASTM permits suppliers to “submit[] to the owner,

for approval prior to manufacture, designs other than those prescribed in the specific section for a product” so long as “the product … meet[s] all the tests and performance requirements specified by the owner in accordance with the appropriate sections on manufacture and physical requirements.” Appx3 § 5.2.1 (emphasis added).

-3- replace several fiber-reinforced manholes awaiting installation. See Ex. 61 at GOV- 0047116. But nineteen non-complying manholes had already been installed. Appx159; Appx161. Boland requested a variance from the Corps and suggested various guarantees and fixes, Ex. 22 at GOV-0001251, but was ultimately required to replace the manholes. The Corps was initially amenable to accepting Boland’s variance request. See Ex. 61 at GOV-0047117.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Adickes v. S. H. Kress & Co.
398 U.S. 144 (Supreme Court, 1970)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Richard L. Thoen v. The United States
765 F.2d 1110 (Federal Circuit, 1985)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Prineville Sawmill Company, Inc. v. The United States
859 F.2d 905 (Federal Circuit, 1988)
Granite Construction Company v. The United States
962 F.2d 998 (Federal Circuit, 1992)
Dairyland Power Cooperative v. United States
16 F.3d 1197 (Federal Circuit, 1994)
Coast Federal Bank, Fsb v. United States
323 F.3d 1035 (Federal Circuit, 2003)
Westlands Water District v. United States
109 Fed. Cl. 177 (Federal Claims, 2013)
Eastern S. S. Lines, Inc. v. United States
112 F. Supp. 167 (Court of Claims, 1953)
In Re Kinney Aluminum Co.
78 F. Supp. 565 (S.D. California, 1948)
Jacob & Youngs, Inc. v. Kent
129 N.E. 889 (New York Court of Appeals, 1921)
Blinderman Construction Co. v. United States
42 Cont. Cas. Fed. 77,210 (Federal Claims, 1997)
Fort Myer Construction Corp. v. United States
43 Cont. Cas. Fed. 77,425 (Federal Claims, 1999)
Elastomeric Roofing Associates, Inc. v. United States
26 Cl. Ct. 1106 (Court of Claims, 1992)
Barsebäck Kraft AB v. United States
121 F.3d 1475 (Federal Circuit, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
David Boland, Inc. v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/david-boland-inc-v-united-states-uscfc-2022.