David Boland, Inc. v. United States

United States Court of Federal Claims·Decided October 17, 2022·No. 22-131·Unpublished

Opinion

No. 22-131C (Filed: Monday, October 17, 2022) ************************** 28 U.S.C 1491 (2018); DAVID BOLAND, INC., Contract Disputes Act, 41 U.S.C. §§ 7101-09, Plaintiff, 7103 (2018); v. FAR 52.233-3; Contracts; motion to THE UNITED STATES, dismiss; subject matter Defendant. jurisdiction; failure to state a claim ************************** Denis L. Durkin, Orlando, FL, for plaintiff. Michael S. Vitale and Brian V. Johnson, of counsel.

Jimmy S. McBirney, Trial Attorney, United States Department of Justice, Civil Division, Commercial Litigation Branch, Washington, DC, with whom were Brian M. Boynton, Principal Deputy Assistant Attorney General, Patricia M. McCarthy, Director, and Steven J. Gillingham, Assistant Director, for defendant. Brett R. Howard, Deputy District Counsel and James M. Inman, Trial Attorney, of counsel.

OPINION

BRUGGINK, Judge.

The United States, through the United States Army Corps of Engineers, contracted with plaintiff, David Boland, Inc. (Boland), to construct a new building for a “military and training center” in Dublin, California. Pending is the government’s motion to dismiss four of the complaint’s six counts, either for lack of subject matter jurisdiction or failure to state a claim on which relief can be granted. The motion is fully briefed, and oral argument was held on October 13, 2022. We grant in part and deny in part. BACKGROUND 1

This complaint arises out of a government contractor’s unsuccessful requests for equitable adjustments (REA). The government awarded Boland with Contract No. W912QR-16-C-0013 (the contract) to construct a new building for U.S. Army Reserve personnel on July 6, 2016. The parties encountered obstacles, which prompted Boland’s disputed REAs.

Bid Protest Delay (Counts I and II)

Shortly after the contract was awarded, an unsuccessful bidder filed a protest with the Government Accountability Office (GAO). In compliance with regulatory requirements, the government issued a notice to suspend performance. 2 Several months later, GAO resolved the protest, and the government issued a notice to proceed on November 28, 2016.

Boland believed that the bid-protest performance delay increased its cost of performance. Particularly, Boland claimed that it could not “secure certain previously selected subcontractors and suppliers” and “enter[ed] into contracts with other companies at increased costs.” Compl. Ex. B. To recover for those costs, Boland submitted an uncertified REA (2017 REA) for $262,060 on October 25, 2017. Id.

Not long after, the government informed Boland that its 2017 REA needed to “provide actual quotes from [its] subcontractors and suppliers.” Mot. to Dismiss App. 1. Boland could not, in its own view however, “isolate the additional actual costs incurred” and instead used “published standards” to estimate its increased costs. Compl. ¶ 22. Ultimately, Boland never provided the government with actual cost data, leaving the issue unresolved. 3

1 The background is drawn from the complaint and the attached materials. 2 Under FAR 33.104(c)(1), the contracting officer “shall immediately suspend performance” when the “agency receives notice of a protest from the GAO.” 3 After several years, Boland eventually certified its 2017 REA and requested a final decision, which the government never issued. 2 At an impasse, Boland submitted a second certified REA on November 2, 2020 (2020 REA), seeking an additional $329,296 in unabsorbed home office overhead incurred during the bid-protest delay. Compl. Ex. C. While Boland still “maintain[ed] that there were significant increased costs of construction,” it “resolved itself to the fact” that it cannot “provide actual cost records.” Id. Nevertheless, it believed that the government owed compensation for unabsorbed overhead. On February 9, 2021, the government issued a Contracting Officer’s Final Decision (COFD) denying Boland’s 2020 REA because it was untimely and failed to meet the regulatory requirements to recover unabsorbed overhead. 4

Power Delay (Counts III and IV)

Completion of the contract required a power supply to the construction site. To supply the necessary power, the government was required to contract with Pacific Gas and Electric Company (PG&E). Setbacks ensued, and the provision of power was delayed. While the parties dispute who was responsible for the power delay, they appear to agree on the following facts.

PG&E needed to inspect the construction site. When PG&E inspected the site, it noted several deviations from what the contract required. Boland eventually corrected those variances, and the government then signed the contract with PG&E. Despite site readiness, installation of the power transformer was scheduled to take place in a couple of months. Both parties understood that this timeframe would delay the project’s completion, but the government claimed that nothing could be done to speed up the process. With waiting being the only option, the transformer was installed 8 weeks later.

To recover for the extended project completion time in 2018, Boland submitted a certified REA for $311,411.22 (Power REA), maintaining that the power delay “was within the government’s responsibility.” Compl. Ex.

4 The contracting officer determined that the 2020 REA was untimely under FAR 52.243-4, the FAR provision for “Changes.” While 52.243-4 was inapplicable, a timeliness issue did exist. As we later discuss, REAs for bid- protest delay must be submitted within 30 days of a notice to proceed under FAR 52.233-3. 3 G. In its REA, Boland claimed that late power installation delayed the project’s completion by 82 days. The government denied the REA and instead agreed only to a non-compensable time extension. Unsatisfied with the government’s offer, Boland hired an independent consulting firm, AM Sist Consulting (AMS). AMS concluded that the government owed Boland compensation for 70 additional days. Based on AMS’s report, Boland resubmitted its REA in 2020 and requested an adjusted amount of $241,636. The contracting officer denied Boland’s adjusted Power REA. In her COFD, the contracting officer explained that it was Boland’s protracted site preparation that delayed execution of the PG&E power supply contract.

CIP Wall Repair (Counts V and VI)

Construction of the building required Boland to install “cast in place” (CIP) walls. After Boland installed part of the first wall, it discovered defects and promptly notified the government. To assess the situation, Boland hired an engineer who evaluated the wall’s defects and concluded that they did not “impact the structural adequacy of the wall.” Compl. Ex. J (CIP Wall REA). Despite the report, the government feared “increased liability” and issued a stop-work order. Compl. ¶ 72. During that time, tests on the wall continued, and Boland eventually addressed the faulty installation process successfully with a revised concrete mix. See Compl. Ex. J. For the CIP walls already installed, Boland compiled a supplementary report to demonstrate the wall’s structural integrity and show that it could be adequately repaired. The government agreed and lifted the stop-work order.

The engineering tests increased Boland’s costs. So too, did the stop- work order delay. Hoping to recoup its losses, Boland submitted a certified REA in 2018, and again in 2019, for $200,967 (CIP Wall REA). Negotiations ensued, and a provisional agreement was reached. The agreement fell through, however, over allegedly inaccurate scheduling information.

Free access — add to your briefcase to read the full text and ask questions with AI

David Boland, Inc. v. United States, (uscfc 2022).

David Boland, Inc. v. United States (David Boland, Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Crown Coat Front Co. v. United States
386 U.S. 503 (Supreme Court, 1967)
Tellabs, Inc. v. Makor Issues & Rights, Ltd.
551 U.S. 308 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
M. Maropakis Carpentry, Inc. v. United States
609 F.3d 1323 (Federal Circuit, 2010)
Centex Corp. v. United States
395 F.3d 1283 (Federal Circuit, 2005)
Felix E. Perez v. United States
156 F.3d 1366 (Federal Circuit, 1998)
Am-Pro Protective Agency, Inc. v. United States
281 F.3d 1234 (Federal Circuit, 2002)
Scott Timber Company v. United States
333 F.3d 1358 (Federal Circuit, 2003)
Mohamad v. Palestinian Authority
132 S. Ct. 1702 (Supreme Court, 2012)
Acevedo v. United States
824 F.3d 1365 (Federal Circuit, 2016)
Walsh Construction Co. v. United States
132 Fed. Cl. 282 (Federal Claims, 2017)
Kiewit Infrastructure West Co. v. United States
972 F.3d 1322 (Federal Circuit, 2020)
Creative Management Services v. United States
989 F.3d 955 (Federal Circuit, 2021)