H.L. Smith, Inc. v. John H. Dalton, Secretary of the Navy

49 F.3d 1563
CourtCourt of Appeals for the Federal Circuit
DecidedJune 1, 1995
Docket94-1318
StatusPublished
Cited by42 cases

This text of 49 F.3d 1563 (H.L. Smith, Inc. v. John H. Dalton, Secretary of the Navy) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H.L. Smith, Inc. v. John H. Dalton, Secretary of the Navy, 49 F.3d 1563 (Fed. Cir. 1995).

Opinion

RADER, Circuit Judge.

H.L. Smith, Inc. submitted several requests for equitable adjustments and time *1564 extensions under its Government contract. The contracting officer declined to issue final decisions on Smith’s submissions. Smith appealed the deemed denials to the Armed Services Board of Contract Appeals. The Board dismissed for lack of jurisdiction. H.L. Smith, Inc., 94-2 B.C.A. (CCH) ¶26,-723, 1994 WL 55629 (1994). Because Smith submitted proper claims under the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 601-613 (1988 & Supp. V 1993), the Board has jurisdiction over Smith’s appeals. This court reverses and remands.

BACKGROUND

In April 1991, Naval Facilities Engineering Command, Portsmouth Naval Shipyard awarded Smith Contract No. N62472-90-C-2029 to repair a bridge at Portsmouth Naval Shipyard in Buttery, Maine. Between June 1992 and April 1993, Smith submitted nine letters requesting equitable adjustments and time extensions on behalf of its subcontractor Grover Enterprises, Inc. Each submission included a letter from Grover under a cover letter. Each explained the circumstances warranting the alleged increased performance cost and time. The Board’s decision accurately describes these letters. Smith, 94-2 B.C.A. (CCH) at 132,931-33.

Smith submitted the first two letters to the Navy in June 1992. Smith did not attach invoices, cost breakdowns, or other documentation explaining how it arrived at the sums requested. The contracting officer handling Smith’s submissions replied that he did not consider Smith’s letters to be valid claims under the disputes clause of the contract. See 48 C.F.R. § 52.238-1 (1994). Smith resubmitted its letters for final decision, adding certification language. The contracting officer then twice sought a more detailed factual submission to allow proper evaluation of Smith’s requests. Smith did not respond with any specific cost-related documentation to support the requested amounts and time extensions.

In December 1992, and then in April 1993, Smith forwarded seven additional letters on behalf of Grover to the contracting officer, alleging that the Government caused delays. Smith again did not provide cost information to support the requested dollar amounts. Nor did Smith explain how it computed the requested amounts. In six separate letters, the contracting officer sought supporting financial documentation, but Smith and Grover did not respond. Receiving no invoices, cost breakdowns, or other supporting financial documentation from either Smith or Grover, despite repeated attempts, the contracting officer took no further action. He declined to make final decisions.

Smith appealed the contracting officer’s inaction to the Board, asserting deemed denials under 41 U.S.C. § 605(c)(5) (1988). The Board dismissed Smith’s appeals, without prejudice, for lack of jurisdiction. Smith, 94-2 B.C.A. (CCH) at 132, 933. The Board held that absent information regarding calculation of the asserted amounts, the letters were not proper CDA claims. Id. Smith appeals.

DISCUSSION

This court reviews de novo the Board’s dismissal of Smith’s requests. 41 U.S.C. § 609(b) (1988); Transamerica Ins. Corp. v. United States, 973 F.2d 1572, 1576 (Fed.Cir.1992). Submission of a valid CDA claim is a jurisdictional prerequisite to appeal to the Board. See W.M. Schlosser Co. v. United States, 705 F.2d 1336, 1338-39 (Fed.Cir.1983). The Board concluded that Smith’s letters were not valid CDA claims because Smith did not substantiate the requested dollar amounts. Thus, this court must decide whether a contractor must submit invoices, detailed cost breakdowns, or other cost-related documentation to make a valid CDA claim.

The CDA requires a Government contractor seeking redress to submit a written claim to a contracting officer for a final decision. 41 U.S.C. § 605(a) (1988). But, neither the CDA nor its implementing regulations, the Federal Acquisition Regulations (FAR), requires submission of a detailed cost breakdown or other specific cost-related documentation with the claim. The CDA does not define “claim,” so this court looks for guidance to its implementing regulations. FAR § 33.201 defines a “claim” as

*1565 a written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum certain, the adjustment or interpretation of contract terms, or other relief arising under or relating to the contract.

48 C.F.R. § 33.201 (1994); see also 48 C.F.R. § 52.233-1 (1994) (Government contract disputes clause defining CDA claim). Interpreting this definition, this court has identified three requirements for a valid CDA claim: (1) the contractor must submit the demand in writing to the contracting officer, (2) the contractor must submit the demand as a matter of right, and (3) the demand must include a sum certain. Essex Electro Eng’rs, Inc. v. United States, 960 F.2d 1576, 1580 (Fed.Cir.), cert. denied, — U.S.-, 113 S.Ct. 408, 121 L.Ed.2d 333 (1992). The regulation itself, and this court’s interpretation of it, do not mention supporting financial documentation.

A contractor must submit in writing “a clear and unequivocal statement that gives the contracting officer adequate notice of the basis and amount of the claim.” Contract Cleaning Maintenance, Inc. v. United States, 811 F.2d 586, 592 (Fed.Cir.1987). But the contractor need not include a detailed breakdown of costs. The contractor may supply adequate notice of the basis and amount of the claim without accounting for each cost component.

Transamerica is on point. In that ease, the contractor certified and submitted to the contracting officer its subcontractor’s claim for an equitable adjustment. Transamerica, 973 F.2d at 1574-75. The claim stated a reason for the increased cost of performance — a defect in the roofing specifications — and included a request for an extension of time to accomplish the expanded scope of the work. Id. at 1574.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tanik Construction Company, Inc.
Armed Services Board of Contract Appeals, 2026
Case Healthcare Solutions, Inc. d/b/a Case HCS of Reston, Virginia
Armed Services Board of Contract Appeals, 2024
United Aeronautical Corp. v. Usaf
80 F.4th 1017 (Ninth Circuit, 2023)
BB Government Services Srl
Armed Services Board of Contract Appeals, 2023
BCC-UIProjects-ZAAZTC Team JV
Armed Services Board of Contract Appeals, 2022
Diaz v. United States
Federal Claims, 2021
M. Nicolas Enterprises, Llc.
Federal Claims, 2021
Penna Group, LLC
Armed Services Board of Contract Appeals, 2021
JAAAT Technical Services, LLC
Armed Services Board of Contract Appeals, 2021
BAE Systems Ordance Systems, Inc.
Armed Services Board of Contract Appeals, 2021
Globe Trailer Manufacturing, Inc.
Armed Services Board of Contract Appeals, 2021
Kamaludin Slyman CSC
Armed Services Board of Contract Appeals, 2020
CiyaSoft Corporation
Armed Services Board of Contract Appeals, 2019

Cite This Page — Counsel Stack

Bluebook (online)
49 F.3d 1563, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hl-smith-inc-v-john-h-dalton-secretary-of-the-navy-cafc-1995.