BAE Systems Ordance Systems, Inc.

CourtArmed Services Board of Contract Appeals
DecidedFebruary 10, 2021
DocketASBCA No. 62416
StatusPublished

This text of BAE Systems Ordance Systems, Inc. (BAE Systems Ordance Systems, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BAE Systems Ordance Systems, Inc., (asbca 2021).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) BAE Systems Ordnance Systems, Inc. ) ASBCA No. 62416 ) Under Contract Nos. W52P1J-11-C-0012 ) W52P1J-11-D-0013 )

APPEARANCE FOR THE APPELLANT: Michael A. Richard, Esq. Obermayer Rebmann Maxwell & Hippel LLP Philadelphia, PA

APPEARANCES FOR THE GOVERNMENT: Scott N. Flesch, Esq. Army Chief Trial Attorney LTC Gregory T. O’Malley, JA LTC Jess R. Rankin, JA Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE PROUTY

The issue before us in the government’s pending motion to dismiss is whether the Federal Circuit’s recent decision in Hejran Hejrat Co. Ltd v. United States Army Corps of Engineers, 930 F.3d 1354 (Fed. Cir. 2019), so alters the law regarding requests for equitable adjustment (REAs) that a contractor submitting documents plainly intended to be REAs, but not claims pursuant to the Contract Disputes Act (CDA), and scrupulously avoiding requesting final decisions from the contracting officer (CO) must, nevertheless, be considered to have submitted claims pursuant to the CDA. In the case before us, the conversion of the REAs to claims without the contractor’s intent or knowledge would require dismissal of the appeal because the time between the denial of the REAs and the submission of this appeal is beyond the CDA’s statute of limitations. For the reasons explained below, Hejran Hejrat does not require such a result and the Army’s motion to dismiss, advancing that argument, is denied.1

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

BAE Systems Ordinance Systems, Inc. (BAE) had two related contracts with the United States Army (Army). The first contract in the caption above (the 12 contract) is

1 The government has also requested a stay of this case. That request is mooted by this decision. the one relevant to the pending motion to dismiss, and it was to perform Facilities Operation and Maintenance of the Radford Army Ammunition Plant (RFAAP), collocated in Radford and Dublin, Virginia (see R4, tab 1). The second contract in the caption (the 13 contract) was to produce propellant at the RFAAP for use in artillery (see R4, tab 3).

An issue arose during contract performance regarding who would be responsible for payment of certain costs relating to environmental conditions at the site and fines that BAE was incurring from state regulators as a result (see R4, tabs 122, 186, 192). As a consequence, BAE submitted three letters to the CO: The first letter was submitted on December 7, 2016 (REA 1 2) (R4, tab 122). The second was submitted on August 3, 2017 (REA 2) (R4, tab 186). The third was submitted on September 6, 2017 (REA 3) (R4, tab 192).

The “subject” line of each of the three letters from BAE labelled it as an REA (R4, tab 122 at 1338, tab 186 at 1612, tab 192 at 1680). Consistent with that label, the introductory paragraph of each letter begins with the words, “In accordance with FAR 52.243-1, Changes – Fixed Price (Alternate I), and DFARS 252.243-7002, Requests for Equitable Adjustment, BAE Systems Ordnance Systems Inc. (BAE Systems) herein submits our Request for Equitable Adjustment (REA) for . . .” 3 (R4, tab 122 at 1339, tab 186 at 1612, tab 192 at 1680). BAE did not request a CO’s final decision pursuant to the CDA in any of the three letters (R4, tabs 122, 186, 192).

The penultimate paragraph of each letter consisted of the following words:

I certify that the request is made in good faith, and that the supporting data are accurate and complete to the best of my knowledge and belief.

(R4, tab 122 at 1343, tab 186 at 1615, tab 192 at 1683) This is precisely the language contained in DFARS 252.243-7002, regarding REAs. The next paragraph was simply a sentence referring the CO to the person signing the letter if she had any questions. They were then signed by Shelley R. Czapkewicz-Klingborg, BAE Senior Manager, Contracts. (R4, tab 122 at 1343, tab 186 at 1615, tab 192 at 1683) Nowhere in the

2 We refer to these letters here as REAs because that is what they were labelled by BAE and, as will be seen later in this opinion that is what we find them to be. 3 The subject lines of the letters all referred to the REAs as being brought pursuant to the 12 contract (R4, tab 122 at 1338, tab 186 at 1612, tab 192 at 1680). The 12 contract incorporated by reference both Federal Acquisition Regulation (FAR) 52.243-1, Changes – Fixed Price (Alternate I), and the Department of Defense Supplement to the Federal Acquisition Regulation (DFARS) 252.243-7002, Requests for Equitable Adjustment (R4, tab 1 at 22).

2 letters does BAE state that the adjustment reflects the amount for which the contractor believes the government is liable, nor do they state that the certifier is authorized to bring the claim on behalf of the contractor (id.), which is the language required for claims certification by the CDA. 41 U.S.C. § 7103(b)(1).

BAE’s opposition to the government’s motion included the declaration of Roosevelt Burden. Mr. Burden testified that he was the Senior Manager of Contracts for BAE who was tasked with converting REA 1, REA 2, and REA 3 into claims within the meaning of the CDA (Burden decl. ¶ 6). Mr. Burden asserts that BAE did not intend for REA 1, REA 2 or REA 3 to be submitted or treated as a claim pursuant to the CDA (Burden decl. ¶¶ 7, 9). This was because BAE initially sought to negotiate the resolution of the REAs rather than pursue a CDA claim (Burden decl. ¶ 8, 10). Mr. Burden explained that in preparation of REA 1, REA 2 and REA 3, BAE purposefully avoided making a request to the CO for a final decision as defined in the CDA, 41 U.S.C. § 7103(d-f) (Burden decl. ¶¶ 7, 9-10).

Thus, on the facts before us, we conclude that each of the three letters was intended by BAE to be an REA as opposed to a CDA claim and that each letter unambiguously communicated as much to the government.

The government has alleged no communications from BAE which expressed a desire to convert these apparent REAs into CDA claims, nor, critically, has it identified any request from BAE for a final decision on the REAs. On the record before us, we find that there was no such request by BAE.

The CO responded to the REAs by letter on November 13, 2018. In the opening paragraph, she described the nature and purpose of the letter:

The purpose of this letter is to notify BAE of my position on contractor entitlement relative to . . . [the] REA submittals. A technical and legal review of the initial REAs submitted were conducted, and were also considered in reaching my position. Upon thorough review and analysis of the information provided, I do not find merit or entitlement to any of the cost elements of the three REAs presented. However, the Procuring Contracting Officer (PCO) is willing to entertain reimbursement of a portion of the penalties paid . . . .

(R4, tab 197 at 1716) To be fair to the government, she did state that a contractor was required to prove its “claims” by a preponderance of evidence and that BAE had not done so (R4, tab 197 at 1719); moreover, she also referred to the REAs as a “claim” once when disavowing any admission of liability stemming from any settlement

3 discussions (R4, tab 197 at 1721), but did not otherwise suggest that she was issuing a final decision upon a claim or that the matter was being treated any differently than an REA. The letter closed by requesting further information from BAE by November 20, 2018 (a week later) (id.).

BAE responded to the CO’s letter on November 19, 2018.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
BAE Systems Ordance Systems, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/bae-systems-ordance-systems-inc-asbca-2021.