Reliance Insurance Company and L.G. Lefler, Inc. v. The United States

931 F.2d 863, 37 Cont. Cas. Fed. 76,083, 1991 U.S. App. LEXIS 7079, 1991 WL 61771
CourtCourt of Appeals for the Federal Circuit
DecidedApril 24, 1991
Docket90-5126
StatusPublished
Cited by36 cases

This text of 931 F.2d 863 (Reliance Insurance Company and L.G. Lefler, Inc. v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reliance Insurance Company and L.G. Lefler, Inc. v. The United States, 931 F.2d 863, 37 Cont. Cas. Fed. 76,083, 1991 U.S. App. LEXIS 7079, 1991 WL 61771 (Fed. Cir. 1991).

Opinion

RADER, Circuit Judge.

Reliance Insurance Company (Reliance) sought equitable adjustment of construction contract No. V101C-1089 with the Veteran’s Administration (VA). The United States Claims Court dismissed four of Reliance’s claims for additional delay overhead. Reliance Ins. Co. v. United States, 20 Cl.Ct. 715 (1990). Reliance appealed. This court affirms.

BACKGROUND

In September 1982, L.G. Lefler, Inc. (Le-fler) contracted with the VA for construction of a clinical addition to a hospital in Tucson, Arizona. The construction was to take 950 days and was worth $11,331,-500.00. Reliance was Lefler’s performance and payment bond surety. If Lefler defaulted, Reliance was responsible to complete the project.

During the contract, the VA issued more than 200 change orders. These changes extended the project by 498 days. Defective contract specifications caused the changes and delays. Attempting to clarify the specifications, Lefler submitted approximately 150 requests for information to the VA during the project.

In late 1984, Lefler defaulted and Reliance assumed responsibility for the contract’s completion. Reliance subsequently submitted six equitable adjustment claims, totaling $1.3 million. Four of these claims sought payment for extended home and field office overhead beyond the delay overhead payments awarded to Reliance under contract clause G-10. The G-10 clause limited overhead recoveries to a percentage of the value of contract changes plus an allowance for profit. The other two claims are not limited to overhead costs. The VA contracting officer denied each claim.

Reliance brought a direct access suit in the Claims Court under the Contract Disputes Act of 1978, 41 U.S.C. § 609(a)(1). The Government moved for partial summary judgment on the four delay overhead claims. The Claims Court granted the Government’s motion, dismissed the four claims, and suspended action on the other two claims pending this appeal. This court has exclusive jurisdiction over Reliance’s appeal under 28 U.S.C. § 1295(a)(3) (1988).

DISCUSSION

In the absence of disputes over material facts, a court may grant the summary judgment motion of a party otherwise enti- *865 tied to judgment as a matter of law. Fed.R.Civ.P. 56(c); Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 250, 106 S.Ct. 2505, 2511, 91 L.Ed.2d 202 (1986). Reliance appeals from a grant of partial summary judgment entered under United States Claims Court Rule 54(b). Therefore, this court views the evidence and draws inferences in Reliance’s favor. See D.L. Auld Co. v. Chroma Graphics Corp., 714 F.2d 1144, 1146 (Fed.Cir.1983).

This appeal requires this court to examine the Claims Court’s application of the G-10 clause to Reliance’s delay overhead claims. Contract interpretation is a question of law which this court reviews under a de novo standard. P.J. Maffei Bldg. Wrecking Corp. v. United States, 732 F.2d 913, 916 (Fed.Cir.1984).

Reliance’s contract contains a clause limiting overhead payments in the event of change orders. The G-10 clause states:

A. Clause 3, Changes and Clause 4, Differing Site Conditions ... are supplemented as follows:
* * * * * *
4. Allowances not to exceed 10 percent each for overhead and profit for the party performing the work will be based upon the value of labor, material and use of construction equipment required to accomplish the change. As the value of the change increases, a declining scale will be used in negotiating the percentage of overhead and profit. Allowable percentages on changes will not exceed the following: 10% overhead and 10% profit on first $20,000; llk% overhead and llk% profit on next $30,000; 5% overhead and 5% profit on balance over $50,000____

See also, 48 C.F.R. Ch. 8, § 852.236-88(b)(d) (1989). The G-10 clause sets a ceiling on the amount of overhead costs recovery under the standard changes clause. 48 C.F.R. Ch. 1, § 52.243-4 (1989).

The G-10 clause does not conflict with the standard changes clause. Nor does the G-10 clause effectively eliminate the changes clause. By its terms, G-10 supplements and limits the standard changes clause. The contract itself states that G-10 supplements the changes clause. The addition of G-10 places a ceiling on delay overhead recoveries.

Further, in reading the contract as a whole, this court interprets provisions to avoid conflicts with other provisions in the same document. Julius Goldman’s Egg City v. United States, 697 F.2d 1051, 1057-58 (Fed.Cir.1983); United States v. Johnson Controls, Inc., 713 F.2d 1541, 1555 (Fed.Cir.1983). Accordingly, the proper interpretation of Reliance’s contract is that the changes clause does not cover delay overhead beyond the percentage limits in the G-10 clause.

The G-10 clause operates regardless of the size and scope of contract changes. The large number and dollar value of changes in Reliance’s contract does not alter the operation of the G-10 limit. Rather, the language of G-10 adjusts the percentage ceilings on delay overhead to account for larger changes. By setting a 5% overhead limit on the balance of changes over $50,000.00, the contract explicitly provided for larger changes. Hence, by its terms, the G-10 clause limits recovery on delay overhead claims of various sizes and costs.

This court has consistently interpreted the G-10 clause. This court interpreted this same clause with the same result in 1986. Santa Fe Eng’rs, Inc. v. United States, 801 F.2d 379 (Fed.Cir.1986). The Santa Fe contract also involved construction on a VA Hospital. The VA issued a change order for different ceiling materials. The parties amicably adjusted the contract price for direct costs but disputed the delay overhead costs. This court determined that “the literal words of G-10 blanket delay overhead as well as overhead on the direct costs incurred by the contractor.” Santa Fe, 801 F.2d at 381.

Like Reliance, the contractor in Santa Fe asserted that G-10 conflicts with the standard changes clause. This court dismissed that contention. Citing Jack Picoult Constr. Co. v. United States, 207 Ct.Cl. 1052, 529 F.2d 532 (1975), this court noted

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Walsh Construction Co. v. United States
132 Fed. Cl. 282 (Federal Claims, 2017)
E & E Enterprises Global, Inc. v. United States
120 Fed. Cl. 165 (Federal Claims, 2015)
Paradigm Learning, Inc. v. United States
93 Fed. Cl. 465 (Federal Claims, 2010)
Boeing Co. v. United States
75 Fed. Cl. 34 (Federal Claims, 2007)
Renda Marine, Inc. v. United States
71 Fed. Cl. 378 (Federal Claims, 2006)
CEMS, Inc. v. United States
59 Fed. Cl. 168 (Federal Claims, 2003)
United States v. Intrados/International Management Group
277 F. Supp. 2d 55 (District of Columbia, 2003)
Scott Timber Company v. United States
333 F.3d 1358 (Federal Circuit, 2003)
Kiewit Construction Co. v. United States
56 Fed. Cl. 414 (Federal Claims, 2003)
M.J. Paquet, Inc. v. New Jersey Department of Transportation
794 A.2d 141 (Supreme Court of New Jersey, 2002)
Brown v. United States
29 F. App'x 588 (Federal Circuit, 2002)
Bristol-Myers Squibb Co. v. United States
48 Fed. Cl. 350 (Federal Claims, 2000)
MJ Paquet, Inc. v. Dept. of Transp.
761 A.2d 122 (New Jersey Superior Court App Division, 2000)
Linda Newman Construction Co. v. United States
48 Fed. Cl. 231 (Federal Claims, 2000)
Melrose Associates, L.P. v. United States
43 Fed. Cl. 124 (Federal Claims, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
931 F.2d 863, 37 Cont. Cas. Fed. 76,083, 1991 U.S. App. LEXIS 7079, 1991 WL 61771, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reliance-insurance-company-and-lg-lefler-inc-v-the-united-states-cafc-1991.