Morrison-Knudsen Company, Inc. v. The United States

397 F.2d 826, 184 Ct. Cl. 661, 1968 U.S. Ct. Cl. LEXIS 129
CourtUnited States Court of Claims
DecidedJune 14, 1968
Docket239-61
StatusPublished
Cited by56 cases

This text of 397 F.2d 826 (Morrison-Knudsen Company, Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morrison-Knudsen Company, Inc. v. The United States, 397 F.2d 826, 184 Ct. Cl. 661, 1968 U.S. Ct. Cl. LEXIS 129 (cc 1968).

Opinion

OPINION

PER CURIAM:

This case was referred to then Trial Commissioner Herbert N. Maletz (now a Judge of the United States Customs Court) with directions to make recommendation for conclusions of law under the order of reference and Rule 57(a). The commissioner has done so in an opinion and report filed on June 20, 1967, wherein facts necessary to the opinion and recommended conclusions are stated. Defendant filed exceptions to the commissioner’s recommended conclusions, except as to those conclusions relating to *829 the finished tolerances of the subgrade of the road, * and the case has been submitted for review by the court on the briefs of the parties and oral argument of counsel.

With respect to the first claim (based on the relocation of the borrow pits), the court stresses, as did the commissioner, the inclusion in this contract of the mandatory standard Changes article with its broad and general reach. We have repeatedly indicated that, where that (or a comparable) clause is contained in a contract, the court will construe the agreement, to the extent it is fairly possible to do so, so as not to eliminate the standard article or deprive it of most of its ordinary coverage. United Contractors v. United States, 368 F.2d 585, 598, 177 Ct.Cl. 151, 165-166 (1966); Thompson Ramo Wooldridge, Inc. v. United States, 361 F.2d 222, 228, 175 Ct. Cl. 527, 536 (1966); Farnsworth & Chambers Co. v. United States, 346 F.2d 577, 580-581, 171 Ct.Cl. 30, 35 (1965); Jack Stone Co. v. United States, 344 F.2d 370, 374-375, 170 Ct.Cl. 281, 288 (1965); Kaiser Industries Corp. v. United States, 340 F.2d 322, 329-330, 169 Ct.Cl. 310, 323-324 (1965); Fehlhaber Corp. v. United States, 151 F.Supp. 817, 825, 138 Ct.Cl. 571, 584 (1957), cert, denied, 355 U.S. 877, 78 S.Ct. 141, 2 L.Ed.2d 108; Loftis v. United States, 76 F.Supp. 816, 825-826, 110 Ct.Cl. 551, 627-629 (1948); Pfotzer v. United States, 77 F.Supp. 390, 399, 400, 111 Ct.Cl. 184, 226, cert, denied, 335 U.S. 885, 69 S.Ct. 237, 93 L.Ed. 424 (1948). The defendant says that here it attempted to cast the whole risk of borrow pit location on the contractor, but if that was its purpose it should have sought permission to delete the mandatory Changes article or to substitute a more limited form of the clause. So long as the Changes article in its normal form is included in a contract, the court is justified in reading the specifications, if reasonably possible, to harmonize and not conflict with that standard clause. That is what the corn-missioner has done in this case, and we think correctly so.

Since the court is in agreement with the opinion and recommended conclusions of the trial commissioner, with minor modifications, it hereby adopts the same, as modified and as supplemented by the preceding paragraph, as the basis for its judgment in this, ease, as hereinafter set forth.

As to the claim based on relocation of borrow pits (treated as Claim I in the opinion), plaintiff is entitled to an equitable adjustment under the Changes clause (on its own behalf and on behalf of its subcontractor) for all the increased costs resulting from the changes in question, which amount (to prevent double recovery) is to be reduced by $16,097 for the compensation plaintiff has already received for the overrun in overhaul. Judgment to this extent is entered for plaintiff with the amount of recovery to be determined in the first instance (if the parties do not agree) by the Board of Contract Appeals of the Department of the Interior.

As to the claim related (in part) to deletion 1 of selected borrow surface course (treated as Claim II, Item 1 in the opinion), plaintiff is entitled to an equitable adjustment under the Changes clause (on its own behalf and on behalf of its subcontractor Edwards) for the additional costs resulting from the directions of the commission which required use of oversized materials in constructing the top 12 inches of the subgrade. Judgment to this extent is entered for plaintiff and in the absence of agreement by the parties, the amount of recovery will be determined in the first instance by the Board of Contract Appeals of the Department of the Interior.

As to the aspect of plaintiff’s claim which is treated as Claim II, Item 2 in the opinion, it is concluded that plaintiff is not entitled to recover and the petition relating to recovery therefor is dismissed.

*830 As to the claim for increased costs resulting from shut-down for the winter of 1954-55 (treated as Claim III in the opinion), plaintiff is entitled to recover for the salary paid to the project superintendent during the shut-down period (plus payroll taxes and insurance thereon) , the labor and equipment costs it incurred in demobilizing its equipment spread at the end of the 1954 season and remobilizing it at the start of the 1955 construction season, and the ownership expense of maintaining in storage during the shut-down period the specific items of equipment required to complete the project. Judgment to this extent is entered for plaintiff with the amount of recovery to be determined pursuant to Rule 47(c).

As to those two portions or aspects of plaintiff’s claims treated as Claim I and Claim II, Item 1 in the opinion, proceedings are suspended for a period of 90 days from the date hereof in order that the case may be returned to the Board of Contract Appeals for the Department of the Interior for determination in the first instance of the amount of recovery (if the parties do not agree thereon). Plaintiff is to comply with appropriate provisions of the General Order of April 1, 1968, implementing Rule 100 in advising the court of the status of such proceedings.

Commissioner Maletz’ opinion, with minor modifications by the court, is as follows:

OPINION OF COMMISSIONER

MALETZ, Commissioner:

This is a suit on a contract between plaintiff and the Alaska Road Commission of the Department of the Interior (hereafter referred to as the commission) for the grading, drainage and related construction work required to improve a 45-mile segment of an existing roadway which extended from Valdez to Fairbanks in the then Territory of Alaska. The 45-mile segment, otherwise identified as section G of the Richardson Highway, extended from milepost 35.9 to milepost 82.1 and was located about 250 miles from Anchorage. The consideration for performance of the work was $2,083,853, based upon unit prices for estimated quantities of the various types of required construction work.

The contract was signed in April 1953 and was completed in the spring of 1955 within the contractual time limit as extended. It called for the construction of highway improvements from excavated and borrow material 1

Related

RCR Building Corporation v. State of Tennessee
Court of Appeals of Tennessee, 2015
Information Systems & Networks, Corp. v. United States
81 Fed. Cl. 740 (Federal Claims, 2008)
URS Group, Inc. v. Tetra Tech FW, Inc.
181 P.3d 380 (Colorado Court of Appeals, 2008)
CEMS, Inc. v. United States
59 Fed. Cl. 168 (Federal Claims, 2003)
J.G.B. Enterprises, Inc. v. United States
57 Fed. Cl. 415 (Federal Claims, 2003)
Ahmad Vakili v. Randy Hawkersmith
Court of Appeals of Tennessee, 2001
Asphalt Roads & Materials Co. v. Commonwealth
512 S.E.2d 804 (Supreme Court of Virginia, 1999)
Hughes Communications Galaxy, Inc. v. United States
42 Cont. Cas. Fed. 77,229 (Federal Claims, 1997)
ThermoCor, Inc. v. United States
40 Cont. Cas. Fed. 76,955 (Federal Claims, 1996)
Burnett Construction Co. v. United States
38 Cont. Cas. Fed. 76,327 (Court of Claims, 1992)
GILBERT PACIFIC v. Dept. of Transp.
822 P.2d 729 (Court of Appeals of Oregon, 1991)
Reliance Insurance v. United States
36 Cont. Cas. Fed. 75,892 (Court of Claims, 1990)
Santa Fe Engineers, Inc. v. The United States
801 F.2d 379 (Federal Circuit, 1986)
Moore Construction Co. v. Clarksville Department of Electricity
707 S.W.2d 1 (Court of Appeals of Tennessee, 1986)
Folk Construction Co. v. United States
31 Cont. Cas. Fed. 71,247 (Court of Claims, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
397 F.2d 826, 184 Ct. Cl. 661, 1968 U.S. Ct. Cl. LEXIS 129, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morrison-knudsen-company-inc-v-the-united-states-cc-1968.