RCR Building Corporation v. State of Tennessee

CourtCourt of Appeals of Tennessee
DecidedAugust 24, 2015
DocketM2014-01555-COA-R3-CV
StatusPublished

This text of RCR Building Corporation v. State of Tennessee (RCR Building Corporation v. State of Tennessee) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
RCR Building Corporation v. State of Tennessee, (Tenn. Ct. App. 2015).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE May 21, 2015 Session

RCR BUILDING CORPORATION v. STATE OF TENNESSEE

Appeal from the Tennessee Claims Commission No. K20130627 Robert N. Hibbett, Commissioner, TN Claims Commission

________________________________

No. M2014-01555-COA-R3-CV – Filed August 24, 2015 _________________________________

This appeal concerns the construction of a welcome center along I-65 North in Ardmore, Tennessee. The State entered into an agreement with a contractor to construct the welcome center and the adjacent roadways and parking lots. As construction progressed, the contractor submitted requests for several changes to the scope of the project, which were denied; the State also denied several pay requests for work the contractor or its subcontractors had already completed. The contractor filed suit against the State alleging nine separate claims for damages. The Claims Commission ruled in favor of the contractor on all claims. The State appeals four of the claims, asserting that the Commission erred in awarding damages. Concluding that the evidence does not preponderate against the Commission’s findings of fact, we affirm the Commissioner in all respects.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Tennessee Claims Commission Affirmed

ANDY D. BENNETT, J., delivered the opinion of the court, in which FRANK G. CLEMENT, P.J., M.S., and W. NEAL MCBRAYER, J., joined.

Herbert H. Slatery, III, Attorney General and Reporter; William E. Young, Solicitor General; and Melissa Brodhag, Senior Counsel; for the appellant, State of Tennessee.

Gregory L. Cashion and Craig N. Mangum, Nashville, Tennessee, for the appellee, RCR Building Corporation. OPINION

FACTS AND PROCEDURAL HISTORY

On February 11, 2010, RCR Building Corporation (“RCR”) entered into a contract with the State of Tennessee Department of Transportation (the “State” or “TDOT”) to demolish and rebuild a welcome center along I-65 North in Ardmore, Tennessee (the “Project”). The Project was financed through the American Recovery and Reinvestment Act and was administered by the Tennessee Department of Finance and Administration, for the ultimate use of the Tennessee Department of Tourism. The State engaged a team of architects and civil engineers from the private sector firms of Kline Swinney & Associates and Vaughn & Melton (collectively the “Design Team”). The Design Team also administered the contract for the Project. Pursuant to Article 7.1 of the contract, RCR or the State could request changes to the contract by: 1) a written change order; 2) a written change directive; or 3) a written order for minor changes.

Thomas Scott, a TDOT inspector, served as the State’s on-site representative and Erosion Prevention Inspector. Kevin True was designated as RCR’s superintendent for the Project. As construction of the Project progressed, RCR submitted requests for several changes to the scope of the Project, which were denied. The State also denied several of RCR’s pay requests for work RCR or its subcontractors had already completed.

On November 8, 2012, RCR filed a complaint with the Tennessee Claims Commission (the “Commission”) alleging that “problems with the plans and specifications caused RCR to perform additional work for which RCR has not been compensated,” and that the State “directed RCR to perform additional work on the Project for which RCR was not compensated.” RCR went on to allege seventeen separate claims for damages against the State. RCR argued that the State was contractually required to pay for the extra work performed by RCR, and thus, the State had breached the contract by failing to pay. On May 10, 2013, the State filed an answer and four counterclaims for RCR’s alleged failure to complete the construction project. On January 3, 2014, the State filed a motion for partial summary judgment, which the Commission denied. RCR voluntarily dismissed eight of its seventeen claims prior to trial.

The Commission held a trial on March 10-13, 2014, at which nine witnesses testified, including Mr. Scott and Mr. True.1 The Commission rendered its decision on July 17, 2014,

1 Each issue raised by the State is heavily fact-intensive and requires a careful examination of the construction plans and the circumstances attendant to the construction of the Project. We will provide specific details of the contract, construction, and testimony, as they relate to each issue on appeal. 2 ruling in favor of RCR on all nine claims, and awarded RCR a total judgment of $96,754.99. The trial court made findings regarding the “contracting parties and their authority under the contract” and the “credibility of witnesses.” The Commission found “the Design Team and State clothed Mr. Scott with the authority to direct activities at the Project work site. The Tribunal finds that Mr. Scott had the apparent authority to bind the State with his words and deeds and had the same authority as the State officers and Design Team under the contract.” The Commission further found that the testimony of Mr. Scott was “vague, curt, contradictory and self-serving.” The Commission stated, “when Mr. Scott’s testimony is contradictory to any other witness[es’] testimony, especially the testimony of Kevin True, then Mr. Scott’s testimony shall not be accredited.” The Commission held, in pertinent part:

[T]he State and Design Team breached the contract on every occasion when it had the Claimant change the scope of the work without a Change Order and then ratified the change after the fact. The State cannot hide behind the Contract when it did not follow the terms of the Contract. To allow the State to avoid payment for the work it directed at the expense of the Claimant would defeat substantive justice.

The trial court dismissed the State’s counterclaims, finding the counterclaims were “retaliatory in nature.”

The State appeals the trial court’s ruling on four of the claims. In particular, this appeal concerns: 1) whether RCR should be compensated for the alleged post-contract change to the construction of concrete expansion joints; 2) whether RCR should be compensated for the alleged post-contract change of the truck parking area from asphalt to concrete; 3) whether RCR should be compensated for the installation of additional stone-fill material pursuant to change order number four; and 4) whether RCR should be compensated for the widening of a project roadway that was allegedly authorized by Mr. Scott. The total amount awarded on the claims being appealed is $79,388.85.

STANDARD OF REVIEW

Appeals from decisions of the Tennessee Claims Commission are governed by the Tennessee Rules of Appellate Procedure. Tenn. Code Ann. § 9-8-403(a)(1); Bowman v. State, 206 S.W.3d 467, 472 (Tenn. Ct. App. 2006). The Commission hears cases without a jury; therefore, this Court must review the Commission’s findings of fact and legal conclusions under the standard of review found in Tenn. R. App. P. 13(d). Bowman, 206 S.W.3d at 472. We review the Commission’s factual findings de novo with a presumption of correctness unless the evidence preponderates otherwise. Id. For the evidence to preponderate against a trial court’s finding of fact, it must support another finding of fact 3 with “greater convincing effect.” Walker v. Sidney Gilreath & Assocs., 40 S.W.3d 66, 71 (Tenn. Ct. App. 2000). This Court reviews the Commission’s legal conclusions de novo with no presumption of correctness. Turner v. State, 184 S.W.3d 701, 704 (Tenn.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Copco Steel & Engineering Co. v. The United States
341 F.2d 590 (Court of Claims, 1965)
Morrison-Knudsen Company, Inc. v. The United States
397 F.2d 826 (Court of Claims, 1968)
Blount Brothers Corporation v. The United States
424 F.2d 1074 (Court of Claims, 1970)
Turner v. State
184 S.W.3d 701 (Court of Appeals of Tennessee, 2005)
Walker v. Sidney Gilreath & Associates
40 S.W.3d 66 (Court of Appeals of Tennessee, 2000)
Bowman v. State
206 S.W.3d 467 (Court of Appeals of Tennessee, 2006)
Allstate Insurance Co. v. Watson
195 S.W.3d 609 (Tennessee Supreme Court, 2006)
Willey v. Terry & Wright of Kentucky, Inc.
421 S.W.2d 362 (Court of Appeals of Kentucky (pre-1976), 1967)
W & O Construction Co. v. City of Smithville
557 S.W.2d 920 (Tennessee Supreme Court, 1977)
Planters Gin Co. v. Federal Compress & Warehouse Co.
78 S.W.3d 885 (Tennessee Supreme Court, 2002)
Wells v. Tennessee Board of Regents
9 S.W.3d 779 (Tennessee Supreme Court, 1999)
Moore Construction Co. v. Clarksville Department of Electricity
707 S.W.2d 1 (Court of Appeals of Tennessee, 1986)
Guiliano v. Cleo, Inc.
995 S.W.2d 88 (Tennessee Supreme Court, 1999)
Bannon v. Jackson
121 Tenn. 381 (Tennessee Supreme Court, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
RCR Building Corporation v. State of Tennessee, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rcr-building-corporation-v-state-of-tennessee-tennctapp-2015.