Bannon v. Jackson

121 Tenn. 381
CourtTennessee Supreme Court
DecidedDecember 15, 1908
StatusPublished
Cited by20 cases

This text of 121 Tenn. 381 (Bannon v. Jackson) is published on Counsel Stack Legal Research, covering Tennessee Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bannon v. Jackson, 121 Tenn. 381 (Tenn. 1908).

Opinion

Mr. Chief Justice Beard

delivered the opinion of the Court.

The late W. H. Jackson and Howell E. Jackson, the owners of a life estate in a lot in Nashville, contracted Avith various parties for the erection on it of a large business house. The complainants, P. & M. J. Bannon, under the name and style of the Louisville Fireproof Construction Company, on the 22d of September, 1893, entered into articles of agreement with the owner to furnish and place in the building the fireproofing required.

By the first article of this agreement, the complainants undertook that they would “welt and satisfactorily erect, finish, and deliver in a true and workmanlike manner the fireproofing materials required in the erection and completion of the new stores, offices, and apartments, . . . agreeably to the plans, detailed drawings, and specifications, prepared for the said work, . . . to the satisfaction and under the direction and personal supervision of the architects. . . .”

The second article stipulated for the payment of the sum of $13,850 for this work by the owners, but with the proviso “that in each case of said payment a certificate shall be obtained from and signed by H. J. Dudley & Son, architects, to the effect the work is done in strict accordance with the drawings and specifications and that they consider the payment properly due.”

The third article provided that the owners at any time during the progress of the work might require [385]*385alterations, deviations, additions to, or omissions from “the said contract, . . . and the same shall in no way injuriously affect or make void the contract; but the difference for the work omitted shall he deducted from the amount of the contract by fair and reasonable valuation, and for additional work required in alterations, as provided and hereafter set forth in article 6.”

Article 6 is in these words:

“No new work of any description done on the premises, or any work of any kind whatsoever, shall be considered extra, unless a written order for the same shall have been given to the contractors by the architects, and their signatures obtained thereto.”

• The seventh article in substance and effect provided that the owner should not in any manner be held responsible for any loss or damage which the complainants might sustain in material or in work.at the hand of any other contractor upon this building.

The work covered by this contract was begun by the complainants soon after the date, and was finished by them in June or July, 1895, and immediately thereafter they presented an account of the amount that they claimed to be due them to W. H. Jackson, who, by the death ■ of H. E. Jackson, which occurred during the progress of the work, was the surviving owner. This account was not accompanied with a certificate from the architects, as required by the second article of the contract. It embraced items of extra [386]*386work aggregating $5,819. Payment being refused, the present bill was filed, seeking a recovery for those amounts, as well as for $808, which they claimed to he due them for damages they had sustained in their work and materials at the hands of other contractors on this building, which it was insisted by them the owners were obligated to pay.

In their bill the complainants admit that the extra work embraced in their account was done without written orders from the architects of the owners; but they allege that they did it by their direction, and that they, and their representative, who was looking after the filling of their contract on this building, were assured, by H. J. Dudley, the senior of this firm of architects, that written orders ' in strict compliance with the requirement of article 6 of the contract had been or would be prepared by him and delivered to the complainants, but that the demands for these written orders were constantly evaded by him and his firm. While it is alleged in the bill that during the progress of the work H. J. Dudley uniformly recognized the obligation of the owners to pay for this work as outside the contract, and by his promise to give them orders in writing covering this extra work lulled complainants into security, yet after the completion of all the work the architects and the defendants denied the liability of' the latter for the same.

To this bill an answer was filed by W. H. Jackson, as well as the other- defendants, in which it was denied [387]*387that the several items claimed as extra work by the complainants were in fact such; hut, on the contrary, it was averred that each one of these items was included in the original contract with complainants. It was further denied that the- architect, H. J. Dudley, made any oral promise to pay any one of said items, and in addition it was averred that, even if it were true he had made such oral promise, the defendants were not bound thereby, by reason of the provision of the sixth article bf the contract, set out above. The owner also .denied the liability of the defendants for the damage that complainants alleged they had sustained at the hands of others, or that there was any sum whatever due complainants on the original contract, because, as averred by the defendant, W. H. Jackson had been compelled to pay other parties sums of money which were properly the debts of complainants, and the sums so paid were relied upon by way of set-off and counterclaim against any demand which complainants may have had against them. It was further averred that complainants were not entitled to a recovery for any balance upon the original contract for the additional reason that the second article thereof made it a condition precedent to the right of complainants to demand payment of defendants for work done that the written certificate of the architect, certifying the money so demanded, was to be obtained, and that complainants had not produced such a certificate.

[388]*388Much evidence was introduced in the cause, and finally the record assumed very large proportions. It is unnecessary, in the view we take of this case, to analyze the testimony. It is sufficient to say that certain matters were developed in the preparation of the cause for trial which throw serious discredit upon the claim of- complainants, if in fact they do not impeach its integrity. Only two or three of these will be mentioned. As has already been stated, the work of complainants was finished in June or July, 1895. They were at once notified that their claim would not be recognized by the owners. The present bill was filed on the 17th of January, 1896. The depositions of the complainants to establish their claim were taken from time to time, so that all. were finished by the 1st of September, 1897. This was the last step taken in the cause by them until the 18fch day of March, 1905, when they took certain depositions in Louisville, Ky., with regard to the character and handwriting of M. J. Bannon.

As a reason for this long lull in the ligation, involving as it did the large amount of money claimed by these complainants to be due them, it is suggested by defendants that it is to be found in the fact that upon the cross-examination of M. J. Bannon in 1897 there was produced and submitted to him by their counsel a paper writing, which is in words and figures as follows:

[389]*389“Nashville, Tennessee, September 9, 1896.
“For services 'rendered we hereby acknowledge indebtedness to H. J.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

RCR Building Corporation v. State of Tennessee
Court of Appeals of Tennessee, 2015
Ahmad Vakili v. Randy Hawkersmith
Court of Appeals of Tennessee, 2001
Realty Shop, Inc. v. RR Westminster Holding, Inc.
7 S.W.3d 581 (Court of Appeals of Tennessee, 1999)
Airline Construction, Inc. v. Barr
807 S.W.2d 247 (Court of Appeals of Tennessee, 1990)
Moore Construction Co. v. Clarksville Department of Electricity
707 S.W.2d 1 (Court of Appeals of Tennessee, 1986)
J. M. Humphries Construction Co. v. City of Memphis
623 S.W.2d 276 (Court of Appeals of Tennessee, 1981)
Dobson v. Rutgers, State University
384 A.2d 1121 (New Jersey Superior Court App Division, 1978)
W & O Construction Co. v. City of Smithville
557 S.W.2d 920 (Tennessee Supreme Court, 1977)
Rossville Federal Savings & Loan Ass'n v. Insurance Co. of North America
174 S.E.2d 204 (Court of Appeals of Georgia, 1970)
Rossville Fed. &C. Assn. v. INS. CO. OF N. AMER
174 S.E.2d 204 (Court of Appeals of Georgia, 1970)
Phifer v. Mutual Ben. Health & Accident Ass'n
148 S.W.2d 17 (Court of Appeals of Tennessee, 1940)
McCrary v. Harrell
62 S.W.2d 566 (Tennessee Supreme Court, 1933)
Atkinson v. Railroad Employes Mutual Relief Society
22 S.W.2d 631 (Tennessee Supreme Court, 1929)
Ault v. Shepherd
8 La. App. 595 (Louisiana Court of Appeal, 1928)
Ragsdale v. Dyer
150 Tenn. 496 (Tennessee Supreme Court, 1924)
Piper v. Murray
115 P. 669 (Montana Supreme Court, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
121 Tenn. 381, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bannon-v-jackson-tenn-1908.