Still v. Regal Wood Products, Inc. (In Re D. L. Bouldin Construction Co.)

6 B.R. 288, 1980 Bankr. LEXIS 4385
CourtUnited States Bankruptcy Court, E.D. Tennessee
DecidedSeptember 30, 1980
DocketBankruptcy No. BK-1-79-01566, Adv. No. 1-79-0044
StatusPublished
Cited by3 cases

This text of 6 B.R. 288 (Still v. Regal Wood Products, Inc. (In Re D. L. Bouldin Construction Co.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, E.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Still v. Regal Wood Products, Inc. (In Re D. L. Bouldin Construction Co.), 6 B.R. 288, 1980 Bankr. LEXIS 4385 (Tenn. 1980).

Opinion

MEMORANDUM

RALPH H. KELLEY, Bankruptcy Judge.

D. L. Bouldin Construction Company (Bouldin) contracted to build a building for Regal Wood Products (Regal). Bouldin filed a petition in bankruptcy after it ceased work on the building and deemed it complete. The trustee in bankruptcy for Bouldin brought this suit against Regal to collect an amount allegedly still owing to Bouldin and to enforce a lien for that amount on Regal’s property.

Most of the other defendants were suppliers or subcontractors on the Regal job. Two were not. Exchange Mutual is the surety on Bouldin’s payment and performance bonds for the Regal job. First Central Bank has a mortgage on Regal’s property.

At the trial the parties generally agreed that the main question is whether the trustee on Bouldin’s behalf can recover from Regal. They also agreed that certain subsidiary questions could be answered first if the court determined the date of completion of the building. The rights of the suppliers and subcontractors against Bouldin, Regal, Exchange Mutual, and First Central Bank were agreed to depend on the date of completion.

Relative to that question, the court finds the facts as follows:

FACTS

In May, 1978, Regal and Bouldin entered into a contract providing for Bouldin to construct a “Stran” steel building with an area of 15,000 square feet. Bouldin began construction, apparently, in the summer of 1978.

Custom Asphalt Paving undertook to do the paving called for in Bouldin’s contract with Regal. The paving was to be of rock and tar. Custom did the work in early November, 1978. Usually, to avoid having the heavy equipment on the paving, it is one of the last things done at a construction site. Custom knew that, because of when it was done, this paving would need some touch-up work in the spring.

Regal started moving machines into the plant in December, 1978. Fire Protection Systems began work on the sprinkler system that month. It did the underground work that month.

Fire Protection Systems continued with the inside work in January, 1979. Buck’s Refrigeration and Air Conditioning had the heat operating in January, 1979. Regal was continuing to set up machines in the building.

In February, Fire Protection Systems completed installing the sprinkler system. Sometime in January or February, Regal hired an electrical contractor to install electrical connections for the machines. That job was completed by February 26, 1979.

On February 26, 1979, John C. Daniels, president of Regal, wrote a letter to D. L. *291 Bouldin complaining that some work had not been done and some repairs were needed. The letter has been referred to as the “punch list”. Besides listing work to be done and repairs, it points out that Regal itself hired and paid the electrical contractor to make the machine connections.

Among other items, the letter listed the following defects and work to be done (paraphrased from letter):

1. The gravel and tar on the parking lots was improperly done and needs to be totally re-done.
2. Front windows and door leak when it rains.
3. Heating system for office and hallway is inadequate and needs more feed-ducts.
4. Sewer lines were not connected to the city sewer system.
5. The condensing unit for the air conditioning has not been installed.
6. The outside building for finishing materials has not been completed.
7. The awnings over the loading dock and overhead door need to be replaced because one has fallen off and the other is bent out of shape.
8. Roof leaks are causing damage to equipment, materials, finished goods, machinery, and the building.
9. Roof vent leaks are also causing damage.
10. The grading on one side of the parking lot is too high and causes water to run into the building, damaging materials.
11. Leaks in the sprinkler system are causing damage to the ceiling and carpet.

Generally the other items in the list called for minor repairs or work to be done or are no longer in dispute.

In March, 1979 Buck’s Refrigeration and Air Conditioning installed a condenser for the air conditioner, but it was the wrong condenser and was removed. Buck’s also added some ducts and corrected some already installed.

Sometime around the end of February or the beginning of March, 1979, a trench was dug for the sewer line connections. The bill is dated March 3, 1979. Apparently the sewer lines were connected in March.

In early April, 1979, Custom Asphalt Paving returned to the site with a work crew, a tank load of oil, four or five truckloads of gravel, and a twelve-ton roller. Custom repaired some soft spots and attempted to correct the grade where it allegedly was too high. On April 19, 1979, John C. Daniels signed a letter accepting Custom’s work, subject to approval by D. L. Bouldin. The work in early April was the last work done at Regal by Custom Asphalt Paving.

In late May and early June, 1979, Fire Protection Systems returned to repair the leaks in the system. It also raised some pipes so that an area could be used for office space. (Apparently this was the overhead office space created pursuant to a contract modification of October 27, 1978.) Fire Protection Systems also installed the signs that go with a sprinkler system. Its last day on the Regal job was June 6, 1979.

Around June 1,1979, Buck’s returned and installed another condenser for the air conditioner. It was the right condenser, but Buck’s didn’t have a circuit breaker needed to operate the system. Bouldin was responsible for furnishing the breaker. The breaker could not be bought locally but was ordered from Neal’s Electric Supply Company. Sometime between June 1 and June 19, 1979, the breaker was delivered. Installation of it was a short job. But Buck’s employees spent all of June 19 at Regal doing the final hook-up and testing of the air conditioning.

After the punch list was received, employees of Bouldin were at Regal at various times to do the work or repairs for which Bouldin admitted responsibility. Keith Bouldin could not recall exactly when crews were at the Regal job between February, 1979 and June 11, 1979, the last day that any of Bouldin’s employees worked at Regal. He testified that Bouldin’s employees had to “work around” Regal’s employees in January when they were setting up ma *292 chines and that the building was useable on March 1, 1979, except for minor work and repairs. Daniels testified that he wrote the punch list letter in late February because the things needed to be done, but Bouldin’s employees had disappeared. John Venier was associated with Regal during the first half of 1979. He testified that Bouldin repaired and did most of the work within about a month after the letter or by the end of March, 1979. John Daniels’ testimony was to the same effect.

On June 8, 1979, D. L.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gooch v. Life Investors Insurance
264 F.R.D. 340 (M.D. Tennessee, 2009)
Rosen v. Tennessee Commissioner of Finance & Administration
280 F. Supp. 2d 743 (M.D. Tennessee, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
6 B.R. 288, 1980 Bankr. LEXIS 4385, Counsel Stack Legal Research, https://law.counselstack.com/opinion/still-v-regal-wood-products-inc-in-re-d-l-bouldin-construction-co-tneb-1980.