East Lake Lumber Box Co. v. Simpson

5 Tenn. App. 51, 1927 Tenn. App. LEXIS 34
CourtCourt of Appeals of Tennessee
DecidedApril 2, 1927
StatusPublished
Cited by7 cases

This text of 5 Tenn. App. 51 (East Lake Lumber Box Co. v. Simpson) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
East Lake Lumber Box Co. v. Simpson, 5 Tenn. App. 51, 1927 Tenn. App. LEXIS 34 (Tenn. Ct. App. 1927).

Opinion

CROWNOVER, J.

The first suit was to recover $1388.01, less $187.38 freight, for lumber and materials furnished to the contractors Harris, Adams & Harris with which to build a store house in Jasper for defendant Simpson, and to enforce a furnishers’ lien against said property.

The second suit was by the contractors Harris, Adams & Harris to recover the balance due on the contract price, and for extras, making' a balance of $2598.30, alleged to be due, and to enforce a mechanic’s lien against the property.

Defendant Simpson denied all liability. He denied that the lumber company had any lien, because it had not given notice within the time required by the statute, and he denied that the contractors had finished the building’, or had constructed it according to the plans and specifications, and he filed his answer as a cross-bill seeking damages for abandonment of contract and for defective construction. Later the cross-bill was amended so as to sue for $2000 damages.

*53 The Chancellor held that the Lumber Company had not served notice as required by the statute and dismissed its bill as against Simpson, but rendered a decree in favor of the contractors for $1200.63 —stating in the decree— “But it appearing that said complainant is entitled to a confessed judgment against defendant, Harris, Adams & Harris, for the sum of $1200.63, with interest from March 20, 1922, to date, amounting to the sum of $108, and complainants will recover the said sum from said Harris, Adams & Harris,” etc.

But in the last above-styled case the Chancellor held that the contractors had breached the contract and that Simpson had been damaged, but as the amount of the damages was not sufficiently shown, he ordered a reference to the-master to take proof and report Simpson’s damagve. He directed that the measure of damages should be the difference between the values of the building as actually erected, and a building erected according to the contract, plans and specifications; and ordered that Simpson be charged with the contract price ($8536.60), and with reasonable pay for such extra work as the proof showed that the contractors were entitled, and should be credited with the payments made to the contractors, and such other reasonable amounts for other changes as the proof showed were left out, beneficial to the contractors, and. in the amount of damages first directed to be ascertained.

The master reported that the contract price, $8536.60 plus extras of $90, totaled $8626.60, credited by payments made by Simpson $7292.03, plus cost of closet left off $50, totaled $7342.03, and that Simpson had been damaged $2000 by reason of the defective construction of the building; hence his total credits were $9342.03, less contract price and extras $8626.60, leaving a balance of $715.42 in Simpson’s favor.

The contractors excepted to the report, and the Chancellor modified it so as to ■ charge Simpson with additional extras $209.50, and rendered a decree for $505.93, and costs of the cause in favor of Simpson and against the contractors. Both the Lumber Company and the contractors appealed and have assigned errors.

The facts, necessary to be stated, are, that Harris, Adams & Harris, a co-partnership of Chattanooga, entered into a contract with J. W. Simpson,- on August 11, 1921, to furnish the materials and to construct a tile store building in Jasper for J. W. Simpson for the sum of $8536.60, and they purchased $1200.63 worth of materials from the East Lake Lumber & Box Company, of Chattanooga, which company furnished said materials and made the last delivery on October 19, 1921. The contractors proceeded to construct said building, to almost completion, but on December 30, 1921, a contro *54 versy arose about the manner of the construction and the completion of said building, and as to the payment of the bills. Simpson insisted that the contractors had not complied with the contract, plans and specifications in certain particulars, and they met at A. R. Hall’s law office in Jasper to adjust matters. After they discussed the differences, and the contractors requested Simpson to draft an agreement and mail it to them at Chattanooga, as they had to catch a train. The keys were turned over to Simpson with the understanding that the building would be completed according to the contract. The agreement was later drafted and mailed to the contractors, who refused to sign it, as they claimed certain, stipulations about the execution of a bond had not been agreed upon. Simpson moved into the building, and one of the contractors came back sometime about January 15, 1922 and did “a little touching up” on the building, but Simpson insisted that the building was not constructed according to the plans and specifications and had not been completed in many respects, and he refused to pay the balance of the contract price.

The Lumber Company, on February 3, 1.922, gave Simpson notice that it had furnished from August 1 to December 1, 1921, $1388.01 worth of materials, itemized, to the contractors for said building, and that the notice was given for the purpose of asserting a fur-nishers’ lien on the property.

On March 20, 1922, the Lumber Company filed its bill against Simpson, alleging these facts, and sought to enforce its furnishers’ lien by attachment; but did not make the contractors parties to the suit.

Later Harris, Adams & Hands, the contractors, filed a bill against Simpson and F. A. Kelly, Trustee, alleging the contract, that they had erected the building according to the plans and specifications, and that Simpson had requested certain changes in the plans and specifications, as follows: (1) In that he had the windows relocated, which broke the bond of the tile and cost them $600 extra in time, labor and material. (2) That he had changed the marble baseboard in front from eighteen inches to twenty-four inches, which cost in time, labor and material $200 extra. (3) That he had the plans of the doors, stairway and vestibule changed which cost them in time, labor and material $175; and that he had made other changes in the floors, from concrete to oak, all of which added to the contract price, totaling $9511.60, upon which he had paid only $7013.22, which left a balance of $2598.38, for which they sued, and sought to enforce a mechanic’s lien by attachment.

The contract and specifications provided that all materials employed in the construction were to be the best of the kind, and all labor was to be performed in the best and most workmanlike man *55 ner by skilled workmen, and that the contractors were to lay ont the work and be responsible for the correctness of the same, and they were to keep a competent foreman at the works so as to duly and adequately protect the work at all times during its progress.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Estate of Jessee v. White
633 S.W.2d 767 (Court of Appeals of Tennessee, 1982)
Edenfield v. Woodlawn Manor, Inc.
462 S.W.2d 237 (Court of Appeals of Tennessee, 1970)
Knoxville Structural Steel Company v. Jones
330 S.W.2d 559 (Court of Appeals of Tennessee, 1959)
Clinchfield Stone Co. v. Stone
254 S.W.2d 8 (Court of Appeals of Tennessee, 1952)
National Nut Co. of California v. Susu Nut Co.
61 F. Supp. 86 (N.D. Illinois, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
5 Tenn. App. 51, 1927 Tenn. App. LEXIS 34, Counsel Stack Legal Research, https://law.counselstack.com/opinion/east-lake-lumber-box-co-v-simpson-tennctapp-1927.