Brady v. Oliver

125 Tenn. 595
CourtTennessee Supreme Court
DecidedDecember 15, 1911
StatusPublished
Cited by70 cases

This text of 125 Tenn. 595 (Brady v. Oliver) is published on Counsel Stack Legal Research, covering Tennessee Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brady v. Oliver, 125 Tenn. 595 (Tenn. 1911).

Opinion

Mr. Justice Lansden

delivered the opinion of the Court.

This is a hill and a cross bill. The main purpose of the original bill is to recover damages against the defendant, Oliver, for the alleged breach of a building contract entered into between the parties, by the terms of which Oliver contracted to construct a power house, a lock and dam, and a core Avail extending from the power house on the east bank of the Tennessee river back to the face of the mountain at Hale’s bar. The complainant alleges his damages to amount to $1,750,000. The defendant filed his answer as a cross bill, by which he sought to .recover from Brady, for an ¿lleged breach upon the part of Brady of the same contract, the sum of $800,000.' The chancellor decreed in favor of Oliver in the sum of $430,529.58. From this decree, Brady prayed a broad appeal, and has assigned errors. Oliver has filed the record for a writ of error, and has assigned two errors thereon. ■ ■

The main work provided for by the contract consisted of the foundations, for a power house, 180 feet long and sixty feet wide on the east bank of the Tennessee river, and extending out into the river; a lock on the west bank of the river, with one concrete wall 630 feet long against the bank, and another 550 feet long, leaving a [603]*603space of sixty feet between, the walls, the walls.to be thirty feet thick at the bottom, and twenty-five feet at the top, and twenty-five or twenty-six feet high; a concrete dam 1200 feet across the river, and connecting the power house and lock; and a concrete core wall on the land, extending from the power house back to the face of the mountain, a distance of 785 feet.

' The original contract was signed between the parties October 19, 1905. It required that the power house work be completed by February 19, 1907, and the entire work by October 19, 1907. Sections 6, 7, and 8 of the original contract are as follows:

“6. It is also agreed that work under this contract shall be begun before October 26, 1905, and shall be prosecuted with such speed, and at such number of points, and with such machinery and force of men, animals and appliances and things as will insure the full completion of all work embraced in this contract not later than the 19th day of October, 1907, and that all the work shall be completed on or before that day.
“The various works are to be begun and prosecuted at such points and at such different portions of the works as shall be directed and approved by the engineer, who shall have power to prescribe the order and approve the manner of executing the same.
“7. Should, at any time during’ the progress of said work, the said contractor refuse or neglect to supply a sufficiency of materials or workmen to insure, in the opinion of the engineer, its completion within the time specified, or should he suspend work (except through [604]*604a stress of weather), on any working day, the said principal shall 'have the power and is hereby authorized, on giving three days’ written notice, to provide, at the ex pense of the contractor, materials and workmen to proceed with and finish the said work (and such expense shall be deducted from the amount retained under this contract by the said principal), and if the amount retained be sufficient to pay such expense, said contractor shall remain liable for any deficiency: Provided, however, that should the said contractor be obstructed or delayed in the prosecution or completion of his work by the act, neglect, delay, or default of the principal, or of the said engineer, or by the abandonment of the work by the employees (commonly known as a strike or strikes) of the contractor, through no fault of the contractor, then the time herein fixed for the completion of the said work shall be extended for a period equivalent to the time so lost by reason of any or all of the causes specified; but no such allowance shall be made unless claim therefor be presented in writing to the said engineer within twenty-four hours of the commencement of such delay or delays. The duration of such extension or extensions shall be certified to by the engineer, but appeal from his decision may be made to arbitration in the manner as herein provided.
“8. And it is also furthermore agreed between the parties hereto that, in case of a default on the part of the contractor to promptly and properly proceed with and complete the work, said principal reserves the right and option to annul and cancel this agreement and to relet [605]*605the work, or any part thereof, or otherwise prosecute it, and said contractor shall not be entitled to any claim for damages on account of such annulment, nor shall such annulment affect the right of said principal to recover damages which may arise from such failure on the part of said contractor to fulfill the terms of this agreement. And in case of such annulment all moneys due said contractor, or retained under the terms of this agreement, shall be- forfeited to said principal; but such forfeiture shall, however, not release such contractor from the fulfillment of this contract, but he and his sureties shall compensate the principal for any and all loss and damage which may result from such default. Said contractor shall be creclitéd with the amount of the moneys so forfeited toward any greater sum that he may become liable for to said principal on account of the default of said contractor.”

The defendant, Oliver, entered upon the performance of this contract soon after its execution. In a short time thereafter controversies arose between the parties concerning a number of material matters, and especially the contention of Oliver that the conditions under which the work was to be done were materially misrepresented in the drawings and specifications, which were made a part of the contract. This controversy was waged for some time, during which progress upon the work seems to have been slow and unsatisfactory to Brady. On the 30th of April, 1907, the parties entered into a supplemental contract, by the terms of which all of the preceding disputes were settled, or a basis of settlement [606]*606was agreed upon, and further time was given Oliver in which to complete the work. This contract provided as follows: .

“It has been and is hereby mutually agreed between the said principal and the said contractor:
“(T) That the claim for compensation for work and •material in the slopes, and in excavating for the core wall, and for damages claimed as the result of alleged delay of work in the excavation of said core wall, alleged to be caused by the engineer of said Brady, which is asserted by the contractor to be additional work and damages for which he is entitled to extra compensation, be referred to Engineer Bogart for decision, with the privilege reserved to either party to have arbitration, if demanded and as in the contract provided, after his decision.
“(2) It is further agreed that the engineer shall divide the cofferdam into four or more sections, and shall apportion to each section its due proportion of the contract price, and give to the contractor separate estimates on each section. The first estimate of any section shall be due when the section is completed and the excavation made as designated by the contract, and other estimates when and as prescribed in the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Julie Buhler v. Lefkovitz & Lefkovitz, PLLC
Court of Appeals of Tennessee, 2025
Buhler v. Davis
M.D. Tennessee, 2022
Mid-South Industries, Inc. v. Martin MacHine & Tool, Inc.
342 S.W.3d 19 (Court of Appeals of Tennessee, 2010)
Forrest Construction Co. v. Laughlin
337 S.W.3d 211 (Court of Appeals of Tennessee, 2009)
UT Medical Group, Inc. v. Vogt
235 S.W.3d 110 (Tennessee Supreme Court, 2007)
Harper-Wittbrodt Automotive Group, LLC v. Sam Teague
Court of Appeals of Tennessee, 2006
Lopez v. Taylor
195 S.W.3d 627 (Court of Appeals of Tennessee, 2005)
Chuck Robertson v. Melvin G. George
Court of Appeals of Tennessee, 2001
Greene v. THGC, Inc.
915 S.W.2d 809 (Court of Appeals of Tennessee, 1995)
Freytag v. Crass
913 S.W.2d 171 (Court of Appeals of Tennessee, 1995)
Lamons v. Chamberlain
909 S.W.2d 795 (Court of Appeals of Tennessee, 1993)
Loveday v. Cate
854 S.W.2d 877 (Court of Appeals of Tennessee, 1992)
Jamison v. Jamison Pest Control Co.
852 S.W.2d 884 (Court of Appeals of Tennessee, 1992)
Wright v. Wright
832 S.W.2d 542 (Court of Appeals of Tennessee, 1991)
McClain v. Kimbrough Const. Co., Inc.
806 S.W.2d 194 (Court of Appeals of Tennessee, 1990)
Harlan v. Hardaway
796 S.W.2d 953 (Court of Appeals of Tennessee, 1990)
GRW Enterprises, Inc. v. Davis
797 S.W.2d 606 (Court of Appeals of Tennessee, 1990)
Williamson v. Upchurch
768 S.W.2d 265 (Court of Appeals of Tennessee, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
125 Tenn. 595, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brady-v-oliver-tenn-1911.