Anvil Mining Co. v. Humble

153 U.S. 540, 14 S. Ct. 876, 38 L. Ed. 814, 1894 U.S. LEXIS 2203
CourtSupreme Court of the United States
DecidedMay 14, 1894
Docket323
StatusPublished
Cited by167 cases

This text of 153 U.S. 540 (Anvil Mining Co. v. Humble) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anvil Mining Co. v. Humble, 153 U.S. 540, 14 S. Ct. 876, 38 L. Ed. 814, 1894 U.S. LEXIS 2203 (1894).

Opinion

Mr. Justice Brewer,

after stating the cáse, delivered the opinion of the court.

The claims of the respective parties, as stated by the court in its charge to the jury, are briefly these: Plaintiffs claimed, *547 first, an amount unpaid for ore mined in September and October; second, wages which they had paid during certain periods when they were delayed in the prosecution of the work by the fault of the defendant; and third, the profits which they would have made if the defendant had not prevented them from completing the contract. On the other hand, the defendant claimed first, excessive freights paid by reason of a failure on the part of the plaintiffs to produce the ore seasonably; second, damages for a failure to bring out that per cent of the ore which by the. contract plaintiffs had agreed to take out of the mine; and third, damages on account of the unskilful working of the mine.

The first claim of the plaintiffs, to wit, for ore mined in September and October, is not disputed. With regard to the second, the court accepted the rule of law agreed upon by counsel for both parties, and, therefore, there is no dispute as to that. The controversy is in respect to plaintiff’s claim for profits, and here many questions are discussed by counsel. We shall in our examination of them follow the order in which they are presented in the brief of defendant’s counsel. The first objection to any recovery under this claim is that by the very terms of the contract the defendant was at liberty to terminate it at any time, and hence it is insisted that; even if it did so, plaintiffs were not entitled to recover any profits which they might have made had it not been terminated; that, coupled with the right to terminate, was a special provision, to wit, an award of referees for estimating the damages which the plaintiffs should sustain in consequence of such termination, and that no attempt to secure such an award was alleged or proved. To this it may be replied that the contract- did not give to the defendant a right arbitrarily to terminate the contract, but only when it determined that the caving system was “prejudicial to the future welfare and development of the mine,” and that there is no pretence that it ever made such determination. On the contrary, the defendant set up as a-defence that the plaintiffs abandoned- the work and thus broke thé contract, and that it suffered great damage thereby, and on the trial the whole *548 scope of its testimony in this respect was in denial of the charge that it had stopped the plaintiffs from continuing the mining of ore, or in any manner sought to terminate the contract. For aught that appears to the contrary in this record, the defendant, now as ever, believes that the caving system is not only not prejudicial, but the best method of working the mine, and broke the contract with plaintiffs only for the sake of giving it to another party.

A second matter of dispute, and one which bears upon the rightfulness of the conduct of the respective parties pending the work, arises on the construction to be given to the stipulation of July 10. The original contract provided that the ore should contain at least 56 per cent of metallic iron, and' that no ore of lower grade should be accepted or paid for by the company. The contention of the defendant is that this stipulation modified the contract so that thereafter all the ore taken from the mine in order to be accepted must contain at least 58 per cent of metallic iron, while the plaintiffs insist that this only applied to the ore from the second and third levels, that.from the first level being subject to the provision of the original contract, to wit, 56 per cent of metallic iron. We agree with the plaintiffs in their construction of the stipulation. The original contract was only for removing ore from the first level, the company having, however, the option to extend it to the second and third levels. This stipulation provides for such an extension, but it is made expressly subject to “ an exception.” The use of the word “ exception ” indicates that something is taken out from the principal matter provided for in the clause or paragraph in which the word is found, and not that something is taken out of or changed from other provisions in other clauses of the entire contract. It will be borne in mind that this is an independent agreement, made at a subsequent time, though supplemental to and in extension of the original contract. And while for a full understanding of the scope of the obligations created by it, the original contract must be referred to, yet, in determining the import of the language used, it is to be construed as an independent agreement, and when it *549 makes an extension of the obligations of the plaintiffs to a new matter anything which is stated as an exception is to be taken as an exception to the obligations assumed in respect to this additional matter. If the intent was.to change the stipulation as to the first level, some other word than “ exception ” would unquestionably have been used. It is unnecessary to refer to extrinsic testimony, of which there was some and of great significance, in order to establish the meaning of this stipulation. For, standing by itself, the fair and reasonable construction is that the stipulation as to the increased per cent was applicable only to the ore taken from the second and third levels, while as to the first level there was no change.

A third proposition -of defendant is that “ under the facts in this case the damages claimed for loss of profits were too uncertain, contingent, and conjectural to found a verdict upon.” Profits which are a mere matter of speculation cannot be made the basis of recovery in suits for breach of contract, while profits which are reasonably certain may be. As said by Mr. Justice Lamar, in Howard v. Stillwell & Bierce Manufacturing Co., 139 U. S. 199, 206: “ But it is equally well settled that the profits which would have been realized had the contract been performed, and which have been prevented by its breach, are included in the damages to be recovered in every case where such profits are not open to the objection of uncertainty or of remoteness, or where from the express or implied terms of the contract itself, or the special circumstances under which it was made, it may be reasonably presumed that they were within the intent and mutual understanding of both parties at the time it was entered into.” See also Cincinnati Gas Company v. Western Siemens Company, 152 U. S. 200.

Now, there was in this case testimony to show the cost of mining each ton of ore, and also the amount of ore remaining in the first level of the mine at the time the work stopped. From these figures the profit which would have been made by the plaintiffs if they had completed the work of mining all the ore on the first level is a mere matter of multiplication. *550 It is true that the cost of mining the remaining ore might differ from that of mining the ore which had already been taken out.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Watson v. Cal-Three, LLC
254 P.3d 1189 (Colorado Court of Appeals, 2011)
ACG, INC. v. Southeast Elevator, Inc.
912 S.W.2d 163 (Court of Appeals of Tennessee, 1995)
Wilcox Trucking v. First Hartford Realty, No. 366925 (Nov. 23, 1992)
1992 Conn. Super. Ct. 10510 (Connecticut Superior Court, 1992)
Prudential Insurance Co. of America v. Executive Estates, Inc.
369 N.E.2d 1117 (Indiana Court of Appeals, 1977)
Dalton v. Mullins
293 S.W.2d 470 (Court of Appeals of Kentucky (pre-1976), 1956)
Sprague v. Boyles Bros. Drilling Co.
294 P.2d 689 (Utah Supreme Court, 1956)
In Re Petroleum Carriers Co.
121 F. Supp. 520 (D. Minnesota, 1954)
David J. Joseph Co. v. United States
82 F. Supp. 345 (Court of Claims, 1949)
McWithy v. Heart River School District No. 22
32 N.W.2d 886 (North Dakota Supreme Court, 1948)
Jacob v. Miner
191 P.2d 734 (Arizona Supreme Court, 1948)
Carlson v. Bain
182 P.2d 909 (Supreme Court of Colorado, 1947)
Robinson v. Johancsik
48 A.2d 273 (Supreme Court of Connecticut, 1946)
McKeever v. Washington Heights Realty Corp.
37 A.2d 305 (Court of Appeals of Maryland, 1944)
Martin v. Lafon
100 P.2d 182 (Arizona Supreme Court, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
153 U.S. 540, 14 S. Ct. 876, 38 L. Ed. 814, 1894 U.S. LEXIS 2203, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anvil-mining-co-v-humble-scotus-1894.