Guy M. Beaty, Sr., and Cross-Appellants v. Brock & Blevins Company, Inc., and Cross-Appellees

319 F.2d 43, 1963 U.S. App. LEXIS 4962
CourtCourt of Appeals for the Sixth Circuit
DecidedJune 14, 1963
Docket15003_1
StatusPublished
Cited by12 cases

This text of 319 F.2d 43 (Guy M. Beaty, Sr., and Cross-Appellants v. Brock & Blevins Company, Inc., and Cross-Appellees) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Guy M. Beaty, Sr., and Cross-Appellants v. Brock & Blevins Company, Inc., and Cross-Appellees, 319 F.2d 43, 1963 U.S. App. LEXIS 4962 (6th Cir. 1963).

Opinion

BOYD, District Judge.

Guy M. Beaty, Sr. and others, doing business as Guy M. Beaty & Company, a partnership, with office at Chattanooga, Tennessee, brought suit in a state court in Tennessee against Brock & Blevins Company, Inc., a corporation of Georgia, and the Home Indemnity Company, a New York Corporation. The suit arose out of a construction sub-contract entered into between Beaty & Company and Brock & Blevins. These parties hereinafter will also be referred to as the plaintiffs and the defendant respectively. The Home Indemnity Company is sued as surety on the payment bond of its co-defendant, Brock & Blevins. The cause was duly removed to the District Court. Diversity of citizenship is invoked under Title 28 U.S.C., Section 1332 (a) (1).

During the period of the Korean War the Volunteer Ordnance Works at Tyner, Tennessee, which had been a useful federal facility during World War II, was rehabilitated and restored for the production of explosives. The undertaking was one of some magnitude and a multimillion dollar prime contract for the rehabilitation work was entered into between the Federal Government and Hiwassee Contractors. The prime contractor, Hiwassee, then subcontracted the mechanical work involved to the defendant, Brock & Blevins Company, Inc. Brock & Blevins in turn subcontracted the insulation part of the work on the project to the plaintiffs. It is the latter agreement, actually a sub-subcontract, with which we are here concerned.

As best we can determine from the record it was generally contemplated by all concerned that extra work would be necessary from time to time in the course of this construction. “Extra work” or “additional work” in this sense means work other than that contemplated in the original specifications and addenda. Extra work on this project was authorized by the government’s architects-engineers when they determined that work additional to that disclosed by *45 the specifications and addenda was necessary. Authorization for the doing of such work was accomplished by their issuance of “field directives.” In the ordinary course of things these field directives directly concerned or affected subcontractors down the contractual line. When the field directives authorized insulation work, Brock & Blevins would notify the plaintiffs that field directives had issued, describing the work to be performed. This notification served as the plaintiffs’ authorization to execute the work therein described. Plaintiffs’ charges for such work were submitted by invoices to the defendant. The latter then tacked on a ten per cent handling charge and passed the invoices on to Hiwassee for approval and submission to the government.

The plaintiffs instituted suit to recover amounts allegedly due for work done under two groups of field directives. One such group contained only two field directives, designated M-39 and M-40. The District Court allowed recovery by the plaintiffs for this particular work and it is from that portion of the judgment of the District Court granting such relief in the amount of $7,145.60 that the defendants take their appeal.

The government refused payment of the amounts charged for work done pursuant to the two field directives aforesaid, claiming that such was not extra work, but was included and-disclosed in the original specifications and addenda. Since it had paid for the work so included, the government claimed that payment for the work done pursuant to these field directives had been made. Thus Brock & Blevins did not receive payment for its charges under these field directives and it in turn did not pay the plaintiffs for such work. Brock & Blevins took the position that under its contract with plaintiffs payment to the plaintiffs was conditioned upon receipt of payment from the government. By way of defense such an interpretation of the contract between these parties was sought in the District Court. In order to demonstrate that the contract contemplated such a condition Brock & Blevins undertook to prove a custom among contractors in the area to the effect that subcontractors, especially on government contracts, do not expect payment unless payment is made to their contractors. The District Judge, to whom the case was tried, found no such custom and interpreted the contract as containing no such condition to payment as was urged by Brock & Blevins. The defendant in its appeal contends that the District Court erroneously interpreted the contract.

The intention of the parties as evidenced by the written contract governs our inquiry. Petty v. Sloan, 197 Tenn. 630, 277 S.W.2d 355, 1955. 1 The provisions of the within contract urged by Brock & Blevins as reflecting an intention of the parties that payment to the plaintiffs was conditioned upon payment by the government are the following:

“The Sub-Contractor 2 agrees as follows:

“j * * *
“1. The intent of this agreement is to cover all the requirements for insulation within the scope of the original specifications and addenda as noted above. Any additional work not covered by these specifications and addenda but authorized by the Contracting Officer or his representative will be negotiated and paid for by processing, through proper channels, the necessary Field Directives.
******
“3. Payment for performance of any work will be made monthly and *46 in the same manner that payment is made to the Contractor by Owner.
ft vr ft ft ft
“IX. To be bound to the Contractor by the items of the general conditions of the specifications and addenda, and to conform to and comply with drawings and specifications and addenda, and to assume toward the Contractor all the obligations and responsibilities that the Contractor assumes in and by the aforesaid documents toward the Owner, insofar as they are applicable to this particular sub-contract.”

Do the provisions of the contract relating to the method and time of payment for work done and the processing of claims for the extra work indicate an intention of the parties that payment to the sub-contractor plaintiffs was subject to the condition here urged? The District Court found that the contract merely explained how payment was to be made, but did not condition the defendant’s liability. If the language of the contract be clear and unambiguous, the ascertainment of the intention of the parties is a question for the court. Petty v. Sloan, supra. If the language of the contract is not free of ambiguity, extrinsic evidence, such as evidence of the interpretation the parties themselves have given the contract, may be received to determine the intention of the parties. Fidelity-Phenix Fire Ins. Co. of New York v. Jackson, 181 Tenn. 453, 181 S.W.2d 625, 1944. Upon the court’s findings of fact from such evidence, its interpretation of the contract is largely based. J. W. Bateson Company, Inc. v. Romano, 266 F.2d 360 (C.A.6) 1959.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Surti
434 B.R. 515 (M.D. Tennessee, 2010)
EC Ernst, Inc. v. Koppers Co., Inc.
476 F. Supp. 729 (W.D. Pennsylvania, 1979)
Kaiser v. Lyon Metal Products, Incorporated
461 S.W.2d 893 (Missouri Court of Appeals, 1970)
Zussman v. Lake-Spiro-Shurman, Inc.
469 S.W.2d 671 (Court of Appeals of Tennessee, 1970)
Routed Thru-Pac, Inc. v. The United States
401 F.2d 789 (Court of Claims, 1968)
B. C. Richter Contracting Co. v. Continental Casualty Co.
230 Cal. App. 2d 491 (California Court of Appeal, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
319 F.2d 43, 1963 U.S. App. LEXIS 4962, Counsel Stack Legal Research, https://law.counselstack.com/opinion/guy-m-beaty-sr-and-cross-appellants-v-brock-blevins-company-inc-ca6-1963.