J. R. Hale & Sons v. R. C. Stone Engineering Co.

14 Tenn. App. 461, 1932 Tenn. App. LEXIS 54
CourtCourt of Appeals of Tennessee
DecidedJanuary 30, 1932
StatusPublished
Cited by7 cases

This text of 14 Tenn. App. 461 (J. R. Hale & Sons v. R. C. Stone Engineering Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. R. Hale & Sons v. R. C. Stone Engineering Co., 14 Tenn. App. 461, 1932 Tenn. App. LEXIS 54 (Tenn. Ct. App. 1932).

Opinion

DeWITT, J.

Complainants W. T. Hale, Jr. and R. W. Hale, composing the partnership of J. R. Hale & Sons, filed the bill in this cause on January 28, 1927, against R. C. Stone Engineering Company and Aetna Casualty & Surety Company, to recover damages in the sum of $60,000 for the breach of a contract entered into on September 23, 1924, between J. R. Hale & Sons and R. C. Stone Engineering Company for the erection of a reinforced concrete storage annex to the complainants’ grain elevator, including an oat bleacher, at Nashville, Tennessee. The recovery sought of the Aetna Casualty and Surety Company was predicated upon two bonds in the sum of $28,000 each, executed to the complainants by the Stone Engineering Company as principal, and the Aetna Casualty & Surety Company as surety.

*463 Tbe defendant R. C. Stone Engineering Company was alleged to be a non-resident corporation. No personal service of process was bad upon it and no attachment was issued and levied bn any property belonging to it. It was brought before the court only by publication, and therefore no personal judgment could be rendered against it.

Upon the hearing upon a voluminous record, the Chancellor sustained the pleas in the answer of the Aetna Casualty & Surety Company that the complainants’ right of action was barred because of the contractual limitations in each of the bonds. Prom his decree dismissing the bill the complainants have appealed and in this court they insist, first, that it w'as error to hold that complainants’ right of action was.barred because of the contractual limitations in the bonds sued upon, and second, that it was error not to hold that these contractual limitations had been waived by the Surety Company. So many-provisions of the contract must hereinafter be discussed, that it is here shown, as follows:

“THIS AGREEMENT, made and entered into this 23rd day of September, A. D., 1924, by and between R. C. Stone Engineering Company a corporation organized under the laws of the State of Missouri, party of the First Part, hereinafter designated the Contractor, and J. R. Haíe & Sons, a partnership doing business under the laws of the State of Tennessee, party of the second part, hereinafter designated as Owner,
“WITNESSETH, as follows:
“ARTICLE I; The Contractor shall and will provide all materials and perform all work, except as specified in Article II, necessary to the erection, complete and in operation, of a reinforced concrete storage annex, to the Owner’s grain elevator, near Nashville, Tennessee, including an oat bleacher, all in strict accordance with the plans and specifications attached hereto, and which are a part of this agreement.
“ARTICLE II: The Owner agrees to furnish and erect at his own expense, the boiler and steam piping necessary for the oat bleacher. The Owner further agrees to furnish without cost to the Contractor, the cooling tank for the bleacher, also the pipe between the cooling tank and the bleacher, for sulphur fumes, which equipment the Contractor shall erect in place as a part of his work.
“ARTICLE III: The Owner has retained the John S. Met-calf Co., of Chicago, Illinois, hereinafter designated as the Engineer, to act in his interest as Consulting and Supervising Engineer, and the Contractor hereby recognizes and agrees to the full and complete jurisdiction of said John S. Metcalf Co., in *464 all matters or details pertaining to tbe work comprehended by this agreement.
“ARTICLE IV: Tbe Contractor shall furnish all necessary working of shop drawings or details, which shall in each case receive the formal approval of the Engineer before any material is ordered or any work is done. The Engineer’s representative on the site of the work shall inspect all materials received and all work done, and his judgment as to defective or inferior work or material shall be final. Any material rejected for cause shall be immediately removed from the site, and any defective work shall be replaced promptly, by the Contractor, without cost to the Owner.
“ARTICLE V: The Contractor agrees to start the work immediately upon the execution of this agreement, and to so expedite its progress that it will be substantially completed by January 1, 1925, so that the Owner may safely receive, ship, or store grain on that date, except however, that full time allowance shall be made to the Contractor for delays through causes beyond his reasonable control.
“ARTICLE VI: On the first and fifteenth of each month the Contractor shall prepare and deliver to the Engineer, an estimate of the value of the materials delivered, and work done, during the estimate period. The Engineer shall check said estimate promptly, and the Owner agrees to the immediate payment of eighty-five per cent of the amount of all such estimates bearing the Engineer’s approval. The balance of fifteen per cent is to be retained by the Owner until completion and acceptance of the work. The Contractor agrees that no estimate submitted shall be greater in amount than the relation the completed work bears to the whole amount of the contract price.
“The Contractor also agrees to submit with each estimate receipted invoices and payrolls to the amount of said estimate.
“ARTICLE VII: The Owner agrees to pay for all Work covered by this agreement, in the manner specified in Article VI the sum of $56,000 (FIFTY SIX THOUSAND DOLLARS) plus one-half the cost of the wiring and the fixtures necessary for the electric lights specified.
“ARTICLE VIII: The Contractor agrees that the annex shall have a-storage capacity, without trimming, of 380,000 (three hundred and eighty thousand) bushels of wheat weighing sixty pounds per bushel.
“It is further mutually agreed that the undertakings hereof, and each and all of them, shall be binding upon the successors, administrators, or executors of the respective parties hereto.
*465 ‘'In testimony whereof, the parties hereto have executed tliis agreement, the days and year first above written.
Witness; ‘R. C. Stone Eng. Co.,
“G. T. Butt, ‘By J. C. Stratton,
“Witness; ‘J. R. Hale & Sons,
“J. W. Berrigo. ‘By W. T. Hale, Jr.”

This contract and the specifications provided for the construction of twenty-three concrete tanks for the storage of grain, “basement and conveyor tunnel, conveyor cupola above tanks, installing of belt conveyors and drives, power for same, all spouting to and from bins, connecting both belts to elevators in old elevator adjacent, both to receive in, to and from new tanks and building the bleacher.”

The specifications contained, among other provisions, the following:

“RESPONSIBILITY:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hardcastle v. Harris
170 S.W.3d 67 (Court of Appeals of Tennessee, 2004)
City of Hot Springs v. National Surety Co.
531 S.W.2d 8 (Supreme Court of Arkansas, 1975)
Central Towers Apartments, Inc. v. Martin
453 S.W.2d 789 (Court of Appeals of Tennessee, 1969)
Tullahoma Concrete Pipe Co. v. T. E. Gillespie Construction Co.
405 S.W.2d 657 (Court of Appeals of Tennessee, 1966)
State v. Evans
334 S.W.2d 337 (Court of Appeals of Tennessee, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
14 Tenn. App. 461, 1932 Tenn. App. LEXIS 54, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-r-hale-sons-v-r-c-stone-engineering-co-tennctapp-1932.