Tullahoma Concrete Pipe Co. v. T. E. Gillespie Construction Co.

405 S.W.2d 657, 56 Tenn. App. 208, 1966 Tenn. App. LEXIS 220
CourtCourt of Appeals of Tennessee
DecidedFebruary 25, 1966
StatusPublished
Cited by11 cases

This text of 405 S.W.2d 657 (Tullahoma Concrete Pipe Co. v. T. E. Gillespie Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tullahoma Concrete Pipe Co. v. T. E. Gillespie Construction Co., 405 S.W.2d 657, 56 Tenn. App. 208, 1966 Tenn. App. LEXIS 220 (Tenn. Ct. App. 1966).

Opinion

PURYEAR, J.

For the sake of convenience we will, as counsel have done, refer to the parties herein as they were designated in the trial court, to-wit, Tullahoma Concrete Pipe Company, Inc., as complainant, and to each defendant simply as “defendant.” There being-several defendants, we will refer to the defendant, T. E. Gillespie individually and d./b/a Gillespie Construction Company, as “Gillespie” and the defendant, United States Fidelity and Guaranty Company, as “surety.” "We will refer to the third defendant, Ogles-Comer Company, Inc., as “Ogles-Comer”.

The facts of the case are briefly as follows:

The State of Tennessee awarded a highway construction contract in Wilson County to the defendant, Gillespie, as principal contractor. The project is known as Tennessee Highway Project No. F-024-l-(2), Wilson County, Tennessee, and is referred to as the Lebanon By-Pass. Presumably, Gillespie furnished the statutory bonds required by law for a general contractor on a highway project, but the record is silent on this question with the exception of an allegation to that effect in the original bill and a denial of such allegation in the answers of the defendants.

[211]*211Gillespie sub-contracted a portion of the work to Ogles-Comer, and in turn, Gillespie called on Ogles-Comer, in connection with the sub-contract, to execute in his favor performance and payment bonds guaranteeing Ogles-Comér’s performance of the sub-contract and the payment for labor and materials required by it in the performance of the sub-contract.

United States Fidelity and Guaranty Company exe- ■ cuted these bonds, as surety, with Ogles-Comer as principal, and a copy of the sub-contract labor and materials bond is filed as an exhibit to its answer.

The original bill alleges, and complainant seeks to support this allegation by some proof, that complainant furnished concrete pipe for its use in the performance of its sub-contract and that there is a balance due complainant on this account of $27,898.39. Objections were filed to certain portions of this evidence offered by complainant and these objections were followed by a motion to strike the portions of such testimony, to which objections were made. (Tr. p. 113). This motion to strike was overruled by the Chancellor. (Tr. p. 118). However, the objections were later sustained and the Chancellor held that the proof fails to establish that the materials in question were consumed in the work or necessarily so intended to be consumed.

It is conceded by counsel for all of the parties that Ogles-Comer abandoned and left the job in September, 1962. In order to protect itself on the performance bond, the surety then obtained another contractor to finish that portion of the project which had been sub-contracted by Ogles-Comer.

This suit was filed more than twelve months after Ogles-Comer discontinued its work on the project in [212]*212question. The sub-contract labor and materials bond (Tr. p. 19) provides, among other things, that no suit or action shall be commenced thereunder after the expiration of one year following the date on which the principal (Ogles-Comer) ceased work on said contract. The surety contends that this suit is barred by the foregoing provision of the bond.

During the month of August, 1962, Ogles-Comer executed a note to complainant for the amount which complainant contended Ogles-Comer owed it for materials furnished, but this note has not been filed as an exhibit in this case.

. This note was later negotiated to a bank and was being held by such bank at the time this suit was filed. The bank was not made a party to this suit and the name of ' such bank does not appear in the record.

After the surety filed its answer to the original bill, complainant filed an amended and supplemental bill (Tr. pp. 24-29) alleging, among other things, that the surety offered to settle complainant’s claim for the sum of $25,000.00, that the complainant accepted this offer before it was withdrawn and that this alleged offer and acceptance ripened into a contract with the surety.

This amended and supplemental bill also alleges that the surety assumed the role of a sub-contractor and took over the work of its principal, Ogles-Comer, including the materials delivered by complainant, and that the surety used such materials in the completion of the work and received the benefit thereof.

To this amended and supplemental bill, the surety filed an answer denying the alleged offer of settlement and [213]*213acceptance thereof, and further denying that it had enriched itself hy the use of complainant’s materials by taking’ over the subcontract and completing it.

Gillespie filed an answer to the original, amended and supplemental bills, which neither admitted nor denied the alleged offer of settlement and the other allegations thereof regarding the surety’s taking over the performance of the subcontract, but specifically denying liability to complainant for any amount.

In this answer, Gillespie also incorporated a cross-bill praying that if complainant be awarded a recovery against him that he, in turn, be awarded a recovery against Ogles-Comer and the surety. To this cross-bill, the surety filed its answer, reiterating its denial of liability.

The case was tried by the Chancellor on depositions and documentary evidence, as a result of which the Chancellor entered a decree dismissing the original, amended and supplemental bills against Gillespie and the surety and awarding a recovery in favor of complainant against Ogles-Comer in the sum of $27,898.39, and also dismissing the cross-bill of the defendant, Gillespie, which decree is in words and figures as follows:

“This cause came on to be heard on this 27 day of April, 1965, before the Honorable John D. Templeton, Chancellor, upon the original and amended and supplemental bill of complainant, Tullahoma Concrete Pipe Company, Inc., the answers thereto, the cross bill of the cross complainant, Gillespie, the answer and pro confesso thereto, the depositions on file, motion of defendant, United States Fidelity & Guaranty Company to strike certain testimony contained in the depo[214]*214sition of Jerry Garner, taken on June 14,1964 and filed in this cause on August 24, 1964, upon the arguments and briefs of counsel and upon the entire record in this cause, including particularly a memorandum of the Court filed February 23, 1965, which is hereby ordered made a part of the record in this cause. For the reasons stated in the memorandum of the Court, it is ordered, adjudged and decreed that defendant, United States Fidelity & Guaranty Company’s objections noted on the deposition and its motion to strike certain testimony of Jerry Garner filed in this cause on August 24, 1964, is sustained, to which action of the Court in sustaining defendant’s objections and motion to strike the complainant, Tullahoma Concrete Pipe Company, Inc., duly and timely excepted and now excepts.
IT IS FURTHER ORDERED, ADJUDGED AND DECREED by the Court that complainant’s bill be and the same hereby is dismissed as to the defendants, T. E. Gillespie, individually and d/b/a T. E. Gillespie Construction Company and United States Fidelity & Guaranty Company and by reason thereof, the cross bill of the complainant, T. E. Gillespie d/b/a T. E. Gillespie Construction Company is likewise dismissed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Karl Robert Kokko v. Thomas L. Moore, Jr.
Court of Appeals of Tennessee, 2025
David Desgro v. Paul Pack d/b/a Resi Chek
Court of Appeals of Tennessee, 2013
James Fortune v. Unum Life Insurance Company of America
360 S.W.3d 390 (Court of Appeals of Tennessee, 2010)
Lawrence Westfall v. Brentwood Svc. Grp, Inc.
Court of Appeals of Tennessee, 2000
Mason v. Capitol Records, Inc.
Court of Appeals of Tennessee, 1999
Allen v. National Advertising Co.
798 S.W.2d 766 (Court of Appeals of Tennessee, 1990)
Martin v. Martin
755 S.W.2d 793 (Court of Appeals of Tennessee, 1988)
Covey v. State
504 S.W.2d 387 (Court of Criminal Appeals of Tennessee, 1973)
Neas v. Snapp
426 S.W.2d 498 (Tennessee Supreme Court, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
405 S.W.2d 657, 56 Tenn. App. 208, 1966 Tenn. App. LEXIS 220, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tullahoma-concrete-pipe-co-v-t-e-gillespie-construction-co-tennctapp-1966.