David Desgro v. Paul Pack d/b/a Resi Chek

CourtCourt of Appeals of Tennessee
DecidedJanuary 8, 2013
DocketE2012-00918-COA-R3-CV
StatusPublished

This text of David Desgro v. Paul Pack d/b/a Resi Chek (David Desgro v. Paul Pack d/b/a Resi Chek) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
David Desgro v. Paul Pack d/b/a Resi Chek, (Tenn. Ct. App. 2013).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE Assigned on Briefs November 8, 2012

DAVID DESGRO v. PAUL PACK d/b/a RESI CHEK

Appeal from the Circuit Court for Carter County No. C12376 Hon. Thomas J. Seeley, Jr., Judge

No. E2012-00918-COA-R3-CV-FILED-JANUARY 8, 2013

Plaintiff, David Desgro, alleged that he hired defendant, Paul Pack d/b/a Resi Chek, to perform an inspection on a house plaintiff wanted to purchase. After defendant inspected the house and reported the house had no major problems, plaintiff purchased the house in reliance on defendant’s report. Plaintiff claims that he then discovered multiple serious issues with the house, including plumbing problems, insulation and heat pump problems, and inadequate floor support. Plaintiff filed suit 13 months after the inspection was completed, and defendant moved for summary judgment, claiming that plaintiff’s signed contract with defendant provided that plaintiff must file suit on any claims within one year of the date of inspection. The trial court found that plaintiff signed such an agreement and that the contractual limitations period of one year was reasonable. The trial court granted summary judgment to defendant, ruling that plaintiff’s claims were untimely. Plaintiff appeals. We affirm.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Circuit Court Affirmed; Case Remanded

J OHN W. M CC LARTY, J., delivered the opinion of the Court, in which C HARLES D. S USANO, J R., P.J., and D. M ICHAEL S WINEY, J., joined.

Kathryn J. Dugger-Edwards, Elizabethton, Tennessee, for the appellant, David Desgro.

John B. McKinnon III, Johnson City, Tennessee, for the appellee, Paul Pack d/b/a Resi Chek. OPINION

I. BACKGROUND

On January 6, 2009, the parties met at the subject home and plaintiff signed 1 an agreement that was presented to him by defendant regarding performance of the home inspection. This agreement, titled “NACHI Home Inspection Agreement,” provides,

CLIENT shall have no cause of action against INSPECTOR after one year from the date of the inspection.

The inspection was performed that same day. Plaintiff filed this lawsuit on February 2, 2010, more than one year from the date of inspection. The trial court granted summary judgment to defendant, finding that the contractual limitation period was reasonable and enforceable. The trial court stated that plaintiff “had plenty of time to find any deficiency” because he had been living in the home for at least ten months when the contractual limitations period expired.

II. ISSUES

We consolidate and restate the issues raised on appeal by plaintiff as follows:

A. Whether the agreement was an unenforceable contract of adhesion.

B. Whether the agreement was void as against public policy.

C. Whether the trial court erred in granting summary judgment based on plaintiff’s failure to file this lawsuit within one year from the date of the home inspection.

1 At the trial court level, plaintiff disputed that he signed the subject agreement, admitting that he signed something that day but did not know what it was. Defendant presented the original agreement as an exhibit, and testified that it was the document that plaintiff signed. The court was given examples of plaintiff’s signature on other documents. The court ultimately found that plaintiff signed the agreement and that defendant’s testimony regarding plaintiff’s signature on said document was more credible. Plaintiff has not appealed that finding.

-2- III. STANDARD OF REVIEW

A grant of summary judgment is not presumed correct by this court; rather, this court must “make a fresh determination” in each case that the requirements of Tenn. R. Civ. P. 56 have been satisfied. Watson v. Waters, 375 S.W.3d 282, 291 (Tenn. Ct. App. 2012). In doing so, this court must consider the evidence in the light most favorable to the non-movant and draw all reasonable inferences in his favor. Id.

As this court has previously explained:

The interpretation and construction of a plain and unambiguous written contract is a question of law for determination by the court. It is the duty of the court to enforce the contract according to its plain terms, and the language used in the contract must be taken and understood in its plain, ordinary and popular sense. However, “the cardinal rule for interpretation of contracts is to ascertain the intention of the parties and to give effect to that intention as best can be done consistent with legal principles.” Courts may determine the intention of the parties “by a fair construction of the terms and provisions of the contract, by the subject matter to which it has reference, by the circumstances of the particular transaction giving rise to the question, and by the construction placed on the agreement by the parties in carrying out its terms.”

BFS Retail and Commercial Operations LLC v. Smith, 232 S.W.3d 756, 758 (Tenn. Ct. App. 2007) (citations omitted).

IV. DISCUSSION

A.

Plaintiff argues that the agreement at issue was an unenforceable contract of adhesion because it contains unconscionable and oppressive terms. Plaintiff notes that the contract provided that if he failed to notify defendant of adverse conditions within 14 days of discovery, defendant would be released from all liability. Plaintiff also notes that the contract provided that if defendant was negligent, his damages were limited to the amount of the inspection fee. Plaintiff asserts that the language limiting his time for bringing a claim to one year from the date of the inspection was unconscionable and oppressive.

An adhesion contract has been defined as:

-3- a standardized contract form offered to consumers of goods and services on essentially a ‘take it or leave it’ basis, without affording the consumer a realistic opportunity to bargain and under such conditions that the consumer cannot obtain the desired product or service except by acquiescing to the form of the contract . . .. Courts generally agree that ‘[t]he distinctive feature of a contract of adhesion is that the weaker party has no realistic choice as to its terms.’

Buraczynski v. Eyring, 919 S.W.2d 314, 320 (Tenn. 1996) (citations omitted). The agreement at issue in this case is a standard form contract that leaves the consumer with little or no choice as to its terms. However, plaintiff did not prove that defendant would not have performed the service if he did not sign the contract. Plaintiff also did not question the terms of the agreement and was not told that he had to sign it to procure the home inspection. Further, he could have sought the service from another provider if he did not agree to the terms of the agreement. As such, the contract is not an adhesion contract. See, e.g., Pyburn v. Bill Heard Chevrolet, 63 S.W.3d 351, 359-360 (Tenn. Ct. App. 2001) (holding that the contract was not an adhesion contract where plaintiff was not required to sign the document, when there was no evidence that plaintiff questioned defendant about the contents of the document, and when plaintiff could have bought a van elsewhere if he did not want to sign the contract); Estate of Mooring v. Kindred Nursing Centers, No. W2007-02875-COA-R3- CV, 2009 WL 130184, *5(Tenn. Ct. App. Jan.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arlie "Max" Watson v. Larry Waters
375 S.W.3d 282 (Court of Appeals of Tennessee, 2012)
James Fortune v. Unum Life Insurance Company of America
360 S.W.3d 390 (Court of Appeals of Tennessee, 2010)
Russell v. Bray
116 S.W.3d 1 (Court of Appeals of Tennessee, 2003)
Pyburn v. Bill Heard Chevrolet
63 S.W.3d 351 (Court of Appeals of Tennessee, 2001)
Olson v. Molzen
558 S.W.2d 429 (Tennessee Supreme Court, 1977)
BFS Retail & Commercial Operations, LLC v. Smith
232 S.W.3d 756 (Court of Appeals of Tennessee, 2007)
Carey v. Merritt
148 S.W.3d 912 (Court of Appeals of Tennessee, 2004)
Crawford v. Buckner
839 S.W.2d 754 (Tennessee Supreme Court, 1992)
Buraczynski v. Eyring
919 S.W.2d 314 (Tennessee Supreme Court, 1996)
Hill v. Home Ins. Co.
125 S.W.2d 189 (Court of Appeals of Tennessee, 1938)
Das v. State Farm Fire & Casualty Co.
713 S.W.2d 318 (Court of Appeals of Tennessee, 1986)
Guthrie v. Indemnity Ass'n
49 S.W. 829 (Tennessee Supreme Court, 1899)
State v. Evans
334 S.W.2d 337 (Court of Appeals of Tennessee, 1959)
Tullahoma Concrete Pipe Co. v. T. E. Gillespie Construction Co.
405 S.W.2d 657 (Court of Appeals of Tennessee, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
David Desgro v. Paul Pack d/b/a Resi Chek, Counsel Stack Legal Research, https://law.counselstack.com/opinion/david-desgro-v-paul-pack-dba-resi-chek-tennctapp-2013.